20-073.01 Avista: Barker/BNSF GSP Facilities Relocation DocuSign Envelope ID: 79AEE753-2D87-4948-B6FO-CA1DC4694F03
First Amendment to
Utility Construction Agreement
This First Amendment ("Amendment") to the Utility Construction Agreement, Agreement No. R-43107
("Construction Agreement") is entered into between the City of Spokane Valley ("Local Agency") and
Avista Corporation, a Washington corporation("Utility"), as of April 6,2021. In the event of any conflict
between the Construction Agreement and this Amendment,this Amendment shall control.
Exhibit A to the Construction Agreement is hereby deleted in full and is replaced with the attached
Amended Exhibit A. Based upon this substitution, the Parties mutually recognize and agree that the
Agreement Amount is revised to: $910,907.22.
Except as modified by this Amendment, all of the terms and conditions of the Construction Agreement
shall remain in full force and effect.
IN WITNESS WHEREOF, the parties have executed this Amendment to the Construction Agreement on
the date set forth above.
City of Spokane Valley: Avista Corporation:
l(/F r—DocuSigned by:
BY: Y V,�/l� BY: 4jL„<-
(Signatur ) (Sipatuse2)iAA65D6E64F6...
Mark O I Heather Rosentrater
(Printed Name) (Printed Name)
/V r Sr.VP Energy Delivery
(Title) / (Title)
7124 ` Apr-16-2021 I 1:31 PM PDT
(Date Signed) /// (Date Signed)
First Amendment to Utility Construction Agreement- 1
DocuSign Envelope ID:79AEE753-2D87-4948-B6FO-CA1DC4694F03
AMENDED EXHIBIT A
Transmission Project Cost Estimate Actual Variance
Materials: (3) Self Supporting Steel Structures @ $50,000 $150,000 $212,018 $62,018
each
(2) Direct Embed Steel Poles @ $8,000 each $16,000 $20,672 $4,672
(9) Post Insulators with Clamps @ $1000 each $9,000 $1,734 ($7,266)
(21) Toughened Glass Insulators with Clamps @ $3,150 $2,838
$150 each ($312)
3000ft. "Drake"ACSS Conductor @ $3.00/ft. $9,000 $19,284 $10,284
Miscellaneous Materials (lump sum) $15,000 $18,664 $3,664
TOTAL MATERIALS: $202,150 $275,210 $73,060
Construction: (3) Drilled Pier Foundations @ $50,000 each $150,000 $168,513 $18,513
(2) Direct Embed Foundations @ $10,000 $20,000 $28,780 $8,780
Construction Materials (lump sum) $25,000 $3,033 ($21,967)
Traffic Control (lump sum) $5,000 $1,583 ($3,417)
TOTAL CONSTRUCTION: $200,000 $201,909 $1,909
Construction Structures: (15) Crew-Days @ $5,000 /day $75,000 $104,521 $29,521
Labor:
TOTAL CONSTRUCTION LABOR: $75,000 $104,521 $29,521
Totals: TOTAL (Materials and Construction): $477,150 $581,640 $104,490
TOTAL (Taxes, A&G, and PM @ 20%): $95,800 $90,530 ($5,270)
TOTAL COST (Transmission): $572,950 $672,170 $99,220
Estimate Actual Variance
Electric Distribution Project: $102,438.82 $165,133.41 $62,700.59
Fiber Relocation Project: $60,000.00 $60,000.001 $0
Natural Gas Relocation Project: $13,603.81 $13,603.812 $0
TOTAL PROJECT COST: $748,992.63 $910,907.22 $161,914.59
1 Avista is not seeking recovery of overage related to Fiber Relocation.
2 Work on the Natural Gas Relocation Project has not yet commenced;Avista reserves the right to request overage
from the City for Gas Relocation expenses.
First Amendment to Utility Construction Agreement-2