24-185.00ElderDemoBalfourFacility
Contract No.24-185 CONSTRUCTION AGREEMENT Elder Demo, LLC THIS CONSTRUCTION AGREEMENT(the "Agreement") is made by and between the City of Spokane Valley, a code City of the State of Washington ("City") and Elder Demo, LLC, ("Contractor") jointly referred to as the"Parties". IN CONSIDERATION of the terms and conditions contained herein the Parties agree as follows: 1.Work to Be Performed. Contractor shall do all work and furnish all labor,supervision,tools,materials, supplies, and equipment and other items necessary for the construction and completion of the Balfour Facility Demolition-CIP#0350 (the"Work") in accordance with the Scope of Work outlined in Exhibit A and in accordance with this Agreement (which are by this reference incorporated herein and made part hereof and referred to as the "Contract Documents"), and shall perform any changes in the work in accordance with the Contract Documents. The terms and provisions in this Agreement shall control over any inconsistent or incompatible terms in any other Contract Document. Contractor shall,for the amount set forth in paragraph 4,below,assume and be responsible for the cost and expense of all work required for constructing and completing the Work and related activities to the City's satisfaction. provided for in the Contract Documents, within the time limits prescribed in the Contract Documents. The City Manager or designee shall administer and be the primary contact for Contractor. Upon notice from City,Contractor shall promptly commence work,complete the same in a timely manner,and cure any failure in performance under this Agreement. Unless otherwise directed by City, all work shall be performed in conformance with the Contract Documents, and all City, state, and federal standards, codes, ordinances, regulations, and laws as now existing or as may be adopted or amended. 2. Time for Performance. Contractor shall commence the Work within 10 days of receipt of a notice to proceed and shall complete the Work within the times specified in the Contract Documents, as may be extended in accordance with this Agreement and the Contract Documents. 3. Liquidated Damages. Time is of the essence for this Agreement. Delays cause inconvenience to the residents of City and cost taxpayers undue sums of money. adding time needed for administration, engineering, inspection, and supervision. It is impractical for City to calculate the actual cost of delays. Accordingly, Contractor agrees to pay liquidated damages for failure to achieve Substantial Completion(as defined in the Contract Documents)which shall be in the amount of$250.00 per day. These liquidated damages are not a penalty but are fixed and agreed upon by and between Contractor and City because of the impracticability and difficulty of fixing and ascertaining the actual damages that City would sustain in the event that the Work is not completed in accordance with the Contract Documents. Liquidated damages may be retained by City and deducted from payments otherwise due to the Contractor. 4. Compensation. In consideration of Contractor performing the Work, City agrees to pay Contractor in accordance with the Contract Documents the sum of$128,823.00, plus Washington State Sales Tax of 0350 Balfour Facility Ikrnolition Project Paee 1 of 9 $11,465.25 (if applicable), for a total of$140,288.25, based on the bid submitted by Contractor(Exhibit B), and as may be adjusted in accordance with the Contract Documents. 5. Payment. Contractor may elect to be paid in monthly installments, upon presentation of an application for payment in a form satisfactory to City. Applications for payment shall be sent to the City Finance Department at the address stated in paragraph 6. Pursuant to chapter 60.28 RCW,five percent of the compensation due Contractor shall be retained by City. City reserves the right to withhold payment under this Agreement for that portion of the work(if any)which is determined in the reasonable judgment of the City Manager or designee to be noncompliant with the Contract Documents. City standards, City Code,state standards, or federal standards. 6. Notice. Notice other than applications for payment shall be given in writing as follows: TO THE CITY: TO THE CONTRACTOR: Name: Marci Patterson, City Clerk Name: Dana Brunson,Office Manager Phone: (509)720-5000 Phone:(503)760-6330 Address: 10210 East Sprague Avenue Address: PO Box 10, Wilsonville,OR 97070 Spokane Valley, WA 99206 d 7. Applicable Laws and Standards. The Parties, in the performance of this Agreement, agree to comply ith all applicable federal,state,and local laws,codes, and regulations. 8. Certification Regarding Debarment, Suspension, and Other Responsibility Matters — Primary Covered Transactions. A. By executing this Agreement, the Contractor certifies to the best of its knowledge and belief, that it and its principals: 1. Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any federal department or agency; 2. Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (federal, state, or local) transaction or contract under a public transaction; violation of federal or state antitrust statutes or commission of embezzlement, theft, forgery, bribery. falsification or destruction of records,making false statements, or receiving stolen property; 3. Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (federal, state, or local) with commission of any of the offenses enumerated in paragraph(A)(2)of this certification; and 4. Have not within a three-year period preceding this application/proposal had one or more public transactions(federal,state,or local)terminated for cause or default. B. Where the prospective primary participant is unable to certify to any of the statements in this certification,such prospective participant shall attach an explanation to this Agreement. 0350 Balfour Facility Demolition Project Page 2 of 9 9. Prevailing Wages on Public Works. Contractor,any subcontractor,or other person doing work under this Agreement, shall comply with the requirements of chapter 39.12 RCW, and shall pay each employee an amount not less than the Prevailing Rate of Wage, as specified by the Industrial Statistician of the Washington State Department of Labor and Industries("L&I"). If employing labor in a class not shown, Contractor shall request a determination of the correct wage rate for the class and locality from the Industrial Statistician. Contractor shall provide a copy of any such determinations to City. Before commencing, during, and upon completion of the work,Contractor shall file all forms and pay all fees required by L&I and shall indemnify and hold City harmless from any claims related to its failure to comply with chapter 39.12 RCW. The following information is provided pursuant to RCW 39.12.030: A.State of Washington prevailing wage rates applicable to this public works project,published by L&I,are located at the L&I website address: https://lni.wa.gov/licensintr-permits/public-works projects/prevailing-wage-rates/ B.This Project is located in Spokane County. C.The effective prevailing wage date is the same date as the bid due date as referenced in the original request for bids and as may be revised by addenda. A copy of the applicable prevailing wage rates is also available for viewing at the City Community&Public Works Department located at 10210 East Sprague Avenue, Spokane Valley, WA 99206. Upon request, City will mail a hard copy of the applicable prevailing wages for this project. 10. Relationship of the Parties. It is understood and agreed that Contractor shall be an independent contractor and not the agent or employee of City,that City is interested only in the results to be achieved, and that the right to control the particular manner,method,and means in which the services are performed is solely within the discretion of Contractor. Any and all employees who provide services to City under this Agreement shall be deemed employees solely of Contractor. Contractor shall be solely responsible for the conduct and actions of all its employees under this Agreement and any liability that may attach thereto. 11. Ownership of Documents. All drawings,plans,specifications,and other related documents prepared by Contractor under this Agreement are and shall be the property of City.and may be subject to disclosure pursuant to chapter 42.56 RCW,or other applicable public record laws. 12.Records. The City or State Auditor or any of their representatives shall have full access to and the right to examine during normal business hours all of Contractor's records with respect to all matters covered in this Agreement. Such representatives shall be permitted to audit, examine, make excerpts or transcripts from such records,and to make audits of all contracts, invoices,materials,payrolls, and record of matters covered by this Agreement for a period of three years from the date final payment is made hereunder. 13. Warranty. Unless provided otherwise in the Contract Documents, Contractor warrants that all Work and materials performed or installed under this Agreement are free from defect or failure for a period of one year following final acceptance by City,unless a supplier or manufacturer has a warranty for a greater period, which warranty shall be assigned or transferred to City. In the event a defect or failure occurs in work or materials, Contractor shall,within the warranty period, remedy the same at no cost or expense to 0350 Balfour Facility Demolition Project Page 3 of 9 City. This warranty provision shall not be construed to establish a period of limitation with respect to Contractor's other obligations under this Agreement. 14.Contractor to Be Licensed and Bonded. Contractor shall be duly licensed,registered,and bonded by the State of Washington at all times this Agreement is in effect. 15.Contractor to Provide Performance and Payment Bonds. Contractor shall provide a payment bond and a performance bond in the full amount of the Agreement on the City's bond forms. Alternatively, Contractor may elect to have the City retain 10% of the Agreement amount in lieu of providing the City with a payment bond and a performance bond,pursuant to RCW 39.08.010(3). 16. Insurance. Contractor shall procure and maintain insurance, as required in this Section, without interruption from commencement of the Contractor's work through the term of the Contract and for 30 days after the physical completion date,unless otherwise indicated herein. A. Minimum Scope of Insurance. Contractor shall obtain insurance of the types described below: 1. Automobile liability insurance covering all owned, non-owned, hired and leased vehicles. Coverage shall be at least as broad as Insurance Services Office(ISO)form CA 00 01. 2.Commercial general liability insurance shall be at least as broad as ISO occurrence form CG 00 01 and shall cover liability arising from premises, operations, stop gap liability, independent contractors, products-completed operations for a period of three years following substantial completion of the work for the benefit of the City, personal injury and advertising injury,and liability assumed under an insured contract. The Commercial General Liability insurance shall be endorsed to provide a per project general aggregate limit, using ISO form CG 25 03 05 09 or an endorsement providing at least as broad coverage. There shall be no exclusion for liability arising from explosion, collapse or underground property damage. The City shall be named as an additional insured under the Contractor's Commercial General Liability insurance policy with respect to the work performed for the City using ISO Additional Insured endorsement CG 20 10 10 01 and Additional Insured-Completed Operations endorsement CG 20 37 10 01 or substitute endorsements providing at least as broad coverage. 3. Workers' compensation coverage as required by the industrial insurance laws of the State of Washington. B.Minimum Amounts of Insurance. Contractor shall maintain the following insurance limits: 1. Automobile liability insurance with a minimum combined single limit for bodily injury and property damage of no less than$1,000,000 per accident. 2. Commercial general liability insurance shall be written with limits no less than $2,000,000 each occurrence,$2,000,000 general aggregate,and no less than a$2,000,000 products-completed operations aggregate limit. C. Other Insurance Provisions. The insurance policies are to contain, or be endorsed to contain, the following provisions for automobile liability and commercial general liability insurance: 0350 Balfour Facility Demolition Project Page 4 of 9 I. Contractor's insurance coverage shall be primary insurance with respect to City. Any insurance, self-insurance, or insurance pool coverage maintained by City shall be excess of Contractor's insurance and shall not contribute with it. 2.Contractor shall fax or send electronically in.pdf fonnat a copy of insurer's cancellation notice within two business days of receipt by Contractor. 3. If Contractor maintains higher insurance limits than the minimums shown above, City shall be insured for the full available limits of commercial general and excess or umbrella liability maintained by Contractor, irrespective of whether such limits maintained by Contractor are greater than those required by this Agreement or whether any certificate of insurance furnished to the City evidences limits of liability lower than those maintained by Contractor. 4. Failure on the part of Contractor to maintain the insurance as required shall constitute a material breach of this Agreement, upon which the City may, after giving at least five business days' notice to Contractor to correct the breach, immediately terminate the Agreement, or at its sole discretion, procure or renew insurance and pay any and all premiums in connection therewith, with any sums so expended to be repaid to City on demand, or at the sole discretion of the City, offset against funds due Contractor from the City. D.No Limitation. The Contractor's maintenance of insurance, its scope of coverage. and limits as required herein shall not be construed to limit the liability of the Contractor to the coverage provided by such insurance, or otherwise limit the City's recourse to any remedy available at law or in equity. E. Acceptability of Insurers. Insurance is to be placed with insurers with a current A.M. Best rating of not less than A:VII. F. Evidence of Coverage. As evidence of the insurance coverages required by this Agreement, Contractor shall furnish acceptable insurance certificates to City at the time Contractor returns the signed Agreement,which shall be Exhibit C. The certificate shall specify all of the parties who are additional insureds, and shall include applicable policy endorsements, and the deduction or retention level. Insuring companies or entities are subject to City acceptance. If requested, complete copies of insurance policies shall be provided to City. Contractor shall be financially responsible for all pertinent deductibles,self-insured retentions, and/or self-insurance. G. Failure to Maintain Insurance. Failure on the part of the Contractor to maintain the insurance as required shall constitute a material breach of contract, upon which the City may, after giving at least five business days' notice to Contractor to correct the breach, immediately terminate the Agreement or, at its discretion, procure or renew such insurance and pay any and all premiums in connection therewith,with any sums so expended to be repaid to the City on demand,or at the sole discretion of the City, offset against funds due Contractor from the City. H. Subcontractor Insurance. Contractor shall cause each and every subcontractor to provide insurance coverage that complies with all applicable requirements of Contractor-provided insurance as set forth herein, except Contractor shall have sole responsibility for determining the limits of coverage required to be obtained by subcontractors. Contractor shall ensure that the City is an additional insured on each subcontractor's Commercial General liability insurance policy 0350 13alfour Facility Demolition Project Page 5 of9 using an endorsement as least as broad as ISO CG 20 10 10 01 for ongoing operations and CG 20 37 10 01 for completed operations. 