09-168.00 Inland Asphalt: Sprague Ave Rehab Ph 1r
Washington State Change Order 6
Department of Transportation
Date September 30. 2009
e 1 of
Contract Number 09 -031 Federal Aid Number ARRA -3840 (008)
Contract Title Sprague Avenue Rehabilitation Project #1
Change Order Number 6
Prime Contractor Inland Asphalt Co.
Ordered by Engineer under the terms of Section 1 -04.4 of the Standard Specifications
❑ Proposed by Contractor
Endo ed By
c
Contra r
Surety Consent
Attomey of Fact
Original Contract Amount $ 2,256,393.18
Current Contract Amount
Estimated Net Change This Change
rrzlera
17, 921.52
Estimated Contract Total After Change $ 2,345,908.92
Approval Required Region ❑ Olympia Service Center R Local Agency
If the amount authorized in the Local Agency Agreement is exceeded and federal funds are not available for this
change, the Local Agency will assume the total cost of this Change Order.
X Appro Recommen ed ❑Approved
Approved
Project Engineer //
��/�
Approving Authority per C.A. Agreement
lO -Jd —o7
Date
Date
❑ Approval Recommended ❑Approved
Approved
By
Approving Authority per C.A. Agreement
Date
Date
Cog -14
CHANGE ORDER
Page 2 of 3
Contract No: 09 -031 Change Order No. 6
This Contract is revised as follows:
Description of Work
During asphalt grinding operations on the Sprague Avenue Project areas of inadequate
asphalt thickness were encountered. The project specified that 2.5 inches of asphalt be
removed with a grinder and replaced with 2.5" of Hot Mix Asphalt. Existing areas along
Sprague Avenue had only 2 to 2.5 inches of existing asphalt. Grinding operations in
these areas completely removed all existing asphalt. Existing material in these areas
will need to be removed and reconstructed with crushed surfacing and or asphalt. Two
(2) Working Days will be added to the contract.
1) PAVEMENT REPLACEMENT CSTC /3.5" HMA - Pavement replacement in the
outside eastbound lane between Bowdish Road and Pines Road will be replaced
with crushed surfacing and 3.5 inches of Asphalt. Existing material will be
removed and hauled off.
2) PAVEMENT REPLACEMENT 2.5" HMA - Pavement patching in the center turn
lane and other areas along Sprague Avenue between University Road and
Bowdish Road that were discovered during grinding operations will be paved with
2.5 inches of asphalt. Existing material will be removed and hauled off.
3) PAVEMENT REPLACEMENT MISC AREAS - Pavement patching in
miscellaneous areas along Sprague Avenue between Pines Road and Evergreen
Road that were discovered during grinding operations will be paved with 2.0
inches of asphalt. Existing material will be removed and hauled off.
Materials
The Materials shall meet the requirements of the 2008 Standard Specifications.
Construction Requirements
Work shall meet the requirements of the 2008 Standard Specifications and the special
provisions.
Measurement
"PAVEMENT REPLACEMENT CSTC /3.5" HMA ", PER SQUARE YARD
"PAVEMENT REPLACEMENT 2.5" HMA ", PER SQUARE YARD
"PAVEMENT REPLACEMENT MISC AREAS ", PER SQUARE YARD
Payment
"PAVEMENT REPLACEMENT CSTC /3.5" HMA ", PER SQUARE YARD
"PAVEMENT REPLACEMENT 2.5" HMA ", PER SQUARE YARD
"PAVEMENT REPLACEMENT MISC AREAS ", PER SQUARE YARD
i�
CHANGE ORDER
Page 3 of 3
Contract No: 09 -031
Change Order No. 6
Item Item Description
Unit
Unit Price
Est. Qty.
Est. Amt.
No.
Measure
Change
Change
PAVEMENT REPLACEMENT CSTC /3.5' HMA
SY
$35.75
1706.30
$61,000.23
PAVEMENT REPLACEMENT 2.5" HMA
SY
$39.20
939.60
$36,832.32
PAVEMENT REPLACEMENT MISC AREAS
SY
$30.75
653.30
$20,088.98
(PRICES INCLUDE MARKUP)
TOTAL
$117,921.53