23-039.09NorthForkEnterprisesSullivanRdImprovements CHANGE ORDER NO: 9
ENGINEERING DIVISION CONSTRUCTION CONTRACT NO: 23-039
PROJECT: Sullivan Rd Improvements CONTRACT DATE: 4/25/2023
PRIME CONTRACTOR: North Fork Enterprises CIP NO: 320
DESCRIPTION OF CHANGES
Landscaping at a parcel 45231.3605 as called out on the plans and directed during construction.
m No. Description Unit Quantity Unit Price Dig
C09.1 Landscaping Revision LS 1 $6,660.00 6,660.00
Sales Tax $ N/A
Total Amount of this Change Order(incl.Tax): $ 6,660.00
VERBAL APPROVAL AND JUSTIFICATION
Independent Justification on File Yes
Verbal Approval_ Yes Verbal Approval by KL
PHYSICAL COMPLETION
Original Contract Working Days: 100 _ Revision By This Change Order:
Revisions by Prior Change Orders:_ 4.5 Total Revised Contract Working Days: _104.5
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 3,820,971.36
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 36,991.04
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 3,857,962.40
NET THIS CHANGE ORDER $ 6,660.00
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 3,864,622.40
CONTRACTOR ACCEPTANCE: WA---4-44.IC/ ��I. -� DATE: ''i 1/2_b2_3
The contractor hereby accepts this adjustment under the terms of Section 1-04.4 of the original contract.RECOMMENDED BY: -7Mf
DATE: Z"/if 7-3 raj a
APPROVED BY: ` DATE: /? . 2. Z�
City Engi er
APPROVED BY: N/A DATE:
City Manager
ATTACHMENTS:
Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department