17. Indemnification and Hold Harmless. Contractor shall defend, indemnify and hold the City, its officers,officials,employees and volunteers harmless from any and all claims, injuries,damages, losses or suits including attorney fees,arising out of or in connection with the performance of this Agreement,except for injuries and damages caused by the sole negligence of the City. However, should a court of competent jurisdiction determine that this Agreement is subject to RCW 4.24.115, then, in the event of liability for damages arising out of bodily injury to persons or damages to property caused by or resulting from the concurrent negligence of the Contractor and the City, its officers, officials. employee,. and volunteers,the Contractor's liability hereunder shall be only to the extent of the Contractor's negligence. It is further specifically and expressly understood that the indemnification provided herein constitutes the Contractor's waiver of immunity under Industrial Insurance,Title 51 RCW. solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement. 18.Waiver.No officer,employee,agent,or other individual acting on behalf of either party has the power, right,or authority to waive any of the conditions or provisions of this Agreement. No waiver in one instance shall be held to be waiver of any other subsequent breach or nonperformance. All remedies afforded in this Agreement or by law shall be taken and construed as cumulative and in addition to every other remedy provided herein or by law. Failure of either party to enforce at any time any of the provisions of this Agreement or to require at any time performance by the other party of any provision hereof shall in no way be construed to be a waiver of such provisions nor shall it affect the validity of this Agreement or any part thereof. 19. Assignment and Delegation. Neither party shall assign, transfer, or delegate any or all of the responsibilities of this Agreement or the benefits received hereunder without first obtaining the written consent of the other part). 20. Confidentiality. Contractor may,from time-to-time, receive information which is deemed by City to be confidential. Contractor shall not disclose such information without the prior express written consent of City or upon order of a Court of competent jurisdiction. 21. Disputes. All disputes arising under or related to this Agreement that cannot be resolved through informal discussion and negotiations shall be resolved by litigation filed in the Superior Court of the State of Washington for Spokane County, unless otherwise required by applicable federal or state law. 22. Costs and Attorney's Fees. The prevailing party in any litigation or arbitration arising out of this Agreement shall be entitled to its attorney's fees and costs of such litigation or arbitration(including expert witness fees). 23. Subcontractor Responsibility. As required by RCW 39.06.020, Contractor shall verify responsibility criteria for each first tier subcontractor and its subcontractors of any tier that hires other subcontractors shall verify responsibility criteria for each of its subcontractors. Verification shall include that each subcontractor, at the time of subcontract execution, meets the responsibility criteria listed in RCW 39.04.350(1) and possesses an electrical contractor license, if required by chapter 19.28 RCW, or an elevator contractor license if required by chapter 70.87 RCW. This verification requirement shall be included in every subcontract of every tier. 0350 Balfour Facility I),r.rotition Project Page 6 of 24.Jurisdiction and Venue.This Agreement is entered into in Spokane County, Washington. Venue shall be in Spokane County, State of Washington. 25.Entire Agreement. This Agreement constitutes the entire and complete agreement between the parties and supersedes any prior oral or written agreements. This Agreement may not be changed, modified, or altered except in writing signed by the Parties. 26.Anti-kickback. No officer or employee of City,having the power or duty to perform an official act or action related to this Agreement, shall have or acquire any interest in this Agreement, or have solicited. accepted,or granted a present or future gift, favor. service,or other thing of value from any person with an interest in this \greement. 27. Business Registration. Prior to commencement of Work under this Agreement. Contractor shall register with the City as a business if it has not already done so. 28. Assurance of Compliance with Applicable Federal Law. During the performance of this Agreement, the Contractor,for itself,its assignees, and successors in interest agrees as follows: A. Compliance with Regulations. Contractor shall comply with the federal laws set forth in subsection G, below ("Pertinent Non-Discrimination Authorities") relative to non-discrimination in federally-assisted programs as adopted or amended from time-to-time, which are herein incorporated by reference and made a part of this Agreement. B. Non-discrimination. Contractor,with regard to the work performed by it during this Agreement, shall not discriminate on the grounds of race,color,or national origin in the selection and retention of subcontractors, including procurements of materials and leases of equipment. Contractor shall not participate directly or indirectly in the discrimination prohibited by the Acts and the Regulations, including employment practices when the contract covers any activity. project, or program set forth in Appendix B of 49 CFR Part 21. C. Solicitations for Subcontracts, Including Procurements of Materials and Equipment. In all solicitations, either by competitive bidding, or negotiation made by Contractor for work to be performed under a subcontract, including procurements of materials, or leases of equipment, each potential subcontractor or supplier shall be notified by Contractor of Contractor's obligations under this Agreement and the Acts and the Regulations relative to non-discrimination on the grounds of race, color,or national origin. D. Information and Reports. Contractor shall provide all information and reports required by the Acts, the regulations, and directives issued pursuant thereto, and shall permit access to its books, records,accounts,other sources of information, and its facilities as may be determined by the City or the WSDOT to be pertinent to ascertain compliance with such Acts,regulations,and instructions. Where any information required of Contractor is in the exclusive possession of another who fails or refuses to furnish the information. Contractor shall so certify to the City or the WSDOT, as appropriate,and shall set forth what efforts it has made to obtain the information. E. Sanctions for Noncompliance. In the event of a Contractor's noncompliance with the non- discrimination provisions of this Agreement, the City will impose such contract sanctions as it or the WSDOT may determine to be appropriate, including, but not limited to: 0350 Balfour Facility Demolition Project Page 7 of 9 1. Withholding payments to Contractor under the Agreement until Contractor complies; and/or 2. Cancelling,terminating,or suspending the Agreement,in whole or in part. F. Incorporation of Provisions. Contractor shall include the provisions of Section 28 of this Agreement in every subcontract, including procurements of materials and leases of equipment, unless exempt by the Acts,regulations and directives issued pursuant thereto.Contractor shall take action with respect to any subcontract or procurement as the City or the WSDOT may direct as a means of enforcing such provisions, including sanctions for noncompliance. Provided, that if Contractor becomes involved in, or is threatened with litigation by a subcontractor or supplier because of such direction,Contractor may request that the City enter into any litigation to protect the interests of the City. In addition, Contractor may request the United States to enter into the litigation to protect the interests of the United States. G. Pertinent Non-Discrimination Authorities: During the performance of this Agreement, the Contractor agrees to comply with the following non-discrimination statutes and authorities; including but not limited to: Title VI of the Civil Rights Act of 1964(42 U.S.C. §2000d et seq.,78 stat.252),(prohibits discrimination on the basis of race,color,national origin);and 49 CFR Part 21;and 49 Part 26; The Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, (42 U.S.C. §4601),(prohibits unfair treatment of persons displaced or whose property has been acquired because of Federal or Federal-aid programs and projects); Federal-Aid Highway Act of 1973,(23 U.S.C. §324 et seq.), (prohibits discrimination on the basis of sex); Section 504 of the Rehabilitation Act of 1973, (29 U.S.C. §794 et seq.), as amended, (prohibits discrimination on the basis of disability);and 49 CFR Part 27; The Age Discrimination Act of 1975, as amended, (42 U.S.C. §6101 et seq.), (prohibits discrimination on the basis of age); Airport and Airway Improvement Act of 1982, (49 U.S.C. §471. Section 47123), as amended,(prohibits discrimination based on race,creed, color,national origin,or sex); The Civil Rights Restoration Act of 1987,(PL 100-209), (Broadened the scope, coverage and applicability of Title VI of the Civil Rights Act of 1964,The Age Discrimination Act of 1975 and Section 504 of the Rehabilitation Act of 1973,by expanding the definition of the terms"programs or activities"to include all of the programs or activities of the Federal- aid recipients, sub-recipients and contractors, whether such programs or activities are Federally funded or not); Titles II and III of the Americans with Disabilities Act, which prohibit discrimination on the basis of disability in the operation of public entities,public and private transportation systems,places of public accommodation,and certain testing entities(42 U.S.C. §§12131- 0350 Balfour Facility Demolition Project Page 8 of 9 12189)as implemented by Department of Transportation regulations at 49 C.F.R.parts 37 and 38; The Federal Aviation Administration's Non-discrimination statute (49 U.S.C. §47123) (prohibits discrimination on the basis of race,color,national origin,and sex); Executive Order 12898, Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations, which ensures Non-discrimination against minority populations by discouraging programs, policies, and activities with disproportionately high and adverse human health or environmental effects on minority and low-income populations; Executive Order 13166, Improving Access to Services for Persons with Limited English Proficiency, and resulting agency guidance, national origin discrimination includes discrimination because of Limited English proficiency(LEP). To ensure compliance with Title VI,you must take reasonable steps to ensure that LEP persons have meaningful access to your programs(70 Fed.Reg.at 74087 to 74100);and Title IX of the Education Amendments of 1972, as amended, which prohibits you from discriminating because of sex in education programs or activities(20 U.S.C.§1681 et seg.). 29.Severability. If any section,sentence,clause,or phrase of this Agreement should be held to be invalid for any reason by a court of competent jurisdiction,such invalidity shall not affect the validity of any other section,sentence,clause,or phrase of this Agreement. 30. Exhibits. Exhibits attached and incorporated into this Agreement are: A. Scope of Work B. Cost Statement C. Insurance Endorsements Withold additional retainage per Contractor request) The Parties have executed this Agreement this 2 9 r.PI day of 0 LTV Q E ,2024. CITY OF SPOKANE VALLEY: Contractor: Elder Demo,LLC Hohman,City Manager By:J stin Arrand,Manager Its:Authorized Representative APPROVED AS TO FORM: ice oft e City A o y 0350 Balfour Facility Demolition Project Page 9 of 9 EXHIBIT A City of Spokane Valley Balfour Facility Demolition Project-Contract No. 24-185 SCOPE OF WORK This contract shall provide for all labor and equipment necessary for Asbestos Containing Material (ACM) abatement and demolition of the 4,600 square foot two-story wood framed commercial building along with the"entry bridge"and the partial below-grade foundation. The demolition shall include removal and disposal of all building materials, including contents, and some site vegetation along with a few trees. Additionally,the work will include subgrade preparation and import, placement&compaction of structural fill for a future building pad.All costs,fees, and permits associated with this contract shall be borne by the Contractor.This shall include a Demolition Permit from the City of Spokane Valley,a Notice of Intent Permit from Spokane Regional Clean Air Agency,and a Sewer Abandonment Permit from Spokane County Utilities. Parcel ID-45174.9033,Site Address: 10303 E.Sprague Avenue { , • - FIGURE 1:EXTERIOR,LOOKING NORTH FIGURE 2:EXTERIOR,LOOKING SOUTH . R r • v l t - 32131111110111 1111011 ,.'3 J J FIGURE 3:EXTERIOR,LOOKING EAST FIGURE 4:EXTERIOR,LOOKING WEST 0350 Balfour Facility Demolition Page 115 tiii\i,,i7,4, ,,, ,,- ,: ,,, ,,,, .