Loading...
20-007.02 WM Winkler: CenterPlace West Lawn Phase 2 CITY(W \ Spokane Valley CHANGE ORDER NO: 2 ENGINEERING DIVISION CONSTRUCTION CONTRACT NO: 20-007► 4� PROJECT: CenterPlace West Lawn-Phase II CONTRACT DATE: 1/15/2020 PRIME CONTRACTOR: Wm. Winkler CIP NO: 304 DESCRIPTION OF CHANGES Add concrete base and electrical/lighting for"Rockstar"art sculpture #2 . Extend contract duration due to Covid-19 owner and contractor procurement delays(non-compensable) Item No. Description Unit Quantity Unit Price Total ONSITE-SCHEDULE A CO-2.1 Add Rockstar Sculpture(#2)base with electrical/lighting. $ 6,538.32 8.9% Sales Tax $ 581.91 Total Schedule A $ 7,120.23 Total Amount of this Change Order(incl. Tax): $ 7,120.23 VERBAL APPROVAL AND JUSTIFICATION Independent Justification on File Yes Verbal Approval 4/22/2020 Verbal Approval by Glenn Ritter PHYSICAL COMPLETION Original Contract Working Days: 50 Revision By This Change Order: 28 Revisions by Prior Change Orders: 4 Total Revised Contract Working Days: 82 CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT $ 1,326,030.55 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through CO#1) $ 27,902.56 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 1,353,933.11 NET THIS CHANGE ORDER $ 7,120.23 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 1,361,053.34 CONTRACTOR ACCEPTANCE: DATE: '7 — 2c? 2 [I The contractor hereby accepts this adju, i%entu der the terms of Section 1-04.4 of the original contract. RECOMMENDED BY: DATE: 7/30/20 �� c agar APPROVED BY: DATE: , g.0,3•ZGZ6 Cit gineer Nvi) , APPROVED BY: fr" " _ DATE: 6 City Manager ATTACHMENTS: Change Proposal #4 Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor,PW Project File, Project Inspector,Finance Department \1111111114k Community& Public Works Department Spokane Engineering Division Valley 10210 E Sprague Ave ♦ Spokane Valley WA 99206 509.720.5075 ♦ Fax: 509.720.5075 ♦ cityhall@spokanevalley.org Change Order Memorandum Date: 7/30/20 To: Bill Helbig, City Engineer From: Glenn Ritter, Senior Engineer- Through: Gloria Mantz, Engineering Manager Re: Change Order#2 for CenterPlace West Lawn, CIP#0304 Budget Account No. 309.000.304.594.75.63.00 Wm. Winkler Co. Contract No. 20-007 This change order pays for the installation of the second art sculpture called "Rockstar" as directed by the City Council. It also extends the contract duration by 28 working days to account for City and Contractor procurement delays as a result of Covid-19. This is a non-compensable extension of time. The total cost (including sales tax) for this Change Order work is $7,120.23 paid for by City of Spokane Valley. There are sufficient funds in the project budget to cover these costs. Original Contract Amount: $1,326,030.55 Previous Change Order Cost: $27,902.56 Change Order#2 Cost: 7,120.23 Project Cost including Change Order#2: $1,361,053.34 City Engineer's Contract authority: $5,000.00 ($5,000) Change Order Cost to date: $0.00 Remaining City Engineer's Contract Authority after CO #2 $5,000.00 City Manager's Contract authority: $198,904.58 ($200,000.00 or 15% of contract amount) Change Order Cost to date: $35,022.79 Remaining City Manager's Contract Authority after CO #2 $163,881.79 cc: Finance Department Clerk's office __ Contractor License Numbers: 1 WM. WIik114.