09-192.00 Acme Concrete: Sprague & Pines PCCP IntersectionS#6Q e ,; CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 09 -024 AU SpraguelPlnes PCCP Intersection Project CONTRACT DATE: 4124/2009 IMPROVEMENT PROJECT NO: 0103 This Change Order grants two additional working days for unforeseen conditions detailed in the attached Acme June 19, 2009 Itr. By signing this change order Acme waives all other project claims Including "loss of production" or delay chins. Original Date: 6/22/2009 Prior to this Change Order: 6122/2009 Including this Change Order: Vorkino Dava: 30 Working Dave Added by this C 2 Working Days Including this CO: CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT PRICE: ORIGINAL CONTRACT AMOUNT .... .. ...... ___._ ...... _.____....._._._..._.......... _._ ........ ._.___._ .................__.__. $ _ $634,428. TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT 44,663 _ .................... ................ ... ..........__ ........._.._...........__ _ TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER „•• $„ 676,991. NET THIS CHANGE ORDER. 0• .. .._. . v................._........_. - ...,._._._..._......._.. __ TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER 678,991 • This change order add92 days to contract time. CONTRACTOR ACCEPTANCE: i DATE: -vrz The contractor hereby accepts this adjusVn u erthei o r atcontractforallworkperromed. RECOMMENDED BY: 4 DATE: [o •7� •Q 7 n APPROVED BY: APPROVED BY: DATE: David Merder, C11" aneger ATTACHMENTS: Dlstdbullon: ORIGINALS TO: Contractor, City of Spokane Valley Clerk's Office, PW Project File COPI TO PW Project File P'PutlIe WcAsipurchengleo --- ------ 0.179' (CZ F TyM Concrete Paving, Inc. June 19, 2009 City of Spokane Valley 11707 E Sprague Ave Suite 106 Spokane Valley, WA 99206 Attn: Craig Aldworth, P.E. Re: Sprague and Pines Rd PCCP Intersection Project . Capital Improvement Project No..0103 Additional Work .Days.. :' Dear Mr. Aldworth . During installation of underground drainage structures on the above referenced project, specifically the Phase 3, southern portion, Woodard Construction encountered "unforeseen conditions" causing delay. With this correspondence Acme Concrete Paving is respectfully requesting three (3) additional contract days. Unforeseen Conditions causing delay include: • Utility conflicts requiring time consuming re- routing analysis / approval • Structure additions and Pipe materials substitution • Additional / Parallel piping materials and structure accessing • Repair of existing underground drainage structure and pipe (Drywell / CDF in SW approach) • Phase 3 continuation of the project wide over - excavation and CSTC installation If you have any questions, please contact me at 509- 242 -1234. ate Project Manager 4124 East Broadway, Spokane, WA 99202 • (509) 242 -1234 • FAX (509) 242 -1232 An Equal Opportunity Employer ne In Public Works Department Capital Improvement Program Valley® 11707 E Sprague Ave Suite 106 4 Spokane Valley WA 99206 509.921.1000 ♦ Fax: 509.921.1008 ♦ cityhati@spokanevalley.org Memorandum Date: June 30, 2009 To: Steve Worley, Neil Karsten From: Craig Aldworth Re: Change Order 7 for Sprague Pines PCCP Intersection Project, CIP 0103 Budget Account No. 303.303.0103.595.30.63.00 Acme Concrete Paving Contract 09 -024 This Change Order grants two additional working days for over - excavation and additional storm drainage work. Total estimated cost (incl. tax) for this Change Order work is $0.00, paid for by an 79.5% STA grant and the City of Spokane Valley. There are sufficient funds in the project budget to cover these costs. The Change order adds 2 days to the Contract time. Original Contract amount = $634,428.25 Previous Change Order Cost = $44,563.45 Change Order 97 Cost = $0.00 Project Cost including Change Order #7 = $678,991.70 15% of Original Contract amount = $95,164.24 Max Public Works Director Contract authority = $75,000.00 Change Order Cost to date = $44,563.45 Remaining P.W. Director Contract Authority after CQ #7 $30,436.55 v%� / Public Works Dir ct Pro' Manager Cc: Deputy City Manger Finance Department