„ mv": _ ,_______,, " ►uuuuup° t ka / r _ ._ -- -» ,. . ' 1-. FIGURE 5:INTERIOR,NORTH ENTRY STAIRCASE FIGURE 6:INTERIOR,UPPER NORTH SIDE r'- `r i z = - vii %) I, ' :.,, j. s FIGURE 7:INTERIOR,UPPER SOUTH SIDE FIGURER:INTERIOR,UPPER FIGURES:INTERIOR,UPPER MEWS RESTROOM WOMEN'S RESTROOM f r£ ter'- ,;�. ; \ _ '<. �r r ..,': , las, ' r 3 4� .. c:: .J .. , FIGURE 10:INTERIOR LOWER RESTROOM FIGURE 11:INTERIOR LOWER STORAGE FIGURE 12:INTERIOR LOWER MECHANICAL ROOM 0 3 5 0 Balfour Facility Demolition Page 2 1 5 n II J� FIGURE 13:INTERIOR LOWER-KITCHENETTE FIGURE 14:INTERIOR,LOWER NORTH ' ... + ` , FIGURE 15:INTERIOR,LOWER SOUTH FIGURE 16:INTERIOR,ELECTRICAL ROOM WORK DETAILS Work to include partial site vegetation and tree removal, abatement of ACM,and demolishing, removing and disposing of all building materials and man-made objects. Additionally,the work wilt include relocating approximately 30 granite boulders from around the building to another location onsite. All hauling and dump fees shall be incidental to the work.The excavation that will exist after the lower level and foundation have been removed shall be cleared and grubbed then scarified so "Foundation Material-Class A" per WSDOT Standard Specification 9-03.17 can be placed in 12" maximum thickness lifts and compacted to 95%minimum relative density to match surrounding grade. Foundation material will require a submittal of gradation analysis and a physical sample that will be provided to the City's third-party Materials Testing firm for a proctor test. They will also provide third party inspection services during preparation of subgrade and placement of fill along with compaction testing. See attached Demolition Site Plan for more information. Coordination with utilities, if any,will also be included in this work. Contractor to coordinate with Spokane Valley Fire Department to allow at least one(1)day after abatement and before demolition for destructive training purposes. The Contractor shall remove any debris,tracking,and mud from parking lot, city streets and sidewalks at the end of each workday to ensure public safety. 0350 Balfour Facility Demolition Page 315 The Contractor shall be responsible for dust control during demolition activities including any fees associated with water supplied by the local water utility. PERMITS Contractor to obtain Demolition Permit from City of Spokane Valley. (509)921-1000. Contractor to obtain Notice of Intent Permit from Spokane Regional Clean Air Agency. (509)477-4727. Contractor to obtain Sewer Abandonment Permit from Spokane County Utilities. (509)477-1984. Contractor to obtain water permit and pay all fees as may be needed for dust control from Modern Electric Water Company. (509)928-4540. All debris shall be disposed of in a legal manner.The Contractor shall arrange to dispose of waste at no additional expense to the City of Spokane Valley. WORKING DAYS The project shall be physically completed within ***40***calendar days.Work shall commence on, or around, October 28,2024. The Contractor shall secure the site and staging area with temporary fencing at the end of each work shift to ensure public safety. UTILITIES The electricity will be disconnected from the building by Modern Electric Water Company just prior to demolition. Contractor to arrange the disconnection with Glenn Ritter, Project Manager,from the City of Spokane Valley. (509)720-5018. Gas has been disconnected and capped by Avista away from the building as shown on the attached site plan. Please contact Rob Koschalk of Avista-Gas if needed for confirmation. (509) 280-7383 or robb.koschalk@avistacorp.com. The water connection for the building has already been capped immediately downstream of the meter. Please contact Lance Peterson,Superintendent,with Modern Electric Water Company, (509) 879-6417 if there are any questions or concerns. The sewer service for the building has not been removed yet. Contractor to coordinate with and obtain Sewer Abandonment Permit from Spokane County Utilities. (509)477-1984. The Contractor shall call the One-Call Locator Service for field locations of existing utilities prior to starting work. All exiting utilities to remain shall be protected in place as best as possible. 0 3 5 0 Balfour Facility Demolition Page 415 ASBESTOS An asbestos survey was completed for the building. Asbestos Containing Materials(ACM)were discovered and will need to be abated. Please see attached report by McCrink Consulting dated April 15, 2024 and updated October 15,2024. PAYMENT "Balfour Facility Demolition Project"shall be a lump sum full payment for each of the three items shown on Bid Schedule A for furnishing all tools, labor,equipment,and materials required to abate then demolish and remove all building debris in its entirety and build the compacted pad as listed in the above Scope of Work. The fourth item on Bid Schedule A will be paid only as/if needed and only upon the written approval of the City's Project Manager. Please fill out and submit the attached Bid Proposal packet by the due date. An example of contractual requirements are listed below: • City Contract with the associated insurance requirements (See attached sample) • Pay Prevailing Wages • File Intents and Affidavits • Provide Payment and Performance Bonds (See attached samples) • Provide Retainage Bond, if desired (see attached sample) • Provide Certificate(s) of Insurance w/endorsement(s) • Submit gradation analysis and physical sample of Foundation Material ATTACHMENTS • Demolition Site Plan • Demolition Asbestos Survey Report 0350 Balfour Facility Demolition Page 515 LEGEND —311••••- 4 m FOUND AS NOTED p ---� 0 5 to 20 M'1 -FOUND In'RARE k aw �\ SCALE •-za ° °v. 7 v. V. FT ° v. v. v. v. ® _WATER METER ees Irm , 1 w =WATER.kK R-PIPE xowa existing trees Apgox locate or to remain weMa PRE CONNECTION 8 En lets ® cr a xt.g \` i / 'AR6remeinass R jp- I - Wale remain Mr ro a \\ '..— /, ax,,,,,„•,, e? b Exist rg Maai�existing 1 Cgs to remain weso.see grade(Voice.) 6okpe IGATION VALVE ' I T f o- Po T��aexistinga I X ( ' =MUTT I M •, ;Match existing IA E F=an op grad gYpoa p. (-POLE wit unewxI ? Match existing Ewstinp grad llYWoel) Sit e e [uxs Ire�ero Slope fiat P�to Main ► .e.ry. FENCE T ClEANSUIRUN cuss I .t<. _—_._—_ eoa�rw lrwx x oo.rtexc ( X X It x m I 3 I € MATCH SURNOUNIANO MADE MD COMPACT TO I .,ww E.:urg +'' 3 ks.w.acu.rt.eExen. \ t\\.\,,,, D • v T s X s i Maka exiseng X III X (Gil E - \,___5;(04 I(grad roncall g � .- dg.aee Ilvgi.an '� H g back of 111 walk(tYgirall c emow mr F g X Existing X I31 SxicurpX X Existing cum X ___> §) sidewalk to ? to remain T In I 77 T T Staging Area � I ^ X X X K r _ ., , 1 .. ,•.,:. X IX X X ,derM1 xY�— M3 PA , .I,O 0350 BALFOUR FACILITY DEMOLITION SITE PLAN Demolition Asbestos Survey 10303 E. Sprague Avenue Spokane Valley, Washington 99206 MI ,r Project No.: MC-23-060 By McCrink Consulting, LLC 660 E. Sand Wedge Drive Post Falls, Idaho 83854 Phone: (509) 991-7357 June 26, 2023 Updated April15, 2024 Updated October 15, 2024 TABLE OF CONTENTS Page 1.0 EXECUTIVE SUMMARY 1 2.0 INTRODUCTION 3 2.1 Purpose 2.2 Scope of Services 2.3 Authorization 2.4 Warranty 3.0 METHODOLOGY 3 3.1 Inspection Procedure 3.2 Sampling Procedure 4.0 LABORATORY METHODOLOGY 4 4.1 Method of Analysis-Asbestos 4.2 Laboratory Quality Assurance 5.0 ASBESTOS FINDINGS 4 5.1 Asbestos Containing Materials 5.2 Non-Asbestos Materials APPENDIX Appendix A: Inspector Certification Appendix B: Bulk Asbestos Analytical Results Appendix C: Laboratory Certification 1.0 Executive Summary McCrink Consulting, LLC was retained by the City of Spokane Valley to conduct an asbestos survey for the Building Demolition Project located at 10303 E. Sprague Avenue, Spokane Valley, Washington. The survey was conducted on June 13, 2023, April 9, 2024, and October 15, 2024. Project Area General Building Observations The survey included the interior of the commercial building. The building interior ceilings are textured sheetrock. The sheetrock walls are finished with a wallpaper finish. The wallpaper may be concealing wall texture found in the utility areas of the building. The 2nd floor floors are finished with carpet. The 1st floor floors are finished with carpeting. The restrooms are finished with ceramic tile walls and floors. Floor tile is present in the 1st floor southwest vault room. The building is approximately 55 years old. The building is heated and cooled by rooftop gas fired, forced air, HVAC units. The building exterior had metal wall panels, a built-up tar and felt roof system with roof mastics. The basement exterior walls have a basalt rock facade. Asbestos Containing Materials The materials that were sampled and analyzed and found to contain asbestos consist of the following. 10303 E. Sprague Avenue Interior-Asbestos Materials Homogenous Material Sample Friable Asbestos Type Condition Material Description Number Yes/No Location 2"d floor office Popcorn ceiling B 1 B 2 B Yes Yes Surfacing Good area ceilings texture 3 B� B 5 Popcorn Estimated ceiling texture: quantity: 1,600 s.f. 3%Chrysotile 2"d floor office Joint compound/ B-6 B 7 B Yes Yes Miscellaneous Good area ceilings sheetrock 8 B 9 B 10 Joint including under compound: popcorn ceiling Estimated 2%Chrysotile texture quantity: 1,900 s.f. Sheetrock: N.D. 2"d floor walls Joint compound/ B-15,B-16, Yes Yes Miscellaneous Good sheetrock B-17 Joint compound: Estimated 0%-3% quantity:4,100 s.f. Chrysotile Sheetrock: N.D. 1st floor office Sponge pattern B-28 B 29 Yes Yes Miscellaneous Good area ceilings ceiling texture/ B 30,B-31, Sponge sheetrock B 32 pattern texture:N.D. Estimated Joint quantity: 1,600 s.f. compound: 0%-3% Chrysotile Sheetrock: N.D. 1st floor Popcorn ceiling B-33,B-34, Yes Yes Surfacing Good electrical room texture B 35 Popcorn ceiling Estimated ceiling texture: quantity:90 s.f. 5%Chrysotile 1st floor office Brown wallpaper/ Yes Yes Miscellaneous/ Good B-36,B-37, area walls joint compound/ Wallpaper: Surfacing/ 1 MCCRINK CONSULTING,LLC PROJECT#MC-23-060 sheetrock B-38,B-39 N.D. Miscellaneous Texture:3% Estimated Chrysotile quantity:4,100 s.f. Joint compound: 0%-3% Chrysotile Sheetrock: N.D. 1"floor,Suite Carpet/tan-black No Yes Miscellaneous Good B-40,B-41, 102 office area mastic B-42,B-43 Carpet:N.D. floors Tan-black Estimated mastic:3% quantity:890 s.f. Chrysotile 1"floor Tan-white sheet B-47 B-48 Yes Yes Miscellaneous Good electrical room vinyl/tan mastic Sheet vinyl: 15% Estimated Chrysotile quantity:90 s.f. Tan mastic: 3%Chrysotile 1"floor Tan with black B-49,B-50 No Yes Miscellaneous Good southwest vault spot pattern floor Floor tile 3% room floor tile/black mastic Chrysotile Black mastic: Floor tile: 5%Chrysotile Estimated quantity:30 s.f. Black mastic: Estimated quantity:90 s.f. 1"floor Splatter pattern B_51,B-52, Yes Yes Surfacing Good restroom closet texture/sheetrock B-53 Splatter walls and texture:2%- ceiling Estimated 3%Chrysotile/ quantity:70 s.f. sheetrock: N.D. 10303 E. Sprague Avenue Exterior-Asbestos Materials Homogenous Material Sample Friable Asbestos Type Condition Material Description Number Yes/No Location Roof parapets, Silver paint/black- No Yes Surfacing Good BX-3,BX-4, roof wall caps, gray mastic Silver roof Estimated BX-5,BX-6, paint<1% BX-7 penetrations quantity:650 s.f. Chrysotile and HVAC Black-gray curbs roof mastic: 0%-4% Chrysotile Reference the Asbestos Findings section and the analytical appendix of this report for specific sample information. Signed, Kevin McCrink, AHERA/EPA Accredited Inspector#ON-4644-9601-032524.Expires March 25,2025 AHERA/EPA Accredited Project Designer#ON-4653-9601-070924.Expires June 9,2025 2 MCCRINK CONSULTING,LLC PROJECT#MC-23-060 2.0 Introduction 2.1 Purpose The purpose of the asbestos survey was to provide information on the 10303 E. Sprague Avenue Building Interior Renovation Project regarding the presence of exposed and/or accessible building materials that commonly contain asbestos. 2.2 Scope of Work The scope of work consisted of conducting a visual inspection and sampling survey in accordance with OSHA 29 CFR 1926.1101 and NESHAPS 40 CFR part 61 guidelines to determine the presence of suspected asbestos containing building materials (ACBM) which were exposed and/or accessible. The bulk samples collected from the work area were analyzed at an accredited laboratory to determine the presence and concentrations of asbestos. 2.3 Authorization Authorization to perform this survey was given on June 13, 2023, and March 14, 2024. 2.4 Warranty The field and laboratory results reported herein are considered sufficient in detail and scope to determine the presence of expose and/or accessible suspect asbestos containing building materials in the building at the time of the inspection. McCrink Consulting, LLC warrants that the findings contained herein have been prepared in the general accordance with accepted professional practices at the time of its preparation as applied by similar professionals in the industry. Changes in the state of the art or in applicable regulations cannot be anticipated and have not been addressed in this report. The survey and analytical methods have been used to provide the client with information regarding the presence of accessible and/or exposed suspect asbestos containing building materials existing in the building at the time of the inspection. There is a distinct possibility that conditions may exist which were not apparent during the site visit. This inspection covered only those areas that were exposed and/or accessible to the inspector. The investigation is also limited to the information available from the client at the time of the investigation. No other warranties are implied or expressed. 3.0 Methodology 3.1 Inspection Procedures On June 13, 2023, April 9, 2024, and October 15, 2024, Kevin McCrink, AHERA accredited inspector #ON-4644-9601-032524 conducted the asbestos survey. The initial inspection consisted of the inspector walking through the building to determine the general building lay out, draw a site sketch and to determine the presence of exposed and/or reasonably accessible suspect asbestos containing materials. The suspect materials were then grouped into homogenous material groups that were collected during the sampling phase. 3.2 Sampling Procedures Following the inspection phase, the materials that were identified and grouped into homogenous suspect asbestos materials were then sampled. The sampling was limited to those materials which were exposed and/or accessible and which did not require extensive destructive access to sample. 3 MCCRINK CONSULTING,LLC PROJECT#MC-23-060 The sampling protocol followed was consistent with the guidelines set forth in OSHA 29 CFR 1926.1101 and NESHAPS 40 part 61. Efforts were made to select random sampling locations, but preference was given to damaged or disturbed areas in order to minimize the damage to the building finished surfaces. The sampling and inspection were conducted in the least disruptive manor as possible to the suspect building materials. A copy of the Inspector's accreditation can be found in Appendix A. 4.0 Laboratory Methodology 4.1 Method of Analysis The analysis of the bulk samples for asbestos was performed by EPA method 600/M4-82-020. The bulk samples were prepared for visual examination and identification by polarizing light microscopy. Following the preparation of the material on a glass slide the samples were analyzed for asbestos forms of chrysotile, crocidolite, anthophyllite, actinolite/tremolite, amosite and non- asbestos components that totaled 100 % of the sample volume. Asbestos and non-asbestos elements of each sample were identified utilizing, the unique optical properties associated with them. The identification consisted of identifying specific optical and physical characteristics that included refractive indices, color, pleochroism, birefringence, extinction angles, and sign of elongation and morphology. The volume percentage of each component in the sample was determined by visually estimating the percentage. 