09-159.00 Knife River: Broadway Rehab Ph 2svdQne
galley
Federal Aid Project No.: STPUS - 3846(006)
CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 09 - 036
PROJECT: Broadway Rehabilitation Project- Phase 2 CONTRACT DATE: 7131/2009
CONTRACTOR: Hap Taylor & Sons Inc dbaXnife River CHANGE ORDER NO: 3
CAPITAL IMPROVEMENT PROJECT NO: 0088
This Change Order credits the City for the savings from not galvanizing 60 LF of casing pipe. The galvanizing requirement was
waived to allow Installation when the Union Pacific Railroad removed the existing RR crossing at Lake Rd and Broadway Ave.
Item No Description Unit Quantity Unit Price Total
51 Galvanizing credit LS 1 ($341.04) ($341.04)
Total Amount of this Change Order( Incl. Tax): ($341.04)
SUBSTANTIAL COMPLETION
Original Date:
9/14/2009
Prior to this Change Order:
9/140009
Including this Change Order:
9/14/2009
Nglnal Working Days:
27
Working Days Added by this CO:
0
Working Days Including this CO:
2 7
CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT PRICE:
ORIGINAL TOTAL CONTRACT AMOUNT, $,
_. _-................. ..._._.._..- ._- ._......._....._ . _......- .._......- _......._.
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT _,,,__, , ...... .. ....._- ._._..... _..-.__.......-
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER 5 _
NET THIS CHANGE ORDER _ - .....__,..__....._.__--.�..__. ...... .....$ - 341.04
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 518,435.71
CONTRACTOR ACCEPTANCE: �. - 7 DATE:
The contractor hereby accepts this adjustment under the terms of the original contract for all work perfomed.
RECOMMENDEDB �44 DATE: O
APPROVED BY: L
DATE: (
APPROVED BY: A A & DATE:
DaNd Morcier, City Manager
ATTACHMENTS:
Dlslrlbullon:
ORIGINALS TO: Contractor, City of Spokane Valley Clarks Office, PW Project File
COPIES TO: PW Project File P:Pabrc W0rks1PmrJ1a'!ng1C0 (g/2612007)
Coq- 169
Public Works Department
Capital Improvement Program
11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206
509.921.1000 ♦ Fax: 509.921.1008 ♦ cityhall ®spokanevalley.org
Memorandum
Date: October 6, 2009
To: Steve Worley, Neil Karsten
From: Craig Aldworth
Re: Change Order 3 for Broadway Rehab 2 Project,
CIP 0066
Budget Account No. 303.303.0066.595.30.63.00 Acme Concrete Paving Contract 09 -036
Change Order 3 takes a credit from the contractor for not galvanizing a six inch diameter casing
pipe installed under the Union Pacific Railroad spur line on Broadway Avenue on the west side
of the Lake Road intersection. The Contractor claimed that galvanizing the casing would delay
installation of the casing by a week. The work was scheduled to be done after the railroad
removed the existing crossing and before it installed a concrete plank crossing. The galvanizing
was not required by the railroad so it was waived in exchange for a credit. The cost of the credit
is based on the attached quote from Spokane Galvanizing
The total estimated cost (incl. tax) for this Change Order work is - $341.04, paid for by an 80.0%
STA grant and the City of Spokane Valley. There are sufficient funds in the project budget to
cover these costs.
Original Contract amount = 1 $508,306.75
Previous Change Order Cost = $10,470.00
Change Order #3 Cost = 341.04
Project Cost including Change Order #3 = $518,435.71
15% of Original Contract amount = $77,794.01
Max Public Works Director Contract authority = $75,000.00
Change Order Cost to date = $10,128.96
Remaining P.W. Director Contract Authority after CO #3 $64,871.04
Public WorkZero
r
Cc: Deputy City
Finance Department
Project anager
IIDG quote
Craig Aldworth
Page 1 of 1
From: Craig Aldworth
Sent: Thursday, September 24, 2009 10:54 AM
To: 'Waldo, Dustin'
Cc: 'Carey Hagen'
Subject: FW: HDG quote
Dustin:
I will use the attached $341.04 quote from Spokane Galvanizing for the credit on Item 41 Galy. Steel Casing Pipe,
6 In. Diem.
Craig
From: Dick Lang [ mailto :DLang @spokanegalvanizing.com]
Sent: Thursday, September 24, 2009 10:17 AM
To: Craig Aldworth
Subject: HDG quote
Hi Craig, the cost to Hot Dip Galvanize 3 -pcs of 6" sch.40 pipe x 20' will be .28 cents per pound. Book weight is
1138#s,add approx. 7% for zinc pick up weight.Price is based on finished weight.1138#s plus 7% = 1218 #s x.28
cents = $341.04
Thanks for contacting Spokane Galvanizing. Inc.