�_ER rn . WA: WMWINC'�935LA ID: 10110-UNLIMITED 1-2-4 err; - 000NCRETE CONTRACTOR OR: 193844 Since 1919 MT: 53384 PO Box 430 5516 N. Starr RD Newman Lake,WA 99025 509-489-6100 Fax:509-484-0646 To: City Of Spokane Valley Contact: Address: 11707 E.Sprague Phone: (509)921-1000 Spokane Valley,WA 99206 Fax: (509)921-1008 Project Name: CenterPlace West Lawn-Phase II Bid Number: 2019-798 Project Location: Bid Date: 4/29/2020 Item# Item Description Estimated Quantity Unit Unit Price Total Price CHNAGE PROPOSAL 04 01 ADD Rockstar Sculpture Foundation&Lighting 1.00 LS $6,538.32 $6,538.32 Subtotal for above CHNAGE PROPOSAL 04 Items: $6,538.32 WSST 8.90%: $581.91 Total Price for above CHNAGE PROPOSAL 04 Items: $7,120.23 Notes: • Install of Sculpture by Others. ACCEPTED: CONFIRMED: The above prices,specifications and conditions are satisfactory Wm.Winkler Company and hereby accepted. Buyer: Signature: Authorized Signature: Date of Acceptance: Estimator: Bill Kling (509)489-6100 bkling@wmwinkler.com 6/17/2020 11:05:56 AM Page 1 of 1 f fjtooktt� V .i (JII EF,�- AAAA;'�`� Contractor License Numbers: 4*A WM. JK w WA: WMWINC*935LA ID: 10110-UNLIMITED 1-2-4 e,'4'AirEO'' CONCRETE CONTRACTOR OR: 193844 Since 1919 MT: 53384 PO Box 430 5516 N. Starr RD Newman Lake,WA 99025 509-489-6100 Fax:509-484-0646 Cost Detail With Man Hours By Phase Project Name: CenterPlace West Lawn-Phase I1 Customer: City Of Spokane Valley Job Number: 20001-10 Bid Number: 2019-798 Billing Address: 11707 E.Sprague Bid As: Prime Spokane Valley,WA 99206 Estimator: Bill Kling Phone: (509)921-1000 Project Address: Contact: Completion Date: Pay Items Man Man Hours Unit Total Description Quantity UM Hours per Unit Direct Cost Direct Cost Phase: CHANGE PROPOSAL-ADD Rockstar Sulpture Foundation & Lighting D• 0i-ADD Rockstar Sculpture Foundation& 1.00 LS 5.00 5.00 $6,007.60 $6,007.60 Lighting 0 Ex.&Badcflf-Rodcstar Sculpture Base 1.00 EACH 4.00 4.00 $873.66 $873.66 „V Subgrade Prep Crew(0.50 EACH/PH,0.20 DY) 1.00 EACH 4.00 4.00 $323.66 $323.66 .;b? 308 Excavator 2.00 HR $49.74 $99.48 • Excavator Operator 2.00 HR $55.34 $110.67 .;d). F450 Crew Pickups[0.25] 2.00 HR $20.00 $10.00 • Laborer 2.00 HR $51.75 $103.51 re,') Pre-Cast Concrete Footing/Pedestal- Reuse 1.00 EACH $550.00 $550.00 ®* Drill&Epoxy Anchor Bolts 1.00 LS 1.00 1.00 $118.52 $118.52 ,](j' Drill&Epoxy Anchor Bolts(10.00 LS/DY,0.10 1.00 LS 1.00 1.00 $53.77 $53.77 DY) • Laborer 1.00 HR $53.77 $53.77 Buy Epoxy 1.00 LS $64.75 $64.75 Q Electrical(SUB) (Colvico) 1.00 LS $5,015.43 $5,015.43 Q Landscape And Irrigation(SUB) (Dew Drop 1.00 LS $0.00 $0.00 Sprinklers And Landscaping) Indirect Items Man Man Hours Unit Total Description Quantity UM Hours per Unit Indirect Cost Indirect Cost D I001-Lunch 0.00 LS 0.00 0.00 $0.00 $0.00 5/29/2020 3:49:32 PM Page 1 of 2 Direct Cost Totals Percent of Amount Direct Cost Labor: $267.94 4.46% Equipment Owned: $109.48 1.82% Equipment Rented: $0.00 0.00% Materials Owned: $0.00 0.00% Materials Purchased: $550.00 9.16% Subcontracted: $5,015.43 83.48% Trucking Owned: $0.00 0.00% Trucking Hired: $0.00 0.00% Miscellaneous: $64.75 1.08% Plug: $0.00 0.00% Direct Cost: $6,007.60 Pay Item Summary Percent of Amount