4.2 Laboratory Quality Assurance The asbestos bulk samples collected from the building interior of this project were sent to EMC Laboratories located in Phoenix, Arizona. EMC Laboratories is a NVLAP accredited analytical laboratory. The asbestos bulk samples collected from the building exterior of this project were sent to SanAir Technologies Laboratories, Inc. located in West Chesterfield, Virginia for analysis. SanAir Technologies Laboratories, Inc. is a NVLAP accredited analytical laboratory. Additional asbestos bulk samples collected from the building interior of this project were sent to Mountain Laboratories, Inc., located in Spokane Valley, Washington for analysis. Mountain Laboratories, Inc. is a NVLAP accredited analytical laboratory. 5.0 Findings 5.1 Asbestos Containing Materials OSHA/EPA defines a material to be an asbestos containing material (ACM) in the material contains greater than one percent (>1%) asbestos. Multiple samples are collected and if one sample out of the homogenous sampling group is found to contain asbestos then the material is determined to be an asbestos containing material. Specific materials sampled from the 10303 E. Sprague Avenue Demolition Project that were found to contain asbestos and can be found below. 10303 E. Sprague Avenue Interior-Asbestos Materials Homogenous Material Sample Friable Asbestos Type Condition Material Description Number Yes/No Location 2nd floor office Popcorn ceiling B 1 B 2 B Yes Yes Surfacing Good area ceilings texture 3 B 4 B 5 Popcorn Estimated ceiling texture: quantity: 1,600 s.f. 3%Chrysotile 4 MCCRINK CONSULTING,LLC PROJECT#MC-23-060 2nd floor office Joint compound/ B 6 B 7 B Yes Yes Miscellaneous Good area ceilings sheetrock 8 B-9,B-10 Joint including under compound: popcorn ceiling Estimated 2%Chrysotile texture quantity: 1,900 s.f. Sheetrock: N.D. 2"'floor walls Joint compound/ B-15,B-IS, Yes Yes Miscellaneous Good sheetrock B-17 Joint compound: Estimated 0%-3% quantity:4,100 s.f. Chrysotile Sheetrock: N.D. 1"floor office Sponge pattern B 28 B-29 Yes Yes Miscellaneous Good area ceilings ceiling texture/ B-30,B-31, Sponge sheetrock B-32 pattern texture:N.D. Estimated Joint quantity: 1,600 s.f. compound: 0%-3% Chrysotile Sheetrock: N.D. 1st floor Popcorn ceiling B-33,B-34, Yes Yes Surfacing Good electrical room texture B-35 Popcorn ceiling Estimated ceiling texture: quantity:90 s.f. 5%Chrysotile 15'floor office Brown wallpaper/ Yes Yes Miscellaneous/ Good B-36,B-37, area walls joint compound/ B 38 B-39 Wallpaper: Surfacing/ sheetrock N.D. Miscellaneous Texture:3% Estimated Chrysotile quantity:4,100 s.f. Joint compound: 0%-3% Chrysotile Sheetrock: N.D. 1st floor,Suite Carpet/tan-black No Yes Miscellaneous Good B-40,B-41, 102 office area mastic B-42,B-43 Carpet:N.D. floors Tan-black Estimated mastic:3% quantity:890 s.f. Chrysotile 1s`floor Tan-white sheet B-47 B-48 Yes Yes Miscellaneous Good electrical room vinyl/tan mastic Sheet vinyl: 15% Estimated Chrysotile quantity:90 s.f. Tan mastic: 3%Chrysotile 1st floor Tan with black B-49,B-50 No Yes Miscellaneous Good southwest vault spot pattern floor Floor tile 3% room floor tile/black mastic Chrysotile Black mastic: Floor tile: 5%Chrysotile Estimated quantity:30 s.f. Black mastic: Estimated quantity:90 s.f. 5 MCCRINK CONSULTING,LLC PROJECT#MC-23-060 151 floor Splatter pattern B-51,B-52, Yes Yes Surfacing Good restroom closet texture/sheetrock B-53 Splatter walls and texture:2%- ceiling Estimated 3%Chrysotile/ quantity:70 s.f. sheetrock: N.D. 10303 E. Sprague Avenue Exterior-Asbestos Materials Homogenous Material Sample Friable Asbestos Type Condition Material Description Number Yes/No Location Roof parapets, Silver paint/black- BX-3,BX-4, No Yes Surfacing Good roof wall caps, gray mastic Silver BX-5,BX-6, roof Estimated BX_7 paint<1% penetrations quantity:650 s.f. Chrysotile and HVAC Black-gray curbs roof mastic: 0%-4% Chrysotile 5.2 Non-Asbestos Containing Materials Specific materials sampled from the Interior 10303 E. Sprague Avenue Demolition Project that were found not to contain asbestos and can be found in the following table. 10303 E. Sprague Avenue Interior-Non-Asbestos Containing Materials Homogenous Material Sample Friable Asbestos Type Condition Material Description Number Yes/No Location 2"d floor office Tan wallpaper B 11 B 12 No No Miscellaneous Good area walls Wallpaper: N.D. 2"floor Gray wallpaper/ B_13,B-14 No No Miscellaneous Good stairway area tan mastic Wallpaper: walls N.D. Mastic: N.D. 2nd floor Gray ceramic tile/ B 18 B 19 No No Miscellaneous Good restroom walls tan mastic/gray B_20 21 Ceramic tile: grout N.D. Mastic: N.D. Grout:N.D. 2nd floor Gray ceramic tile/ B 22 B 23 No No Miscellaneous Good restroom floors grave cent grout/gray B 24 B 25 Ceramic tile: N.D. B-26,B-27 Grout:N.D. Cement:N.D. 1'`floor,south Tan carpet mastic/ B-44 B_45 No No Miscellaneous Good suite office gray leveling B 46 Carpet mastic: area floors compound N.D. Leveling compound: N.D. 15`floor HVAC White-silver pipe No No Miscellaneous Good ,B-54,B-55 room water wrap/yellow Wrap:N.D. pipe insulation Insulation: N.D. 6 MCCRINK CONSULTING,LLC PROJECT#MC-23-060 1st floor HVAC White-silver pipe No No Thermal system Good ,B-54,B-55 room water wrap/yellow Wrap:N.D. insulation pipe insulation/black Insulation: felt N.D. Felt:N.D. 1st floor HVAC Gray mudded pipe Yes No Thermal system Good ,B-56,B-57 room water joint Mudded pipe insulation pipe joint joint:N.D. Insulation: N.D. 1"floor Brown cove base/ B 58 B-59 No No Miscellaneous Good southwest vault brown mastic Cove base: room walls N.D. Mastic:<1% Tremolite Building interior Black wall mastic, B-60,B-61, No No Miscellaneous Good on wood gold wall mastic B_62,B-63, Black wall framing under B-64,B-65 mastic:N.D. sheetrock. Gold wall mastic: N.D. 10303 E. Sprague Avenue Exterior- Non-Asbestos Containing Materials Homogenous Material Sample Friable Asbestos Type Condition Material Description Number Yes/No Location Exterior roof Silver paint/built- BX-1,BX2- No No Miscellaneous Good up tar and felt Silver paint: roofing N.D. Built-up roofing:N.D. Exterior walls Black tar paper BX 8 BX 9 No No Miscellaneous Good under metal Tar paper: panel siding N.D. Exterior walls Black tar paper BX-10,BX- No No Miscellaneous Good under wood 11 Tar paper: siding N.D. Exterior lower Black masonry BX-12,BX- No No Miscellaneous Good walls mortar 13 Masonry mortar:N.D. Exterior siding White caulk BX-14,BX- No No Miscellaneous Good seams 15 Caulk:N.D. Exterior east Black roof BX-16,BX- No No Miscellaneous Good decorative membrane 17 Roof roofs membrane: N.D. Exterior east White caulk/black- BX-18,BX- No No Miscellaneous Good decorative roof white sealer 19 Caulk:N.D. seams Sealer:N.D. Exterior door Brown seam BX-20 BX No No Miscellaneous Good and window sealer 21 Seaam sealer: frames N.D. Building Gray concrete BX-22,BX- No No Miscellaneous Good foundation 23 Concrete: N.D. N.D. = None Detected End of section. 7 MCCRINK CONSULTING,LLC PROJECT#MC-23-060 Appendix A Inspector's Certification THE ASBESTOS INSTITUTE Certifies that Kevin Mccrink has attended and received instruction in the EPA approved course AHERA Building Inspector Refresher on March 25, 2024 and successfully completed and passed the competency exam. Certificate: ON-188748-9601-032524 Date of Examination: 25-Mar-2024 _ Date of Expiration: William T. rmess. 25-Mar-2025 ;-Approved Instructor Director THE AssEsros Ramon 20033 N.19"Ave,Building 6,Phoenix,AZ 85027 602-864.6564-www.theasbestoslnstitute corn s , AHERA INSPECTOR ', vi,!t CERTIFICATE This is to certify that t}�,. Kevin McCrink �nj t,il1.� e. has attended and satisfactorily completed all requirements to maintain y { ti. accreditation as an Inspector including a written examination l in accordance with the Toxic Substance Control `� Act Title(Section 206)and 401'E 763. ,_ Accreditation No.514-76--�81129 !,: Dated: December 10,1993 ..: ,. . . c Ronald E.Nowicki 1. ` Nowicki&Associates,Inc. 35516 9th Avenue South,Bldg.#6 .44 . Federal Way,Washington 98003 ., -s - n THE ASBESTOS INSTITUTE Certifies that Kevin Mccrink has attended and rece-ved instr.,ction in the EPA appmoved course AHERA Project Designer Refresher or. July 09, 2024 and successfully completed and passed the competency exam. Certificate: ON-184435-9601-070924 Date of E xamtnaton. 9-Jul-2024 _ Date of Expiratmn eI __ Witham T. 09-Jul-2025 Approved inEt Tirter.• Director THE ASBESTOS INSTITUTE 20033 N 19"Ave,8ui'clmg 5,Phoenix,A2 85027 602.864-6564-www.theasbestosmstitutecorn me rem*M?evae tee re tf ptr Ms ca.nnt•tee th TOutse ranwp Ste a tevrr amrrir Y,A.wore SSYA Ste V Certificate of Completion This is to certify that Kevin McCrink has satisfactorily completed 24 hours of training as an AHERA Project Designer it compliance with TSCA Title II AHERA 40 CFR Part 763 U S EPA Rogion 10 Accredited June 30.2010 w s:aa Andre hanw+E�-y A^G H Cert.R 10-2079 Conducted at. Ems+.Oahe June 30,2011 L N V I x O M M t tt S A t. RGA Environmental.Inc. r>.u... ...,..*fw too•F.a..w...ya oval.Or*m..ma Seattle.WA Appendix B Asbestos Analytical Results EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax: (480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-001 Popcorn Texture,Off White Yes Chrysotile 3% Cellulose Fiber 1% B-1 Carbonates Gypsum Mica Quartz Binder/Filler 96% 0293300-002 Popcorn Texture,Off White Yes Chrysotile 3% Cellulose Fiber <1% B-2 Carbonates Gypsum Mica Quartz Binder/Filler 96% 0293300-003 Popcorn Texture,Off White Yes Chrysotile 3% Cellulose Fiber <1% B-3 Carbonates Gypsum Mica Quartz Binder/Filler 96% 0293300-004 Popcorn Texture,Off White Yes Chrysotile 3% Cellulose Fiber 1 B-4 Carbonates Gypsum Mica Quartz Binder/Filler 96% 0293300-005 Popcorn Texture,Off White No None Detected Cellulose Fiber 2% B-5 Carbonates Gypsum Mica Quartz Binder/Filler 98% Page 1 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax: (480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-006 LAYER 1 No None Detected Cellulose Fiber 12% B-6 Sheetrock,Off White/Brown Gypsum Carbonates Mica Quartz 88% LAYER 2 Yes Chrysotile 2% Cellulose Fiber <1% Joint Compound,White Carbonates Mica Quartz Binder/Filler 97% 0293300-007 LAYER 1 No None Detected Cellulose Fiber 12% B-7 Sheetrock,Off White/Brown Gypsum Carbonates Mica Quartz 88% LAYER 2 Yes Chrysotile 2% Cellulose Fiber 1% Joint Compound,White Carbonates Mica Quartz Binder/Filler 97% 0293300-008 Sheetrock,Off White/Brown No None Detected Cellulose Fiber 12% B-8 Gypsum Carbonates Mica Quartz 88% Page 2 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax:(480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-009 LAYER 1 No None Detected Cellulose Fiber 12% B-9 Sheetrock,Off White/Brown Gypsum Carbonates Mica Quartz 88% LAYER 2 Yes Chrysotile 2% Cellulose Fiber 1% Joint Compound,White Carbonates Mica Quartz Binder/Filler 97% 0293300-010 Sheetrock,Off White/Brown No None Detected Cellulose Fiber 12% B-10 Gypsum Carbonates Mica Quartz 88% 0293300-011 Wallpaper,Tan No None Detected Cellulose Fiber 55% B-11 Carbonates Quartz Binder/Filler 45% 0293300-012 Wallpaper,Tan No None Detected Cellulose Fiber 55% B-12 Carbonates Quartz Binder/Filler 45% 0293300-013 LAYER 1 No None Detected Cellulose Fiber 90% B-13 Wallpaper,Gray Carbonates Binder/Filler 10% LAYER 2 No None Detected Cellulose Fiber 1% Mastic,Yellow Carbonates Quartz Binder/Filler 99% Page 3 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax: (480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-014 LAYER 1 No None Detected Cellulose Fiber 90% B-14 Wallpaper,Gray Carbonates Binder/Filler 10% LAYER 2 No None Detected Joint Compound,White Carbonates Mica Quartz Binder/Filler 100% 0293300-015 LAYER 1 Yes Chrysotile 3% B-15 Joint Compound,White Carbonates Mica Quartz Binder/Filler 97% LAYER 2 No None Detected Cellulose Fiber 10% Sheetrock,White/Brown Gypsum Carbonates Quartz Mica 90% 0293300-016 LAYER 1 Yes Chrysotile 3% B-16 Joint Compound,White Carbonates Mica Quartz Binder/Filler 97% LAYER 2 No None Detected Cellulose Fiber 10% Sheetrock,White/Brown Gypsum Carbonates Quartz Mica 90% • Page 4 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax: (480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-017 LAYER 1 No None Detected B-17 Joint Compound,White Carbonates Mica Quartz Binder/Filler 100% LAYER 2 No None Detected Cellulose Fiber 10% Sheetrock,White/Brown Gypsum Carbonates Quartz Mica 90% 0293300-018 LAYER 1 No None Detected B-18 Ceramic Tile,Gray/Red Gypsum Quartz Binder/Filler 100% LAYER 2 No None Detected Mastic,Tan Carbonates Quartz Binder/Filler 100% 0293300-019 LAYER 1 No None Detected B-19 Ceramic Tile,Gray/Red Gypsum Quartz Binder/Filler 100% LAYER 2 No None Detected Mastic,Tan Carbonates Quartz Binder/Filler 100% 0293300-020 Grout,Gray No None Detected B-20 Quartz Gypsum Carbonates Mica Binder/Filler 100% Page 5 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax:(480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-021 Grout,Gray No None Detected B-21 Quartz Gypsum Carbonates Mica Binder/Filler 100% 0293300-022 LAYER 1 No None Detected B-22 Ceramic Tile,Brown Gypsum Quartz Binder/Filler 100% LAYER 2 No None Detected Grout,Gray Quartz Gypsum Carbonates Mica Binder/Filler 100% 0293300-023 LAYER 1 No None Detected B-23 Ceramic Tile, Brown Gypsum Quartz Binder/Filler 100% LAYER 2 No None Detected Grout,Gray Quartz Gypsum Carbonates Mica Binder/Filler 100% 0293300-024 Grout,Gray No None Detected B-24 Quartz Gypsum Carbonates Mica Binder/Filler 100% Page 6 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax:(480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-025 Grout,Gray No None Detected B-25 Quartz Gypsum Carbonates Mica Binder/Filler 100% 0293300-026 Cement,Gray No None Detected B-26 Quartz Gypsum Carbonates Mica Binder/Filler 100% 0293300-027 Cement,Gray No None Detected B-27 Quartz Gypsum Carbonates Mica Binder/Filler 100% 0293300-028 LAYER 1 No None Detected B-28 Square Pattern Texture/Paint, Carbonates Off White Perlite Note:Layer is mainly Paint-little Quartz Texture present Binder/Filler 100% LAYER 2 No None Detected Cellulose Fiber 10% Sheetrock,Off White/Brown Fibrous Glass 2% Gypsum Carbonates Quartz Mica 88% LAYER 3 Yes Chrysotile 3% Joint Compound,White Carbonates Mica Quartz Perlite Binder/Filler 97% Page 7 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax: (480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-029 LAYER 1 No None Detected B-29 Square Pattern Texture/Paint, Carbonates Off White Perlite Note:Layer is mainly Paint-little Quartz Texture present Binder/Filler 100% LAYER 2 No None Detected Cellulose Fiber 10% Sheetrock,Off White/Brown Fibrous Glass 2% Gypsum Carbonates Quartz Mica 88% LAYER 3 No None Detected Joint Compound,White Carbonates Perlite Quartz Binder/Filler 100% 0293300-030 LAYER 1 No None Detected B-30 Square Pattern Texture/Paint, Carbonates Off White Perlite Note:Layer is mainly Paint-little Quartz Texture present Binder/Filler 100% LAYER 2 No None Detected Cellulose Fiber 10% Sheetrock,Off White/Brown Fibrous Glass 2% Gypsum Carbonates Quartz Mica 88% LAYER 3 No None Detected Joint Compound,White Carbonates Perlite Quartz Binder/Filler 100% Page 8 