22-023.01RobsDemolitionBestRdPropertyCleanup S"" ane
Pok
Valley Change Order No: 1
Construction Contract No: 22-023
CITY OF SPOKANE VALLEY—4216 N.BEST RD. CLEAN-UP PROJECT
THE CONTRACT IS MODIFIED AS FOLLOWS:
WORK TO INCLUDE
Description of Change:
Contractor removed the fire/debris pile as called out in the AWM but the adhesive that was still stuck to the concrete slab was not
addressed.The city needs to figure out a way to pay for the disposal of the approx.40'x25'slab to Graham Road facility.
This is a Change Order for the lump sum cost of$6,850.00.This cost includes the extra labor involved to line the dump truck with
plastic,the plastic&tape plus the additional cost of dump fee.
Cost Justification
The extra cost will be two extra dump truck loads to the Graham Road Facility for approx.$2,000 to$3,000 per load plus the two
rolls of plastic at a cost of approx.$600 a piece plus the labor of the IRS employees to line the truck.There would be no extra cost
from Rob's Demolition since this slab was slated for removal anyway just at a lower dump fee.
Time
No working days are added.
Payment:
This change order is in the amount of$6,850.00.
The total contract amount will be increased accordingly. $ 98,420.00 Original contract amount
$ 6.850.00 Change Order#l
$ 105,270.00 Total
9.369.03 Tax 8.9%
$ 114,639.03 Total to date
Prime Contractor Signature: Date: _j Z —2
Project Manager's Signature for Execution: '"""' Date: --1" 2 - 2 a