Bid Price Total Direct Cost: $6,007.60 91.88% Total DC Adds/Cuts: $0.00 0.00% Total Indirect Cost: $0.00 0.00% Total Bond: $0.00 0.00% Total Overall Cost: $6,007.60 91.88% Total Overhead: $99.22 1.52% Total Profit: $431.50 6.60% Total Margin: $530.72 8.12% Total Bid Price: $6,538.32 5/29/2020 3:49:32 PM CenterPlace West Lawn-Phase II Page 2 of 2 i = fl=lie IN 1‘.:Vr 7'1 = Cium;I II•.1 i j 1 _1 [ PO BOX 2682•SPOKANE, WA 99220 • 509-536-1875 - COLVII*134D6 JOB NAME: Centerpiece Lawn Install New Light Fixtures For Sculpture 5/27/2020 ITEM QTY. UNIT PR. ,EXT. PR. LABOR 1 EXT. LABOR 8" X 12" TUBE 3 $ 5.00 $ 15.00 3 9 CONCRETE 0.5 $ 130.00 $ 65.00 1 0.5_ CONCRETE SHORT LOAD 1 $ 200.00 $ 200.00 0 ROUGHIN STAKE 3 $ - 1 3 1" SCHEDULE 80 CONDUIT 100 $ 0.50 $ 50.00 0.02 2 1" SCHEDULE 80 ELBOWS 8 $ 2.85 $ 22.80 0.1 0.8 1" COUPLINGS 16 $ 0.25 $ 4.00 0 1" MALE ADAPTORS 3 $ 1.50 $ 4.50 0 DITCH LABOR 70 $ 3.50 $ 245.00 0.03 2.1 HAUL DITCH/POLES 2 $ 10.00 $ 20.00 0.5 1 SAND 2 $ 9.00 $ 18.00 0.3 0.6 LIGHT FIXTURES QUOTE 3 $ 351.00 1 $ 1,053.00 0 INSTALL LIGHT FIXTURS 3 $ - 1 3 $ - 0 #10 350 $ 0.29 $ 101.85 0.008 2.8 $ - 0 TYPE 1 JUNCTION NON SLIP 1 $ 385.00 $ 385.00 1.5 1.5 $ - 0 MATERIAL SUBTOTAL $ 2,184.15 0 TAX 8.90% $ 194.39 MATERIAL TOTAL $ 2,378.54 MATERIAL M/U 21% $ 499.49 HRS 26.3 MATERIAL TOTAL $ 2,878.03_ PER HR $63.00 LABOR SUBTOTAL $ 1,656.90 LABOR M/U 29% $ 480.50 LABOR TOTAL $2,137.40 JOB TOTAL $ 5,015.43 amerlux \fa r i et a A Delta Group Company Single Array Features The Amerlux Varieta flood luminaire employs solid state technology and preci- LED Flood Light sion engineering to provide LED solutions for exterior signage,wall washing,and landscape layouts.All components are encapsulated inside a single attractive enclosure designed for superior performance in weather resistant applications. Offered in a choice of finishes,and color temperatures,three mounting options and glare shield are also available. 111, Product Overview Type: Exterior Flood Lighting Wattage: 31W Lumen Output: 3,170 Im Color Temp: 3000K,4000K,5000K Dimming: 0-10V PROJECT: TYPE: Application: Mounting Accessories: Exterior flood lighting for signage,wall •GSP17-Ground Stake washing,and landscape layouts. •PMBS-2-18-Pole Mount 14 6/' *1 •WMS14-Wall Mount Construction: •Extruded aluminum housing •EGS-External Glare Shield •IP67 sealed optical module I si •Die-cast aluminum faceplate Accessories: Finish: Optics: Premium quality thermoset polyester •Lumen maintenance:70%@ 60,000 powdercoat for a durable finish. r hours •1 lens module containing 16 LEDs Ambient Operating Range: available in a number of symmetric or -30°C to 40°C 4 w."_ asymmetric axial beam spread patterns Weight: I. 5 lbs EPA: 0.25 Electrical: •Integral driver •Input voltage 120V-277V auto- sensing •Power consumption 31W •1/2°NPT wire entry •0-10V dimming is standard ETL listed,suitable for wet locations. Mounting: •Oast aluminum pivot •180°tilt,360°rotation [�, year limited POWDER ` A O. warranty ,..,TOUGH' � %1L-, > LIT-E00028.01/21/20•Page 1 of 6 Amerlux reserves the right to change details that do not affect overall function and performance. Amerlux•,LLC•178 Bauer Drive.Oakland,NJ 07438•P.973-882-6010 F:973-882-2606•amerlux.com Subject: 0304 CenterPlace Importance: High Good morning Bill, Please see below for the approximate location of our proposed art sculpture#2, "Rockstar!" 