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax:(480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-031 LAYER 1 No None Detected B-31 Square Pattern Texture/Paint, Carbonates Off White Perlite Note:Layer is mainly Paint-little Quartz Texture present Binder/Filler 100% LAYER 2 No None Detected Cellulose Fiber 10% Sheetrock,Off White/Brown Gypsum Carbonates Quartz Mica 90% LAYER 3 No None Detected Joint Compound,White Carbonates Perlite Quartz Binder/Filler 100% 0293300-032 LAYER 1 No None Detected B-32 Square Pattern Texture/Paint, Carbonates Off White Perlite Note:Layer is mainly Paint-little Quartz Texture present Binder/Filler 100% LAYER 2 No None Detected Cellulose Fiber 10% Sheetrock,Off White/Brown Gypsum Carbonates Quartz Mica 90% LAYER 3 No None Detected Joint Compound,White Carbonates Perlite Quartz Binder/Filler 100% 0293300-033 Popcorn Texture,White Yes Chrysotile 5% B-33 Carbonates Mica Quartz Binder/Filler 95% Page 9 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax:(480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-034 Popcorn Texture,White Yes Chrysotile 5% B-34 Carbonates Mica Quartz Binder/Filler 95% 0293300-035 Popcorn Texture,White Yes Chrysotile 5% B-35 Carbonates Mica Quartz Binder/Filler 95% 0293300-036 LAYER 1 No None Detected Cellulose Fiber 90% B-36 Wallpaper,Brown Carbonates 10% LAYER 2 Yes Chrysotile 3% Joint Compound,White Carbonates Mica Quartz Binder/Filler 97% LAYER 3 No None Detected Cellulose Fiber 10% Sheetrock,Off White/Brown Fibrous Glass 2% Gypsum Carbonates Quartz Mica 88% Page 10 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax: (480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-037 LAYER 1 No None Detected Cellulose Fiber 90% B-37 Wallpaper, Brown Carbonates 10% LAYER 2 Yes Chrysotile 3% Joint Compound,White Carbonates Mica Quartz Binder/Filler 97% LAYER 3 No None Detected Cellulose Fiber 10% Sheetrock,Off White/Brown Fibrous Glass 2% Gypsum Carbonates Quartz Mica 88% 0293300-038 LAYER 1 No None Detected Cellulose Fiber 90% B-38 Wallpaper,Brown Carbonates 10% LAYER 2 Yes Chrysotile 3% Joint Compound,White Carbonates Mica Quartz Binder/Filler 97% LAYER 3 No None Detected Cellulose Fiber 10% Sheetrock,Off White/Brown Fibrous Glass 2% Gypsum Carbonates Quartz ' Mica 88% Page 11 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax:(480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-039 LAYER 1 Yes Chrysotile 3% B-39 Joint Compound,White Carbonates Mica Quartz Binder/Filler 97% LAYER 2 Yes Chrysotile 3% Texture,Off White Carbonates Mica Quartz Perlite Binder/Filler 97% 0293300-040 LAYER 1 No None Detected Synthetic Fiber 80% B-40 Carpet,White/Gray Foam Carbonates Binder/Filler 20% LAYER 2 Yes Chrysotile 3% Mastic,Tan/Black Carbonates Quartz Binder/Filler 97% 0293300-041 LAYER 1 No None Detected Synthetic Fiber 80% B-41 Carpet,White/Gray Foam Carbonates Binder/Filler 20% LAYER 2 Yes Chrysotile 3% Mastic,Tan/Black Carbonates Quartz Binder/Filler 97% Page 12 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax:(480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-042 LAYER 1 No None Detected Synthetic Fiber 80% B-42 Carpet,White/Gray Foam Carbonates Binder/Filler 20% LAYER 2 Yes Chrysotile 3% Mastic,Tan/Black Carbonates Quartz Binder/Filler 97% 0293300-043 LAYER 1 No None Detected Synthetic Fiber 80% B-43 Carpet,White/Gray Foam Carbonates Binder/Filler 20% LAYER 2 Yes Chrysotile 3% Mastic,Tan/Black Carbonates Quartz Binder/Filler 97% 0293300-044 LAYER 1 No None Detected B-44 Mastic,Tan Carbonates Quartz Binder/Filler 100% LAYER 2 No None Detected Leveling Compound,Gray Carbonates Gypsum Quartz Binder/Filler 100% Page 13 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax: (480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-045 LAYER 1 No None Detected B-45 Mastic,Tan Carbonates Quartz Binder/Filler 100% LAYER 2 No None Detected Leveling Compound,Gray Carbonates Gypsum Quartz Binder/Filler 100% 0293300-046 LAYER 1 No None Detected B-46 Mastic,Tan Carbonates Quartz Binder/Filler 100% LAYER 2 No None Detected Leveling Compound,Gray Carbonates Gypsum Quartz Binder/Filler 100% 0293300-047 LAYER 1 Yes Chrysotile 15% Cellulose Fiber 5% B-47 Sheet Vinyl,TanNvhite Carbonates Quartz Binder/Filler 80% LAYER 2 Yes Chrysotile 3% Mastic,Yellow Carbonates Note:Difficult to separate Quartz adjacent layer Binder/Filler 97% Page 14 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax:(480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-048 LAYER 1 Yes Chrysotile 15% Cellulose Fiber 5% B-48 Sheet Vinyl,TanI Nhite Carbonates Quartz Binder/Filler 80% LAYER 2 Yes Chrysotile 3% Mastic,Yellow Carbonates Note:Difficult to separate Quartz adjacent layer Binder/Filler 97% 0293300-049 LAYER 1 Yes Chrysotile 3% B-49 Floor Tile,Tan/Black Carbonates Quartz Binder/Filler 97% LAYER 2 Yes Chrysotile 5% Mastic,Black Carbonates Quartz Binder/Filler 95% 0293300-050 LAYER 1 Yes Chrysotile 3% B-50 Floor Tile,Tan/Black Carbonates Quartz Binder/Filler 97% LAYER 2 Yes Chrysotile 5% Mastic,Black Carbonates Quartz Binder/Filler 95% 0293300-051 LAYER 1 Yes Chrysotile 2% Cellulose Fiber 1ok B-51 Texture/Paint,Yellow Carbonates Note:Layer is mainly Paint Quartz Binder/Filler 97% LAYER 2 No None Detected Cellulose Fiber 10% Sheetrock,Off White/Brown Gypsum Carbonates Quartz Mica 90% Page 15 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax:(480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-052 LAYER 1 Yes Chrysotile 3% Texture/Paint,Yellow B-52 Carbonates Note:Layer is mainly Paint-little Mica Texture present Quartz Binder/Filler 97% LAYER 2 No None Detected Cellulose Fiber 10% Sheetrock,Off White/Brown Gypsum Carbonates Quartz Mica 90% 0293300-053 LAYER 1 Yes Chrysotile 3% Texture/Paint,Yellow B-53 Carbonates Note:Layer is mainly Paint-little Mica Texture present Quartz Binder/Filler 97% LAYER 2 No None Detected Cellulose Fiber 10% Sheetrock,Off White/Brown Gypsum Carbonates Quartz Mica 90% 0293300-054 LAYER 1 No None Detected Cellulose Fiber 30% B-54 Insulation Wrap,White/Silver Aluminum Carbonates Binder/Filler 70% LAYER 2 No None Detected Fibrous Glass 100% Insulation,Yellow Page 16 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street,Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax: (480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-055 LAYER 1 No None Detected Cellulose Fiber 30% B-55 Insulation Wrap,White/Silver Aluminum Carbonates Binder/Filler 70% LAYER 2 No None Detected Fibrous Glass 100% Insulation,Yellow LAYER 3 No None Detected Fibrous Glass 40% Felt,Black Carbonates Binder/Filler 60% 0293300-056 Mud Joint Packing,Gray No None Detected Mineral Wool 30% B-56 Carbonates Gypsum Quartz Binder/Filler 70% 0293300-057 Mud Joint Packing,Gray No None Detected Mineral Wool 30% B-57 Carbonates Gypsum Quartz Binder/Filler 70% 0293300-058 LAYER 1 No None Detected B-58 Covebase,Brown Carbonates Quartz Binder/Filler 100% LAYER 2 Yes Tremolite <1% Talc 2% Mastic,Dk.Brown Non-Fibrous Tremolite 2% Carbonates Quartz Binder/Filler 95% Page 17 of 18 EMC LABS, INC. Laboratory Report 9830 S.51st Street, Suite B109, Phoenix, AZ 85044 0293300 Phone: 800-362-3373 or 480-940-5294-Fax: (480)893-1726 Bulk Asbestos Analysis by Polarized Light Microscopy NVLAP#101926-0 Client: McCRINK CONSULTING, LLC Job#/P.O. #: MC-23-060 Address: 660 E. SAND WEDGE DRIVE Date Received: 06/14/2023 POST FALLS, ID 83854 Date Analyzed: 06/16/2023 Collected: 06/12/2023 Date Reported: 06/16/2023 Project Name: 10303 E. SPRAGUE AVE., SPOKANE Submitted By: KEVIN McCRINK VALLEY, WA Collected By: Address: EPA Method: App.E to Sub.E of 40 CFR Part 763 and EPA/600/R-93 Lab ID Sample Layer Name/ Asbestos Asbestos Type Non-Asbestos Client ID Location Sample Description Detected (%) Constituents 0293300-059 LAYER 1 No None Detected B-59 Covebase, Brown Carbonates Quartz Binder/Filler 100% LAYER 2 Yes Tremolite <1% Talc 2% Mastic,Dk.Brown Non-Fibrous Tremolite 2°/d Carbonates Quartz Binder/Filler 95% (445‘1 -- 411 Analyst- Matt Kettler Signatory-Lab Director-Kurt Kettler Distinctly stratified,easily separable layers of samples are analyzed as subsamples of the whole and are reported separately far each discernible layer.All analyses are derived from calibrated visual estimate and measured in area percent unless otherwise noted.The report applies to the standards or procedures identified and to the sample(s)tested.The test results are not necessarily indicative or representative of the qualities of the lot from which the sample was taken or of apparently identical or similar products,nor do they represent an ongoing quality assurance program unless so noted.This report is for the exclusive use of the addressed client and will not be reproduced wholly or in part for adverfising or other purposes over our signature or in connection with our name without special written permission.The report shall not be reproduced except in full,without written approval by our laboratory.The samples not destroyed in testing are retained a maximum of sixty days.The laboratory measurement of uncertainty for the test method is approximately less than 1 by area percent.Accredited by the National Institute of Standards and Technology,Voluntary Laboratory Accreditation Program for selected test method(s)for asbestos.The accreditation or any reports generated by this laboratory in no way constitutes or implies product certification,approval,or endorsement by the National Institute of Standards and Technology.The report must not be used by the client to claim product certlfication,approval,or endorsement by NVLAP,NIST,or any agency of the Federal Government. Page 18 of 18 Page 1 1 of LI CHAIN OF CUSTODY LAB#'(9G' -.e1,0, EMC Laboratories Jp ,,, 9830 S. 51ST St.,Ste R-109 TAT: � < r Phoenix,AZ 85044 � (800) 362-3373 Fax(480) 893-1726 Rec' ci: JUN 14 A.M, COMPANY NAME: McCrink Consulting, LLC BILLTO: (If Different Location) 660 E. Sand Wedge Drive Post Falls, ID 83854 CONTACT: Kevin McCrink Phone/Fax: (509) 991-7357 Email: envriskmgm@aol.com Now Accepting: VISA-MASTERCARD Price Quoted: $ _ /Sample $ /Layers COMPLETE ITEMS 1-4: (Failure to complete any items may cause a delay in processing or analyzing your samples) 1. TURNAROUND TIME: [4hr rush} [[8hr rush} [1-Day] [3-Day] ] [8016-Day] [6-10 Day] ****Prior confirmation of turnaround time is-required ****Additional charges for rush analysis(please call marketing department for pricing details) ****Laboratory analysis maybe subject , .e ay I : edit terms are not met 2. TYPE OF ANALYSIS: c ulk-PLM [Air-PCM] [Lead] [Point Count] [Fungi:AOC,W-C, Bulk,Swab,Tape] 3. DISPOSAL INSTRUC I Oi -. Dispose of samples at EMC] / [Return samples to me at my expense] (If you do not indicate preference,EMC will dispose of samples 60 days from analysis.) Project Name: 10303 P. l CaV Avg. 5Pog-Aloe YAt.. ,,f , K1A P.O. Number: Project Number:_ Me - MC -2&- 01,6 _ EMC CLIENT DATE& LOCATION/MATERIAL Samples SAMPLE# SAMPLE# TIME TYPE Accepted SAMPLED Yes / No QoU N�r -12-zJ �b t >g-z \ ' N 3, a - 3 • N — -- 1 N l '( T2DCtC N - _+. .e' N / e N - i( q 1, .N IY N ��1 n 3-!1 T-A- ) w Prl-t- 14 r N la E-.)a ) 1 i ti N 13-13 G P wAAA-PAPO , N ?^15 1 of 6r-r CoM fU/tJA 1 S �ie_c 1G,• f N -1 SPECIAL INSTRUCTIONS: .� Sample Collector: (Print) Kevin McCrink (Signature) � �, `, /_ Relinquished by: ''''''"'� Date/Time:f) vly1- �RPreived by bA Y e'"--U" — Date/Time: U Relinquished by: Lbn'u7 Date/Time:l[a ` Received by: _Date/Tim - Relinquished by: Date/Time Received by: Date ** In the event of any dispute between the above parties for these services or otherwise, parties agree that jurisdiction and venue will be in Phoenix,Arizona and prevailing party will be entitled to attorney's fees and court costs. I Page � ofLi CHAIN OF CUSTODY LAB# :0)9 3fl`v EMC La16T St, es TAT: a ~� 9830 S. 51sT St.,Ste R-109 --� U Phoenix,AZ 85044 (800) 362-3373 Fax(480)893-1726 Rec'd: ;� f ,LC 4 AP. COMPANY NAME: McCrink Consulting, LLC BILL TO: (If Different Location) 660 E. Sand Wedge Drive Post Falls, ID 83854 CONTACT: Kevin McCrink Phone/Fax: (509) 991-7357 Email: envriskmgm@aol.com Now Accepting: VISA-MASTERCARD Price Quoted: $ /Sample $ / Layers COMPLETE ITEMS 1-4: (Failure to complete any items may cause a delay in processing or analyzing your samples) 1. TURNAROUND TIME: [4hr rush} [[8hr rush} [1-Day] 2-Day) [3-Day] ] [8016-Day] [6-10 Day] ****Prior confirmation of turnaround time is required ****Additional charges for rush analysis(please call marketing department for pricing details) ****Laboratory analysis may be subject to d I dit terms are not met 2. TYPE OF ANALYSIS: [B -PL [Air-PCM] [Lead] [Point Count] [Fungi: AOC,W-C, Bulk, Swab, Tape] 3. DISPOSAL INSTRUCTIO . [Dispose of samples at EMC] / [Return samples to me at my expense] (If you do not indicate preference,EMC will dispose of samples 60 days from analysis.) Project Name: P.O. Number: Project Number:__MC-21- EMC CLIENT DATE& LOCATION/MATERIAL Samples SAMPLE# SAMPLE# TIME Ye TYPE Accepted/ s SAMPLED f No a (o- 1 -1,3 Solr cbmfoJNU 1 s HiErie- cic 1 N ) / J 3 r _ ) ' 4 oratc1if (l: �ciz_ 1 /to !.As Lie '1 N a) ( 1 N �' oW GO-4i 11 c- -iLE j l .t e0L)T 1 N -2Z �'(t )L l3•Z3 1 I , l r , N r f N 1 / -21s o1,16F,- ?a-i'elul - (ilk /Sii -rc)6 N Z 'B-2q 1 J 1 1 N SPECIAL.INSTRUCTIONS: ,,,w�,� Sample Collector: (Print) Kevin McCrink Relinquished by: (Signatures - 1 DateiTime: `Za�Received b Date/Time: /Aar? Dhed b : Date/Time: 1 41 Received by:. Date/Tim 1 �� Rellnquls y Date/Ti by: _ Date/Time Received by: - — ** In the event of any dispute between the above parties for these services or otherwise, parties agree that jurisdiction and venue will be in Phoenix,Arizona and prevailing party will be entitled to attorney's fees and court costs. Page 3 of i_ CHAIN OF CUSTODY T,AR#: cP,'3 DC EMC Laboratories 9 9830 S. 51ST St.,Ste R-109 TAT: 1�O Phoenix,AZ 85044 (800) 362-3373 Fax(480) 893-1726 Rea' d: alki 14 4 ), COMPANY NAME: McCrink Consulting, LLC BILL TO: (If Different Location) 660 E. Sand Wedge Drive Post Falls, ID 83854 CONTACT: Kevin McCrink Phone/Fax: (509) 991-7357 Email: envriskmgm@aol.com Now Accepting: VISA-MASTERCARD Price Quoted: $ /Sample $__ - / Layers COMPLETE ITEMS 1-4: (Failure to complete any items may cause a delay in processing or analyzing your samples) 1. TURNAROUND TIME: [4hr rush} [[8hr rush} [1-Day] 2-Da [3-Day] ] [8016-Day] [6-10 Day] ****Prior confirmation of turnaround time is required ****Additional charges for rush analysis(please call marketing department for pricing details) ****Laboratory analysis may be subject to d y if cr dit terms are not met 2. TYPE OF ANALYSIS: [B k-PLM [Air-PCM] [Lead] [Point Count] [Fungi:AOC,W-C, Bulk, Swab,Tape] 3. DISPOSAL INSTRUCTION : [Dispose of samples at EMC] / [Return samples to me at my expensBI (If you do not indicate preference,EMC will dispose of samples 60 days from analysis.) Project Name: I i P.O. Number: Project Number MC-21- i EMC CLIENT DATE& LOCATION/MATERIAL Samples SAMPLE# SAMPLE# TIME TYPE Accepted SAMPLED Yes / No \l 4-31 CD-t2. Pa .44 194 7-64r- �j` ec�< N r U � 8 'SZ ( I I G J N $-3 y3 PGts `�Xru N �3 t Y N B-;s- , 4 N C 13 r36 e..0W rJ WALLPAYeiLAStrer Com pvrvA 153.