09-192.00 Acme Concrete: Sprague & Pines PCCP IntersectionS#6Q e
,;
CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 09 -024
AU
SpraguelPlnes PCCP Intersection Project CONTRACT DATE: 4124/2009
IMPROVEMENT PROJECT NO: 0103
This Change Order grants two additional working days for unforeseen conditions detailed in the attached Acme June 19, 2009 Itr.
By signing this change order Acme waives all other project claims Including "loss of production" or delay chins.
Original Date: 6/22/2009 Prior to this Change Order: 6122/2009 Including this Change Order:
Vorkino Dava: 30 Working Dave Added by this C 2 Working Days Including this CO:
CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT PRICE:
ORIGINAL CONTRACT AMOUNT .... .. ...... ___._ ...... _.____....._._._..._.......... _._ ........ ._.___._ .................__.__. $ _ $634,428.
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT 44,663
_ .................... ................ ... ..........__ ........._.._...........__ _
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER „•• $„ 676,991.
NET THIS CHANGE ORDER. 0•
.. .._. .
v................._........_. - ...,._._._..._......._.. __
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER 678,991 •
This change order add92 days to contract time.
CONTRACTOR ACCEPTANCE: i DATE: -vrz
The contractor hereby accepts this adjusVn u erthei o r atcontractforallworkperromed.
RECOMMENDED BY: 4 DATE: [o •7� •Q 7
n
APPROVED BY:
APPROVED BY: DATE:
David Merder, C11" aneger
ATTACHMENTS:
Dlstdbullon:
ORIGINALS TO: Contractor, City of Spokane Valley Clerk's Office, PW Project File
COPI TO PW Project File P'PutlIe WcAsipurchengleo --- ------
0.179' (CZ
F TyM
Concrete Paving, Inc.
June 19, 2009
City of Spokane Valley
11707 E Sprague Ave Suite 106
Spokane Valley, WA 99206
Attn: Craig Aldworth, P.E.
Re: Sprague and Pines Rd PCCP Intersection Project .
Capital Improvement Project No..0103
Additional Work .Days.. :'
Dear Mr. Aldworth .
During installation of underground drainage structures on the above referenced project,
specifically the Phase 3, southern portion, Woodard Construction encountered "unforeseen
conditions" causing delay. With this correspondence Acme Concrete Paving is respectfully
requesting three (3) additional contract days.
Unforeseen Conditions causing delay include:
• Utility conflicts requiring time consuming re- routing analysis / approval
• Structure additions and Pipe materials substitution
• Additional / Parallel piping materials and structure accessing
• Repair of existing underground drainage structure and pipe (Drywell / CDF in SW
approach)
• Phase 3 continuation of the project wide over - excavation and CSTC installation
If you have any questions, please contact me at 509- 242 -1234.
ate
Project Manager
4124 East Broadway, Spokane, WA 99202 • (509) 242 -1234 • FAX (509) 242 -1232
An Equal Opportunity Employer
ne In Public Works Department
Capital Improvement Program
Valley®
11707 E Sprague Ave Suite 106 4 Spokane Valley WA 99206
509.921.1000 ♦ Fax: 509.921.1008 ♦ cityhati@spokanevalley.org
Memorandum
Date: June 30, 2009
To: Steve Worley, Neil Karsten
From: Craig Aldworth
Re: Change Order 7 for Sprague Pines PCCP Intersection Project, CIP 0103
Budget Account No. 303.303.0103.595.30.63.00 Acme Concrete Paving Contract 09 -024
This Change Order grants two additional working days for over - excavation and additional storm
drainage work.
Total estimated cost (incl. tax) for this Change Order work is $0.00, paid for by an 79.5% STA
grant and the City of Spokane Valley. There are sufficient funds in the project budget to cover
these costs. The Change order adds 2 days to the Contract time.
Original Contract amount = $634,428.25
Previous Change Order Cost = $44,563.45
Change Order 97 Cost = $0.00
Project Cost including Change Order #7 = $678,991.70
15% of Original Contract amount = $95,164.24
Max Public Works Director Contract authority = $75,000.00
Change Order Cost to date = $44,563.45
Remaining P.W. Director Contract Authority after CQ #7 $30,436.55