2 RM (r-%—bel ` ' A5 h 'V.��„r,: cle 00Qo00 1 Sf 3 K. B in . _..4. .a,Qao / f' g tHt; SHEET Mr BG y '. NT 3 '? %3,` ' ' h Al I Proposed Rockstar' fi r y ` •ti e Art Sculpture on u? . 44� , 40 ee '4110 .01._.. �'"IP round concrete base �'�� z ''� r1,11 {iy=g;s . fro. g4t RN Apr.`. ,';,. 20 „�t :tic gig' a i ra+� it -r2 4 1#� 4 RN 20�A ET , 5 ,,. 13 „Hirt iidiNg.e. ' ': I� (PH2\ The City Council just decided that it is, in fact,going to be located in the West Lawn area. As we discussed, please put together a rough estimate by Monday afternoon for additional work as follows: • 3' diameter x 5' deep pre-cast concrete base, 12" above grade, bevel on top. • Mounting of art sculpture, similar to art sculpture#1. • "Design" and installation of 3 uplights, similar to sculpture#1. We anticipate the sculpture to be delivered to CenterPlace on Wednesday, so we will know more about how this one is to be mounted so you can finalize your proposal. We wanted to be sure to get this in front of you and your crews ASAP, so that you could plan for it. We are unsure about the requirement for new electrical conduit, so please ask Colvico ASAP?We also expect that some shrubs will need to be located slightly differently than shown in order to make room for the base. Again,we are looking for a very similar installation as the current art sculpture#1. Thanks for your help and please do not hesitate to contact me with any questions. Glenn Glenn Ritter,PE I Senior Engineer 10210 E.Sprague Avenue I Spokane Valley,WA 99206 (509)720-5018 I gritter@sookanevallev.org In a Val This email and any attachments may be subject to disclosure pursuant to Washington State's Public Record Act,chapter 42.56 RCW. 2 Bill Kling From: Brendan Bemis <brendan@dewdropnw.com> Sent: Tuesday, May 19, 2020 7:57 AM To: Bill Kling Cc: Skye Baker Subject: RE:0304 CenterPlace No impacts for landscape. We will adjust shrubs around sculpture. No irrigation lines to be relocated either. One issue to consider: there is overhead spray irrigation in that area. Can the sculpture get wet? Thanks, Brendan Bemis Dew Drop Sprinklers & Landscape Spokane,WA 0: 509.922.7168 C: 509.499.5826 brendan@dewdropnw.com From: Bill Kling<bkling@wmwinkler.com> Sent: Monday, May 18, 2020 3:24 PM To: Brad Henriksen <bhenriksen@wmwinkler.com>;Skye Baker<sbaker@wmwinkler.com> Cc: Brendan Bemis<brendan@dewdropnw.com>;Tom Baldwin<tbaldwin@colvicoinc.com> Subject: FW: 0304 CenterPlace Importance: High Just a heads up that the City has asked us to work with them on pricing the below outside of the Architect and Engineer. Looking for"budget" numbers from anyone impacted tomorrow morning. Thanks, Bill Kling I Wm. Winkler Co. P.O. Box 430 15516 N.Starr Rd I Newman Lake,WA 99025 Phone:509-489-6100 I Mobile:208-818-2408 I Fax:509-484-0646 bkling@wmwinkler.com I www.wmwinkler.com ` tiKL • 1919 1Q 12020 okANE From:Glenn Ritter<gritter@spokanevalley.org> Sent:Saturday, May 16, 2020 7:19 AM To: Bill Kling<bkling@wmwinkler.com> Cc:Chris J. Winkler<chris@wmwinkler.com>; Skye Baker<sbaker@wmwinkler.com>; Mike Stone <mstone@spokanevalley.org>; Don Hesse<dhesse@spokanevalley.org> 1