},Ell✓i N 37 / 1 J ' L 7 i N N -3 rC1 C Orvfoos. ! 5 0-,e-`e N 0 � I 0 er 1 - r- - /11 5l)i_ N �I Q "4i t(I E / I ( N N 1 rA 5I1 L {'('n"`'{. J,e-",✓f a coytiootJAP N SPECIAL INSTRUCTIONS: Sample Collector: (Print) Kevin McCrink ___ (Signature/ Relinquished by: - - '''"'�`""` -' Date/Time: -1Z `Z3 eceived by: f Date/Time:01 /� Relinquished by:_ "" CdCti69'-' Date/Time: 1 Received by: Date/Tim J Relinquished by: Date/Time Received by: Date i * In the event of any dispute between the above parties for these services or otherwise, parties agree that jurisdiction and venue will be in Phoenix,Arizona and prevailing party will be entitled to attorney's fees and court costs. Page of LA CHAIN OF CUSTODY T.AR# ;33 EMC Laboratories �,� (� 9830 S. 51sr St.,Ste R-109 TAT: `--X Ok.°"- 1 Phoenix,AZ 85044 (800) 362-3373 Fax(480) 893-1726 Rec'd: tklt$ili 4 /th, COMPANY NAME: McCrink Consulting, LLC BILL TO: (If Different Location) 660 E. Sand Wedge Drive Post Falls, ID 83854 CONTACT: Kevin McCrink Phone/Fax: (509) 991-7357 Email: envriskmgm@aol.com Now Accepting: VISA-MASTERCARD Price Quoted: $ /Sample $ / Layers COMPLETE ITEMS 1-4: (Failure to complete any items may cause elay in processing or analyzing your samples) 1. TURNAROUND TIME: [4hr rush} [[8hr rush) [1-Day] [2-D9 , [3-Day] ] [8016-Day] [6-10 Day] ****Prior confirmation of turnaround time is required ****Additional charges for rush analysis(please call marketing department for pricing details) ****Laboratory analysis may be subject t deter if it terms are not met 2. TYPE OF ANALYSIS: [ ulk-PLM] [Air-PCM] [Lead] [Point Count] [Fungi:AOC,W-C, Bulk, Swab,Tape] 3. DISPOSAL INSTRUCTIO Dispose of samples at EMC] / [Return samples to me at my expense] (If you do not indicate preference,EMC will dispose of samples 60 days from analysis.) Project Name: P.O. Number: Project Number:___MC-21- EMC CLIENT DATE& LOCATION/MATERIAL Samples SAMPLE# SAMPLE# TIME TYPE Accepted SAMPLED Yes / No $-`t 6 G'j z.z3 !Ap lvt r16126) -1 Fiv�clp..,S Co in - N 1k $ -9 7 -MO-t 14 Stifer 1J1IV Tiatt' p74fi1 N � _ yg t 1 1 j / / N LQO) i -Li/ Apr ti r {>3LAtac- f-L002. rii.E l F314 C )V 4457c N SO -56 1 1 ! 1 ) I N El -S/ "V 0 15 u N i YN n 3-53 / Y N j 5U B -- -Y LS v1-1 (�.T( / LI 't•0 GJ - LNscx. -7,UJJ Y N 6 ♦ /)f� / L 1 p/'� - t ( Y N lJ la f 56 ry r"� t-( 01/ �ficie-l(\ 1 Y N 51 3 _5 ) 1. 1 } YN - • C6c VPi6 aotga,s N Tl� Y N i 5c ) .-61 f i i t / 1Y N Y N i SPECIAL INSTRUCTIONS: Sample Collector: (Print) Kevin McCrink ( �(Signature, y�� Relinquished by: 10 �' "'-c. rC_, Date/Time:Jor�2'Z Received by""nP42� Date/Time:I,pi l-c"Ii Relinquished by: � afar— Date/Time!t��,"I" Ara eceived by: Date/Tim ,11 Relinquished by: Date/Time Received by: Date i e ** In the event of any dispute between the above parties for these services or otherwise, parties agree that jurisdiction and venue will be in Phoenix,Arizona and prevailing party will be entitled to attorney's fees and court costs. •K San ir Technologies Laboratory The Identification Specialists Analysis Report prepared for McCrink Consulting, LLC Report Date:4/11/2024 Project Name: 10303 E Sprague Ave Demo SanAir ID#: 24020176 L1--J TESTING NVLAP LAB CODE 200870-0 10501 Trade Court North Chesterfield, Virginia 23236 888.895.1177 804.897.1177 fax:804.897.0070 IAQ@SanAir.com SanAiccom Page 1 of 9 SanAir ID Number 24020176 SanAIr FINAL REPORT Technologies Laboratory 4/11/2024 8:35:06 AM Name: McCrink Consulting, LLC Project Number: Address: 660 E. Sand Wedge Drive P.O. Number: Post Falls, ID 83854 Project Name: 10303 E Sprague Ave Demo Phone: 509-991-7357 Collected Date:4/9/2024 Received Date:4/10/2024 10:15:00 AM Dear Kevin McCrink, We at SanAir would like to thank you for the work you recently submitted. The 23 sample(s)were received on Wednesday,April 10, 2024 via UPS. The final report(s) is enclosed for the following sample(s): BX-1, BX-2, BX-3, BX-4, BX-5, BX-6, BX-7, BX-8, BX-9, BX-10, BX-11, BX-12, BX-13, BX-14, BX-15, BX-16, BX-17, BX-18, BX-19, BX-20, BX-21, BX-22, BX-23. These results only pertain to this job and should not be used in the interpretation of any other job. This report is only complete in its entirety. Refer to the listing below of the pages included in a complete final report. Sincerely, 1c142.44141.-`,Aft�i f eYL�� Sandra Sobrino " Asbestos & Materials Laboratory Manager SanAir Technologies Laboratory Final Report Includes: -Cover Letter -Analysis Pages -Disclaimers and Additional Information Sample conditions: -23 samples in Good condition. 10501 Trade Ct., N. Chesterfield,VA 23236 1804.897.1177 I Fax: 804.897.0070 I www.SanAir.com I IAQ@SanAir.com Page 2 of 9 SanAir ID Number 24020176 San iSanAir FINAL REPORT Technologies Laboratory 4/11/2024 8:35:06 AM Name: McCrink Consulting, LLC Project Number: Address: 660 E. Sand Wedge Drive P.O. Number: Post Falls, ID 83854 Project Name: 10303 E Sprague Ave Demo Phone: 509-991-7357 Collected Date:4/9/2024 Received Date:4/10/2024 10:15:00 AM Analyst: Forman, Sydney Asbestos Bulk PLM EPA 600/R-93/116 Stereoscopic Components SanAir ID/Description Appearance %Fibrous %Non-fibrous Asbestos Fibers BX-1/24020176-001 Silver 100%Other None Detected Paint/Built Up Roofing,Paint Non-Fibrous Homogeneous BX-1/24020176-001 Black 100%Other None Detected Paint/Built Up Roofing,Tar Non-Fibrous Homogeneous BX-1/24020176-001 Black 30%Glass 70%Other None Detected Paint/Built Up Roofing,Felt Non-Fibrous Homogeneous BX-2/24020176-002 Silver 100%Other None Detected Paint/Built Up Roofing,Paint Non-Fibrous Homogeneous BX-2/24020176-002 Black 100%Other None Detected Paint/Built Up Roofing,Tar Non-Fibrous Homogeneous BX-2/24020176-002 Black 30%Glass 70%Other None Detected Paint/Built Up Roofing,Felt Non-Fibrous Homogeneous BX-3/24020176-003 Gray 96%Other 4%Chrysotile Mastic/Built Up Roofing,Mastic Non-Fibrous Heterogeneous BX-3/24020176-003 White 20%Glass 80%Other None Detected Mastic/Built Up Roofing,Shingle Non-Fibrous Heterogeneous BX-3/24020176-003 Black 100%Other None Detected Mastic/Built Up Roofing,Tar Non-Fibrous Homogeneous BX-4/24020176-004 Gray 96%Other 4%Chrysotile Mastic Non-Fibrous Heterogeneous Analyst: 0 jolt/new. Approved Signatory: Analysis Date: 4/10/2024 Date: 4/11/2024 Page 3 of 9 SanAir ID Number Sank����• 24020176 FINAL REPORT Technologies Laboratory 4/11/2024 8:35:06 AM Name: McCrink Consulting, LLC Project Number: Address: 660 E. Sand Wedge Drive P.O. Number: Post Falls, ID 83854 Project Name: 10303 E Sprague Ave Demo Phone: 509-991-7357 Collected Date:4/9/2024 Received Date:4/10/2024 10:15:00 AM Analyst: Forman, Sydney Asbestos Bulk PLM EPA 600/R-93/116 Stereoscopic Components SanAir ID/Description Appearance %Fibrous %Non-fibrous Asbestos Fibers BX-5/24020176-005 Not Analyzed Mastic BX-6/24020176-006 Silver 100%Other < 1%Chrysotile Paint/Mastic,Paint Non-Fibrous Homogeneous BX-6/24020176-006 Black 97%Other 3%Chrysotile Paint/Mastic,Mastic Non-Fibrous Homogeneous BX-7/24020176-007 Silver 100%Other < 1%Chrysotile Paint/Mastic,Paint Non-Fibrous Homogeneous BX-7/24020176-007 Not Analyzed Paint/Mastic,Mastic BX-7/24020176-007 White 20%Glass 80%Other None Detected Paint/Mastic,Shingle Non-Fibrous Heterogeneous BX-8/24020176-008 Black 70%Cellulose 30%Other None Detected Tar Paper Fibrous Homogeneous BX-9/24020176-009 Black 70%Cellulose 30%Other None Detected Tar Paper Fibrous Homogeneous BX-10/24020176-010 Black 70%Cellulose 30%Other None Detected Tar Paper Fibrous Homogeneous BX-11/24020176-011 Black 70%Cellulose 30%Other None Detected Tar Paper Fibrous Homogeneous Analyst: 4eitivai ,10'7��VY - Approved Signatory: Analysis Date: 4/10/2024 Date: 4/11/2024 10501 Trade Ct., N. Chesterfield,VA 23236 1804.897.1177 I Fax: 804.897.0070 I www.SanAir.com I IAQ@SanAir.com Page 4 of 9 SanAir ID Number \ ... 24020176 Sani-ur FINAL REPORT Technologies Laboratory 4/11/2024 8:35:06 AM Name: McCrink Consulting, LLC Project Number: Address: 660 E. Sand Wedge Drive P.O. Number: Post Falls, ID 83854 Project Name: 10303 E Sprague Ave Demo Phone: 509-991-7357 Collected Date:4/9/2024 Received Date:4/10/2024 10:15:00 AM Analyst: Forman, Sydney Asbestos Bulk PLM EPA 600/R-93/116 Stereoscopic Components SanAir ID/Description Appearance %Fibrous %Non-fibrous Asbestos Fibers BX-12/24020176-012 Black 100%Other None Detected Mortar Non-Fibrous Homogeneous BX-13/24020176-013 Black 100%Other None Detected Mortar Non-Fibrous Homogeneous BX-14/24020176-014 White 3%Cellulose 97%Other None Detected Caulk Non-Fibrous Heterogeneous BX-15/24020176-015 White 3%Cellulose 97%Other None Detected Caulk Non-Fibrous Heterogeneous BX-16/24020176-016 Black 100%Other None Detected Roof Membrane Non-Fibrous Homogeneous BX-17/24020176-017 Black 100%Other None Detected Roof Membrane Non-Fibrous Homogeneous BX-18/24020176-018 White 100%Other None Detected Caulk/Sealer,Caulk Non-Fibrous Homogeneous BX-18/24020176-018 Black 100%Other None Detected Caulk/Sealer,Sealer Non-Fibrous Homogeneous BX-19/24020176-019 Black 100%Other None Detected Sealer Non-Fibrous Homogeneous BX-20/24020176-020 Brown 100%Other None Detected Window Sealer Non-Fibrous Homogeneous Analyst: 4emexa, ioWn,{4- Approved Signatory: p i_i_i____AA. Analysis Date: 4/10/2024 Date: 4/11/2024 10501 Trade Ct., N. Chesterfield, VA 23236 1804.897.1177 I Fax: 804.897.0070 I www.SanAir.com i IAQ@SanAir.com Page 5 of 9 SanAir ID Number 24020176 San i Ir FINAL REPORT Technologies Laboratory 4/11/2024 8:35:06 AM Name: McCrink Consulting, LLC Project Number: Address: 660 E. Sand Wedge Drive P.O. Number: Post Falls, ID 83854 Project Name: 10303 E Sprague Ave Demo Phone: 509-991-7357 Collected Date:4/9/2024 Received Date:4/10/2024 10:15:00 AM Analyst: Forman, Sydney Asbestos Bulk PLM EPA 600/R-93/116 Stereoscopic Components SanAir ID/Description Appearance %Fibrous %Non-fibrous Asbestos Fibers BX-21/24020176-021 Brown 100%Other None Detected Window Sealer Non-Fibrous Homogeneous BX-22/24020176-022 Various 100%Other None Detected Concrete Non-Fibrous Heterogeneous BX-23/24020176-023 Various 100%Other None Detected Concrete Non-Fibrous Heterogeneous Analyst: Approved Signatory: Analysis Date: 4/10/2024 Date: 4/11/2024 10501 Trade Ct., N. Chesterfield, VA 23236 1804.897.1177 I Fax: 804.897.0070 I www.SanAir.com I IAQ@SanAir.com Page 6 of 9 Disclaimer This report is the sole property of the client named on the SanAir Technologies Laboratory chain- of-custody(COC). Results in the report are confidential information intended only for the use by the customer listed on the COC. Neither results nor reports will be discussed with or released to any third party without our client's written permission. The final report shall not be reproduced except in full without written approval of the laboratory to assure that parts of the report are not taken out of context. This report and any information contained within shall not be edited, altered, or modified in any way by any persons or agencies receiving, viewing, distributing, or otherwise possessing a copy of this final report. The laboratory reserves the right to perform amendments to any finalized report, of which shall supersede and make obsolete any previous editions. Such changes, modifications, additions, or deletions shall be effective immediately upon notice thereof, which may be given by means including but not limited to posting on the SanAir client portal website, electronic or conventional mail, or by any other means. The information provided in this report applies only to the samples submitted and is relevant only for the date, time, and location of sampling. The accuracy of the results is dependent upon the client's sampling procedure and information provided to the laboratory by the client on the COC. SanAir assumes no responsibility for the sampling procedure and will provide evaluation reports based solely on the sample(s) in the condition in which they arrived at the laboratory and information provided by the client on the COC, such as: project number, project name, collection dates, po number, special instructions, samples collected by, sample numbers, sample identifications, sample type, selected analysis type, flow rate, total volume or area, and start stop times that may affect the validity of the results in this report. Samples were received in good condition unless otherwise noted on the report. SanAir assumes no responsibility or liability for the manner in which the results are used or interpreted. This report does not constitute nor shall not be used by the client to claim product, process, system, or person certification, approval, or endorsement by NVLAP, NIST, NELAC, AIHA LAP, LLC or any other U.S. governmental agencies and may not be accredited by every local, state, and federal regulatory agencies. Samples are held for a period of 60 days. Fibers smaller than 5 microns cannot be seen with this method due to scope limitations. For NY state samples, method EPA 600/M4-82-020 is performed. NYELAP Disclaimer: Polarized- light microscopy is not consistently reliable in detecting asbestos in floor covering and similar non-friable organically bound materials. Quantitative transmission electron microscopy is currently the only method that can be used to determine if this material can be considered or treated as non-asbestos containing. Asbestos Accreditations National Voluntary Laboratory Accreditation Program (NVLAP) Lab Code 200870-0 City of Philadelphia Department of Public Health Air Management Services, Certification#ALL-460 Commonwealth of Pennsylvania Department of Environmental Protection Number 68-05397 California State Environmental Laboratory Accreditation Program Certificate Number 2915 Colorado Department of Public Health and Environment Registration Number AL-23143 Connecticut Department of Public Health Environmental Laboratory Registration Number PH-0105 Massachusetts Department of Labor Standards Asbestos Analytical Services License Number: AA000222 State of Maine Department of Environmental Protection License Number: LB-0075, LA-0084 New York State Department of Health Laboratory ID: 11983 State of Rhode Island Department of Health Certification No.: PCM00126, PLM00126, TEM00126 Texas Department of State Health Services License Number: 300440 Commonwealth of Virginia Department of Professional and Occupational Regulation Number: 3333000323 State of Washington Department of Ecology Laboratory ID: C989 State of West Virginia Bureau for Public Health Analytical Laboratory Number: LT000616 Vermont Department of Health License Number: Asb-Co-An-000006 Louisiana Department of Environmental Quality Al Number 212253, Certificate#05088 Revision Date: 4/18/2023 Page 7 of 9 �, , 10501 Trade Ct.,Suite 100 sattAirlfllHttmber N. Chesterfield,VA 23236 Asbestos ! )b,, © J 1 4 S�tnA i 804.897.117 (888.895.1177 Chain of Custody Fax Fax 804.897.0070 Form 140,Rev 7,10/2012012 Technologies Laboratory sanair.Con1 Company: McCrink Consulting, LLC Project#: :'ollectedby: 660 E. Sand Wedge Drive /003 e. $QRA6.Vt: AV1E- D 509-991-7357 Address: Project Name: q Phone#: City,St.,Zip: Post Falls, ID 83854 . Date Collected: J _q P-I Fax#: State of Collection: Accountl: 4177 P.O.Number: Email: Bulk Air Soil ABB PLM EPA 600/R-93/1 16 ABA PCM NIOSH 7400 ABSE PLM EPA 600/R-93 116(Qual.) I 1 ABA-2 OSHA w'TWA* Stop U D Vermiculite L ABEPA PLM EPA 400 Point Count LI, ABTEM TEM AHERA n ABB PLM EPA 600/R-93;116 I ABBIK PLM EPA 1000 Point Count n ABATN TEM NIOSH 7402 n ABEPA3 ,PLM EPA 400 Point Count ABBEN PLM EPA NOB** n ABT2 TEM Level II n ABCM Cincinnati Method n ABBCH TEM Chatfield** n Other: a Dust ABBTM TEM EPA NOB** New York ELAP ABWA TEM Wipe ASTM D-6480 El ABQ PLM Qualitative ABEPA2 NY ELAP 198.1 ABDMV TEM Microvac ASTM D-5755 ** Available on 24-hr.to 5-day TAT ABENY NY ELAP 198.6 PLM NOB El ABBNY NY ELAP 198.4 TEM NOB n Water Matrix Other ABHE EPA 100.2 P Positive Stop n , Turn Around 3 HR(4 IIR TEM) 0 6 HR(8HR TEM) 0 12 HR 0 I Day W Times 0 2 Days 0 3 Days 0 4 Days ❑ 5 Days ISpecial Instructions [ i Volume ` Sample Flow Start—Stop Sample# Sample ldentilication/Location or Area Date Rate* Time* -6X4 slcvee ?Astir IRulcrtie 2oog-1.14 iiVTz 3X-2 t 3 / , 1 8X 3 ray MAs�,c 1 �U>L1- 11PQov�,�s _ -B x-' 17 psis-6c. $X-S 1X-4 ssLva2 ?Awl-f VIAC4 M4Sric X. 7 1 t / 1 BX—$ -j4� Q 1 gsX_q I , t 8X-10 Pig ilt ? / $X- IZ, Ofisi 6ut-cv.. smear -4e R un i uished b Date Time ei •L b 4r y/ODate 4",' Time s If no technician is provided,then the primary contact for your account will be selected.Unless scheduled,the turnaround time for ali samples received after 3 pm EST will be logged in the next business day.Weekend or holiday work must be scheduled ahead of time and is charged at 150' of the 3hr TAT or a minimuni charge of S150. A courier charge will be applied for same day and one-day turnaround times for olrsite work.San_kir corers Ground and Next Day Air shipping.Shipments billed to SanAlr with a faster shipping rate will result in additional charges. Page of Page 8 of 9 qoa Q / 76 Form 140,Revision 1, 1/20/2017 Volume or Sample Flow Start—Stop Sample# Sample Identification/Location Area Date Rate* Time* IV Ai w4,-re cq()L4 BX_, I S'x - I(, ; , ... TO ��� X" 17 1 t 1 r CA . t- : g C VP I .X-2' iQoW w W lNS -.:1..` IIII .7 _ i l �1���� 1(-2.2-- La140.4-11 III____ Special Instructions I I ed Relinquished by Date Time by., Date Timev/�& /o./ -4 Cr `9` zy (� 2772 if no technician is provided,then the primary contact for your account will be selected.Unless scheduled,the turnaround time for all samples received after 3 pm EST will be logged in the neat business day.Weekend or holiday work must be scheduled ahead of time and is charged at 150%of the 3hr TAT or a minimum charge of S150. A courier charge will be applied for same day and one-day turnaround times fur Asite work.o SanAir covers Ground and Next Day Air shipping. Shipments billed to SanAir with a faster shipping rate will result in additional charges. Page of ` Page 9 of 9 au am oratories HYaQ 9922 East Montgomery Suite 13 TESTING Spokane Valley,WA 99206 NVIAPIAB CODE 101890-0 (509)922-1365•Fax(509)922-1380 October 15,2024 McCrink Consulting,LLC Project Name: 10303 E. Sprague Ave. Kevin McCrink 660 E. Sand Wedge Drive Post Falls,ID 83854 Dear Mr.McCrink, The enclosed report details results for the analysis of the bulk sample(s) submitted to Mountain Laboratories on October 15, 2024. Sample analysis was performed to determine asbestos type and content using Polarized Light Microscopy,supplemented by Dispersion Staining(PLM/DS). This report includes a summary of the analytical results and chain of custody. Analytical results are only reflective of the samples tested as received and presented in this report. Mountain Laboratories limits warranty to proper analysis methods and takes no responsibility for sample procurement. It has been our pleasure providing you with these analytical services. If you have any questions regarding this report,please do not hesitate to call us at(509)922-1365. Sincerely, Heidi L.Porret Laboratory Manager Mountain Laboratories Mountain Laboratories NW,Inc. Enclosure: 2134.39388.39393 MOUNTAIN LABORATORIES BULK SAMPLE ANALYSIS FOR ASBESTOS McCrink Consulting,LLC Project Name: 10303 E. Sprague Ave. Kevin McCrink 660 E. Sand Wedge Drive Post Falls,ID 83854 Test Method:40 CFR,Part 763,Subpart E,Appendix E and EPA/600/R-93/116 Customer#:2134 Laboratory No. B24-39388 B24-39389 B24-39390 Sample ID No. B-60 B-61 B-62 Sample Description Wall Mastic Wall Mastic Wall Mastic Sample Treatment Teased/Heated Teased/Heated Teased/Heated Homogeneous Yes Yes Yes Layered No No No Fibrous No No No Sample Color Black Black Black Asbestos Present No No No Asbestos Type and N.D. N.D. N.D. Percentage Total%Asbestos None None None Other Fibrous Material In Sample Non-Fibrous Material Other 100% Other 100% Other 100% Date Analyzed:October 15,2024 Analyzed By:Liz Templeton Mountain Laboratories,Mountain Laboratories NW,Inc.limits warranty to proper analysis methods only and takes no responsibility for sample procurement.Mountain Laboratories,Mountain Laboratories NW,Inc.,9922 E.Montgomery Suite#13,Spokane Washington 99206(509)922-1365-Fax(509)922-1380. PLM has been known to miss asbestos in a small percentage of samples. Thus negative or al%PLM results should be tested with either SEM or TEM. Customer is responsible for sample separation.This report may only be reproduced in full with written approval by Mountain Laboratories. Sample results must not be used by the customer to claim product certification,approval,or endorsement by NVLAP,MST,or any agency of the Federal Government. Page 2 of 4 MOUNTAIN LABORATORIES BULK SAMPLE ANALYSIS FOR ASBESTOS McCrink Consulting,LLC Project Name: 10303 E.Sprague Ave. Kevin McCrink 660 E. Sand Wedge Drive Post Falls,ID 83854 Test Method:40 CFR,Part 763 Subpart E,Appendix E,and EPA/600/R-93/116 Customer#:2134 Laboratory No. B24-39391 B24-39392 B24-39393 Sample ID No. B-63 B-64 B-65 Sample Description Wall Mastic Wall Mastic Wall Mastic Sample Treatment Teased/Heated Teased/Heated Teased/Heated Homogeneous Yes Yes Yes Layered No No No Fibrous No No No Sample Color Gold Black Black Asbestos Present No No No Asbestos Type and Gold Mastic:N.D. N.D. N.D. Percentage Total%Asbestos None None None Other Fibrous Material In Sample Other 100% Other 100% Other 100%LNon-Fibrous Material No Black Mastic in sample. Date Analyzed:October 15,2024 Analyzed By:Liz Templeton Mountain Laboratories,Mountain Laboratories NW,Inc.limits warranty to proper analysis methods only and takes no responsibility for sample procurement.Mountain Laboratories,Mountain Laboratories NW,Inc.,9922 E.Montgomery Suite#13,Spokane Washington 99206(509)922-1365-Fax(509)922-1380. PLM has been known to miss asbestos in a small percentage of samples. Thus negative or<I%PLM results should be tested with either SEM or TEM. Customer is responsible for sample separation.This report may only be reproduced in full with written approval by Mountain Laboratories. Sample results must not be used by the customer to claim product certification,approval,or endorsement by NVLAP,N1ST,or any agency of the Federal Government. Page 3 of 4 Mountain Laboratories Project Name: I 0)3 e`. fivMo DT"Gr°VL Division of Mountain In,pcction&Laboratory Services.Inc, 0!1-Y<t e- v A►i/ r ✓� 1/� 9922 E.Montgomery.Suite 13 Project No: L bG (/ Spokane,Washington 99206 PHONE:509-922-1365 FAX:509-922-1380 Results: MAIL. FAX PHONE mccrinkconsultinq(a,gmail 509-991-7357 CHAIN OF CUSTODY RECORD CLIENT BILLING ADDRESS: vNAI I SIS RLQtilltla) TURNAROUND McCrink Consulting,LLC, RUS 3 DAY 660 E.Sand Wedge Drive 5 DAY Post Falls,ID 83854 48 HR - a SEND COPY REPORT TO: 3 I—)--6 0'_ McCrink Consulting.LLC, a - I-: 660 E.Sand Wedge Drive 7 f 7- Post �^' YZ �,J V /� L L Falls.ID 83854 — ..e 41I �1 "` ALTO ` ' i — z rti 7_.- n\Asi;( 1-y AD SAMPLL:n SASII'I.li DESCRII'IION II) DA IF TI\IL - _ _ RESULTS'REMARIKS o 5-.0 ]mac-A(-I' LJA-t�- MAS7i� /b-is.24 1 GZ I i G3 -Gy t ) . P' GS / RELEASED BY: RECEIVED BY: COMPANY Mf ANY AGENCY 1 TIME DATEMETHOD RECEIVED CONDITION SIGNATURE(signature) (SIGNATURE) OR AFFILIATION l�� U t1 e G 4' Laboratories ,.. , 11 } Appendix C Laboratory Certification United States Department of Commerce National Institute of Standards and Technology Certificate of Accreditation to ISO/IEC 17025 :2017 N V LAP LAB CODE: 101926-0 EMC Labs, Inc. Phoenix, AZ is accredited by the National Voluntary Laboratory Accreditation Program for specific services, listed on the Scope of Accreditation, for: Asbestos Fiber Analysis This laboratory is accredited in accordance with the recognized International Standard ISO/lEC 17025:2017. This accreditation demonstrates technical competence for a defined scope and the operation of a laboratory quality management system (refer to joint ISO-ILAC-IAF Communique dated January 2009). 0,141-OF co, 2022-07-01 through 2023-06-30 >. Effective Dates yFo e For the National Voluntary Laboratory Accreditation Program -rATEs OF United States Department of Commerce National Institute of Standards and Technology , , Certificate of Accreditation to ISO/IEC 17025 : 2017 NVLAP LAB CODE: 101890-O Mountain Laboratories Spokane Valley, WA is accredited by the National Voluntary Laboratory Accreditation Program for specific services, listed on the Scope of Accreditation. for: Asbestos Fiber Analysis This laboratory is accredited in accordance with the recognized International Standard ISO/IEC 17025:2017. This accreditation demonstrates technical competence for a defined scope and the operation of a laboratory quality management system (refer to joint ISO-ILAC-lAF Communique dated January 2009). e ANT OFe , tttt y F 1 vvvv 2023-10-01 through 2024-09-30 � ;:c• • Effective Dates e For the National Voluntdry Laboratory Accreditation Program Fo STATES OF National Voluntary WM ® '� ' Laboratory Accreditation Program V Q SCOPE OF ACCREDITATION TO ISO/IEC 17025:2017 Mountain Laboratories 9922 East Montgomery. Suite 13 Spokane Valley. WA 99206 Ms. Heidi L. Porret Phone: 509-922-1365 Fax: 509-922-1380 Email: heidi@mountainlaboratories.com ASBESTOS FIBER ANALYSIS NVLAP LAB CODE 101890-0 Bulk Asbestos Analysis Code Description 18;A0 1 EPA--40 CFR Appendix E to Subpart E of Part 763.Interim Method of the Determination of Asbestos in Bulk insulation Samples I 8/A0 3 EPA 6001R-93/116:Method for the Determination of Asbestos in Bulk Building Materials r 1 For the National Voluntary LaborathyAccreditation Program Effective 2023-10-0!through 2024-09-30 Page 1 of 1 United States Department of Commerce National Institute of Standards and Technology HwitLf rah i l trot` Certificate of Accreditation to ISO/IEC 17025:2017 NVLAP LAB CODE: 200870-0 SanAir Technologies Laboratory, Inc. N. Chesterfield, VA is accredited by the National Voluntary Laboratory Accreditation Program for specific services, listed on the Scope of Accreditation, for: Asbestos Fiber Analysis This laboratory is accredited in accordance with the recognized International Standard ISO/IEC 17025:2017. This accreditation demonstrates technical competence for a defined scope and the operation of a laboratory quality management system (refer to joint ISO-ILAC-IAF Communique dated January 2009). �40Et1OFco 2023-04-01 through 2024-03-31 ��� Effective Dates Zoe '*` 0�" For the National Volunt _ bborator,�Accreditation Program ri r� National Voluntary Laboratory Accreditation Program SCOPE OF ACCREDITATION TO ISO/IEC 17025:2017 SanAir Technologies Laboratory, Inc. 10501 Trade Court N. Chesterfield, VA 23236 Ms. Sandra Sobrino Phone: 804-897-1177 Fax: 804-897-0070 Email: ssobrino@sanair.com http://www.sanair.com ASBESTOS FIBER ANALYSIS NVLAP LAB CODE 200870-0 Bulk Asbestos Analysis Code Description 18/A01 EPA--40 CFR Appendix E to Subpart E of Part 763,Interim Method of the Determination of Asbestos in Bulk Insulation Samples 18/A03 EPA 600/R-93/116:Method for the Determination of Asbestos in Bulk Building Materials Airborne Asbestos Analysis Code Description 18/A02 U.S.EPA's"Interim Transmission Electron Microscopy Analytical Methods-Mandatory and Nonmandatory-and Mandatory Section to Determine Completion of Response Actions"as found in 40 CFR,Part 763,Subpart E,Appendix A. r , For the National Volunta L.)6 rat Accreditation Program Effective 2023-04-01 through 2024-03-31 Page 1 of I EXHIBIT B BID PROPOSAL PACKET Balfour Facility Demolition BID PROPOSAL BID PROPOSAL CHECKLIST This Checklist and the documents listed below constitute a complete Bid Proposal. Failure to execute any of the following documents, or any addition, condition or limitation in writing to the form of the bid,not explicitly invited in the Bid Documents may become cause for rejection of the bid as irregular. The BIDDER shall check each respective box indicating inclusion of each itcm: [) Bid Proposal Checklist [)] Proposal Form [ Certification of Compliance with Wage Payment Statutes [)4 Contractor's Administrative Information [)) Bidder Qualification Statement [ Representations and Certifications The above forms have been included in the electronic submittal(PDF package),properly identified and delivered at the place and time described in the Small Works Invitation to Bid form. Signature: C _ —. Date: 10-18-24 Title: Project Manager Com an y: Elder Demo. LLC P City of Spokane Valley 1 Bid Proposal Documents 0350 Balfour Facility Demolition PROPOSAL FORM PROJECT NUMBER: 0350 PROJECT TITLE: Balfour Facility Demolition NAME OF FIRM SUBMITTING BID: Elder Demo, LLC Each bid shall constitute an offer to the City of Spokane Valley as outlined herein and no bidder may withdraw his bid after the hour set for the closing. RECEIPT OF ADDENDA:Bidder acknowledges receipt of the following addenda by checking the box(es): © 1 ® 2 El 4 CI REJECTION: The City reserves the right to reject any or all proposals, portions or parts thereof and to waive all minor irregularities in bidding. Special attention will be directed to the qualifications of the bidders when considering awarding a contract. TIME TO COMPLETE:The contract shall be substantially completed in twenty-eight(28)calendar days from the date of commencement. FREIGHT: Bid price(s)to include all freight costs to and from the job site. SCHEDULES: A Bidder must complete all the schedules or his bid will be rejected as non-responsive. The undersigned hereby certifies that (he/they) (has/have) personally examined the location and construction details of work as outlined on the plans and specifications for the above project and(has/have) read thoroughly and understands the plans, specifications, and contract governing the work embraced in this improvement and the method by which payment will be made for said work and hereby proposes to undertake and complete the work embraced in this improvement in accordance with said plans, specifications,and contract in accordance with the prices provided below. The Bidder,to be considered responsible,shall provide in legible figures(not words)handwritten in ink or typed,a unit price(except Lump Sum items)and total for each of the items shown on the following schedule: City of Spokane Valley 2 Bid Proposal Documents 0350 Balfour Facility Demolition Bid Schedule A ITEM# ITEM DESCRIPTION UNITS QUANTITY PRICE/UNIT TOTAL 101 Abate ACM LUMP SUM 1 L.S. $67,791.00 102 Demolish and dispose of building LUMP SUM 1 L.S. $27,634.00 103 Future building pad LUMP SUM 1 L.S. $18,398.00 104 Minor Change CALC 1 CALC $15,000.00 BID SCHEDULE A SUB-TOTAL $128,823.00 8.9%Tax $11,465.25 BID SCHEDULE A TOTAL $140,288.25 Z------ li Person/Entity Name: Allen Kackman Signature of Bidder: s_: t z b ; Company: Elder Demo, LLC Date: 10-18-24 City of Spokane Valley 3 Bid Proposal Documents 0350 Balfour Facility Demolition Client#: 134059 KERRCONT ACORDr. CERTIFICATE OF LIABILITY INSURANCE DATE(MM/DD/YYYY)10/29/2024 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER.THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND,EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S),AUTHORIZED REPRESENTATIVE OR PRODUCER,AND THE CERTIFICATE HOLDER. IMPORTANT:If the certificate holder is an ADDITIONAL INSURED,the policy(ies)must have ADDITIONAL INSURED provisions or be endorsed. If SUBROGATION IS WAIVED,subject to the terms and conditions of the policy,certain policies may require an endorsement.A statement on this certificate does not confer any rights to the certificate holder in lieu of such endorsement(s). PRODUCER CONTACT NAME: Bernadette Burns Propel Insurance PHONE 800 499-0933 FAX 866 577-1326 (A/C,No,Ext): (A/C,NO 805 SW Broadway;Suite 2300 E-MAIL ADDRESS: Bernadette.Burns@propelinsurance.com P COM Construction INSURER(S)AFFORDING COVERAGE NAIL# Portland,OR 97205-3363 INSURER A:Cincinnati Insurance Company 10677 INSURED INSURER B:SAIF Corporation 36196 Elder Demo, LLC.DBA: Elder Demolition Axis Surplus Insurance Company 26620 INSURER C: P P Y PO Box 10 INSURER D: Wilsonville,OR 97070 INSURER E: INSURER F: COVERAGES CERTIFICATE NUMBER: REVISION NUMBER: THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. LTR TYPE OF INSURANCE INSR END POLICY NUMBER POLICY EFF POLICY EXP LIMITS {MMIDD/YYYY) (MM/DD/YYYY) A X COMMERCIAL GENERAL LIABILITY EPP0580790 05/15/2024 05/15/2025 EACH OCCURRENCE $1,000,000 CLAIMS-MADE X OCCUR PREMISESO(EaE�urrence) ,$500,000 X BI/PD Ded:10000 MED EXP(Any one person) $10,000 PERSONAL&ADV INJURY $1,000,000 GEN'L AGGREGATE LIMIT APPLIES PER: GENERAL AGGREGATE $2,000,000 PRO- POLICY X JECT LOC PRODUCTS-COMP/OP AGG $2,000,000 OTHER: WA Stop Gap $1,000,000 A AUTOMOBILE LIABILITY EBA0580790 05/15/2024 05/15/2025 Ea COMBaccidINEDent)SINGLE LIMIT $1,000,000 { X ANY AUTO BODILY INJURY(Per person) $ OWNED SCHEDULED BODILY INJURY(Per accident) $ AUTOS ONLY AUTOS HIRED NON-OWNED PROPERTY DAMAGE $ AUTOS ONLY AUTOS ONLY (Per accident) A x UMBRELLA LIAB X OCCUR EPP0580790 05/15/2024 05/15/2025 EACH OCCURRENCE $15,000,000 EXCESS LIAB CLAIMS-MADE AGGREGATE $15,000,000 DED RETENTION$ $ B WORKERS COMPENSATION 100052665 10/01/2024 10/01/2025 X I STATUTE I ERH AND EMPLOYERS'LIABILITY ANY PROPRIETOR/PARTNER/EXECUTIVE Y/N E.L.EACH ACCIDENT $1,000,000 OFFICER/MEMBER EXCLUDED? N/A (Mandatory In NH) E.L.DISEASE-EA EMPLOYEE $1,000,000 If yes,describe under DESCRIPTION OF OPERATIONS below E.L.DISEASE-POLICY LIMIT $1,000,000 A Leased/Rented EQ EPP0580790 05/15/2024 05/15/2025 500,000/DED: $500 C Cont. Pollution CM006465012024 05/15/2024 05/15/2025 5MM Incident/5MM Agg -Retention $25K SIR DESCRIPTION OF OPERATIONS/LOCATIONS/VEHICLES(ACORD 101,Additional Remarks Schedule,may be attached if more space is required) RE: Project#2438-Balfour Park.Additional insured, primary and non-contributory basis and waiver of subrogation status applies per attached forms, if required by written contract. CERTIFICATE HOLDER CANCELLATION Cityof Spokane Valley,WA SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE p THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN 10210 E Sprague Avenue ACCORDANCE WITH THE POLICY PROVISIONS. Spokane Valley,WA 99206 AUTHORIZED REPRESENTATIVE , �1 ©1988-2015 ACORD CORPORATION.All rights reserved. ACORD 25(2016/03) 1 of 1 The ACORD name and logo are registered marks of ACORD #57013454/M6955496 KXSOO THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. CONTRACTORS ADDITIONAL INSURED - AUTOMATIC STATUS AND AUTOMATIC WAIVER OF SUBROGATION WHEN REQUIRED IN WRITTEN CONTRACT, AGREEMENT, PERMIT OR AUTHORIZATION This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART A. Additional Insured - Owners, Lessees Or cluded in the "products-completed Contractors - Automatic Status For Other operations hazard", but only if: Parties When Required In Written Contract Or Agreement With You (1) The Coverage Part to which this endorsement is attached pro- 1. Section II - Who Is An Insured is vides coverage for "bodily injury" amended to include as an additional in- or "property damage" included sured any person or organization you within the "products-completed have agreed in writing in a contract or operations hazard"; and agreement to add as an additional in- sured on this Coverage Part. Such per (2) The written contract or written son(s) or organization(s) is an additional agreement requires you to pro- insured only with respect to liability for: vide additional insured coverage included within the "products- a. "Bodily injury", "property damage" or completed operations hazard" "personal and advertising injury" for that person or organization. caused, in whole or in part, by the performance of your ongoing opera If the written contract or written tions by you or on your behalf, under agreement requires you to provide that written contract or written additional insured coverage included agreement. Ongoing operations does within the "products completed oper not apply to "bodily injury" or"proper- ations hazard" for a specified length ty damage" occurring after: of time for that person or organiza- tion, the "bodily injury" or "property (1) All work, including materials, damage" must occur prior to the ex- parts or equipment furnished in piration of that period of time in order connection with such work, on for this insurance to apply. the project (other than service, maintenance or repairs) to be If the written contract or written performed by or on behalf of the agreement requires you to provide additional insured(s) at the loca additional insured coverage for a tion of the covered operations person or organization per only ISO has been completed; or additional insured endorsement form number CG 20 10, without specifying (2) That portion of"your work" out of an edition date, and without specifi- which the injury or damage aris- cally requiring additional insured es has been put to its intended coverage included within the "prod- use by any person or organiza- ucts-completed operations hazard", tion other than another contrac- this Paragraph b. does not apply to tor or subcontractor engaged in that person or organization. performing operations for a prin- cipal as a part of the same pro- 2. If the written contract or written agree- ject; and ment described in Paragraph 1. above specifically requires you to provide addi- b. "Bodily injury" or "property damage" tional insured coverage to that person or caused, in whole or in part, by "your organization: work" performed under that written contract or written agreement and in- a. Arising out of your ongoing opera- tions or arising out of"your work"; or Includes copyrighted material of Insurance GA 472 05 20 Services Office, Inc., with its permission. Page 1 of 3 b. By way of an edition of an ISO addi- 2. With respect to the insurance afforded to tional insured endorsement that in- the additional insureds described in Para- cludes arising out of your ongoing graph B.1., the following additional exclu- operations or arising out of "your sions apply: work"; This insurance does not apply to: then the phrase caused, in whole or in part, by in Paragraph A.1.a. and/or Para- a. "Bodily injury", "property damage" or graph A.1.b. above, whichever applies, is "personal and advertising injury" aril replaced by the phrase arising out of. ing out of operations performed for the federal government, state or mu- 3. With respect to the insurance afforded to nicipality; or the additional insureds described in Para- graph A.1., the following additional exclu- b. "Bodily injury" or "property damage" sion applies: included within the "products- completed operations hazard." This insurance does not apply to "bodily injury", "property damage" or "personal C. The insurance afforded to additional insureds and advertising injury" arising out of the described in Paragraphs A. and B.: rendering of, or the failure to render, any 1. Only applies to the extent permitted by professional architectural, engineering or law; and surveying services, including: a. 2. Will not be broader than that which you The preparing, approving or failing to are required by the written contract, writ- prepare or approve, maps, shop ten agreement, written permit or written drawings, opinions, reports, surveys, authorization to provide for such addition- field orders, change orders or draw- al insured; and ings and specifications; or 3. Does not apply to any person, organiza- b. Supervisory, inspection, architectural tion, state, governmental agency or sub- or engineering activities. division or political subdivision specifically This exclusion applies even if the claims named as an additional insured for the against any insured allege negligence or same project in the schedule of an en other wrongdoing in the supervision, hir- added to this Coverage Part. ing, employment, training or monitoring of D. With respect to the insurance afforded to the others by that insured, if the "occurrence" additional insureds described in Paragraphs which caused the "bodily injury" or "prop- A. and B.,the following is added to Section III erty damage", or the offense which - Limits Of Insurance: caused the "personal and advertising inju- ry", involved the rendering of, or the fail- The most we will pay on behalf of the addi- ure to render, any professional architec- tional insured is the amount of insurance: tural, engineering or surveying services. 1. Required by the written contract, written 4. This Paragraph A. does not apply to addi- agreement, written permit or written au- tional insureds described in Paragraph B. thorization described in Paragraphs A. and B. For the purpose of determining the B. Additional Insured - State Or Governmental required amount of insurance only,we will Agency Or Subdivision Or Political Subdi- include the minimum amount of any Urn- vision - Automatic Status When Required brella Liability or Excess Liability cover- In Written Permits Or Authorizations age required for that additional insured in 1. Section II - Who Is An Insured is that written contract, written agreement, amended to include as an additional in written permit or written authorization; or sured any state or governmental agency 2. Available under the applicable limits of in- or subdivision or political subdivision you surance; have agreed in writing in a permit or au- thorization to add as an additional insured whichever is less. on this Coverage Part. Such state or gov- ernmental agency or subdivision or politi This endorsement shall not increase the appli- cal subdivision is an additional insured cable limits of insurance. only with respect to operations performed E. Section IV - Commercial General Liability by you or on your behalf for which the Conditions is amended to add the following: state or governmental agency or subdivi- sion or political subdivision has issued, in Automatic Additional Insured Provision writing, a permit or authorization. Includes copyrighted material of Insurance GA 472 05 20 Services Office, Inc., with its permission. Page 2 of 3 This insurance applies only if the "bodily inju- scribed in Paragraph A. or B. that this in- ry" or "property damage" occurs, or the "per- surance would be primary to any other in- sonal and advertising injury" offense is corn- surance available to the additional in- mitted: sured. 1. During the policy period; and As used in this endorsement, wrap-up insur- ance means a centralized insurance program 2. Subsequent to your execution of the writ- under which one party has secured either in- ten contract or written agreement, or the surance or self-insurance covering some or all issuance of a written permit or written au- of the contractors or subcontractors perform- thorization, described in Paragraphs A. ing work on one or more specific project(s). and B. Primary And Noncontributory Insurance F. Except when G. below applies, the following is When Required By Written Contract, added to Section IV - Commercial General Agreement, Permit Or Authorization Liability Conditions, Other Insurance, and supersedes any provision to the contrary: Except when wrap-up insurance applies to the claim or "suit" on behalf of the additional in- When Other Additional Insured Coverage sured, this insurance is primary to and will not Applies On An Excess Basis seek contribution from any other insurance This insurance is primary to other insurance available to the additional insured described in available to the additional insured described in Paragraphs A. and B. provided that: Paragraphs A. and B.except: 1. The additional insured is a Named In- 1. As otherwise provided in Section IV - sured under such other insurance; and Commercial General Liability Condi- 2. You have agreed in writing in a contract, tions, Other Insurance, b. Excess In- agreement, permit or authorization de- surance; or scribed in Paragraph A. or B. that this in- 2. For any other valid and collectible insur- surance would be primary and would not ance available to the additional insured as seek contribution from any other insur an additional insured on another insur ante available to the additional insured. ance policy that is written on an excess As used in this endorsement, wrap-up insur- basis. In such case, this insurance is also ance means a centralized insurance program excess. under which one party has secured either in- G. The following is added to Section IV - Com- surance or self-insurance covering some or all mercial General Liability Conditions, Other of the contractors or subcontractors perform Insurance, and supersedes any provision to ing work on one or more specific project(s). the contrary: H. Section IV - Commercial General Liability Primary Insurance When Required By Writ- Conditions, Transfer Of Rights Of Recov- ten Contract, Agreement, Permit Or Au- ery Against Others To Us is amended by the thorization addition of the following: Except when wrap-up insurance applies to the Waiver of Subrogation claim or "suit" on behalf of the additional in- We waive any right of recovery against any sured, this insurance is primary to any other additional insured under this endorsement, insurance available to the additional insured because of any payment we make under this described in Paragraphs A. and B. provided endorsement, to whom the insured has that: waived its right of recovery in a written con- 1. The additional insured is a Named In- tract, written agreement, written permit or writ- sured under such other insurance; and ten authorization. Such waiver by us applies only to the extent that the insured has waived 2. You have agreed in writing in a contract, its right of recovery against such additional in- agreement, permit or authorization de- sured prior to loss. Includes copyrighted material of Insurance GA 472 05 20 Services Office, Inc., with its permission. Page 3 of 3