23-141.03NADegerstromPinesMissionIntersectionImprovements
Spokane ,,�Valley CHANGE ORDER NO: 3 ENGINEERING DIVISION CONSTRUCTION CONTRACT NO: 23-141.03 PROJECT: Pines and Mission Intersection Improvements CONTRACT DATE: 8/4/2023 PRIME CONTRACTOR: N.A. Degerstrom, Inc. CIP NO: 300 DESCRIPTION OF CHANGES Additional HMA patching and stormwater work associated with Field Work Directive#1 and#4. Item No. Description Unit Quantity Unit Price Total 115(Sch A) REMOVE CEMENT CONCRETE DRIVEWAY APPROACH SY 47 $ 6.00 $ 282.00 151 (Sch A) CEMENT CONCRETE DRIVEWAY APPROACH SY 47 $ 135.00 $ 6,345.00 177 (Sch A) HMA CL.3/8"PG 34H-28,4 INCH DEPTH SY 89 $ 300.00 $ 26,700.00 178 (Sch A) FWD#01 STORM REVISIONS LS 1 $ 3,272.07 $ 3,272.07 179(Sch A) FWD#04 STORM REVISIONS LS 1 $ 3,527.10 $ 3,527.10 8.9%Sales Tax(applicable only to Bid Schedule B) $ N/A Total Amount of this Change Order(incl.Tax): $ 40,126.17 VERBAL APPROVAL AND JUSTIFICATION Independent Justification on File Yes Verbal Approval Yes Verbal Approval by GMR PHYSICAL COMPLETION Original Contract Working Days: 70 Revision By This Change Order: 3 Revisions by Prior Change Orders: 9 Total Revised Contract Working Days: 82 CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT $ 1,549,863.60 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through CO#02) $ 111,277.48 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 1,661,141.08 NET THIS CHANGE ORDER $ 40,126.17 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 1,701,267.25 Digitally signed by John Brueher John B r u e h e r D g C=Us,Egbrueher@nadinc.com,O=N A. CONTRACTOR ACCEPTANCE: Degerstrom,cN,lohn Br�eher DATE: 10—8—2 0 2 4 The contractor hereby accepts this adjustment and the terms orSec�ion�1 tf4. "of the original contract. RECOMMENDED BY: DATE: 10/9/24 Project n er APPROVED BY: DATE: 10/09/2024 Engln dry onager P r e APPROVED BY: i DATE: /(.(.7.2c 2 Public Works Director APPROVED BY: N/A - Within PW Director's Authority DATE: City Manager ATTACHMENTS: Change Order Description Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor, PW Project File, Project Inspector, Finance Department COSV Form 9/5/2014 Spokane ��Valley Change Order No: 3 Construction Contract No: 23-141.03 All work,materials,and measurements to be in accordance with the provisions of the Standard Specifications and Special Provisions for the type of construction involved. THE CONTRACT IS MODIFIED AS FOLLOWS: Background: Issue#1 The City determined that Hot Mix Asphalt(HMA)repairs were necessary since there was less existing asphalt within the roadway than anticipated.After the 2-inch planing on the south side of Mission Avenue according to plan,underlying base material was encountered.The repair included removing the substandard areas 6"below final grade, scarifying and recompacting the existing base and patching back with 4 inches of HMA prior to top lift. Issue#2 The City determined after potholing for utilities that existing utilities conflicted with the plan location of the new storm pipe at CB 3 at Sta. 5+55.80 to DW 2 at Sta.5+43.38. See Field Work Directive(FWD)#1. The storm was redesigned to use ductile iron and go shallower with the inverts to allow for the storm sewer to go over the top of the existing utilities and maintain the design intent. The abutting driveway approach next to CB 3 was determined to be badly cracked and deteriorated beyond repair so the City decided to remove and replace the driveway to provide a consistent neat edge for the new roadway paving and to accommodate the necessary drainage. Issue#3 There was a low spot in the existing curb at Sta.4+08.47 Rt creating ponding and deteriorating the existing pavement at that location. Per FWD#4,the City requested additional stormwater improvements to place a drainage structure near this low spot to collect the roadway runoff. In order to install the additional stormwater work, a concrete driveway had to be replaced. Description of Change: Issue#1 This change order compensates the Contractor for repairing the existing roadway where the existing HMA was not as thick as expected with underlying base material encountered and paving the section back 4-inch depth of HMA. Issue#2 This change order compensates the Contractor changes in material and the associated labor required to install the ductile iron versus the PVC pipe and the additional CDF backfill. This also compensates the contractor for additional quantity of removal and replacement of concrete driveway approach. Issue#3 This change order compensates the Contractor for the additional stormwater improvements associated with FWD #4. This also compensates the contractor for additional quantity of removal and replacement of concrete driveway approach. Specification: Requirement of Section 2-02, 5-04, & 8-06 of the Standard Specifications shall apply. Plans: The attached sheets CLO2 from FWD#1 and CLO5 from FWD#4 are added. ��pt��ane ,jValley Change Order No: 3 Construction Contract No: 23-141.03 Time: Three additional working days are added to the Contract for this change. Measurement: "HMA CL. 3/8"PG 64H-28,4 Inch Depth"will be measured by the square yard as marked in the field by the Engineer. No Specific Measurement will be made for lump sum item"FWD#01 Storm Revisions". No Specific Measurement will be made for lump sum item"FWD#04 Storm Revisions". Payment: This change order increases the quantity of existing bid items and will be paid using bid unit prices. This change order also creates three new items. Payment for new item#177"HMA CL. 3/8"PG 34H-28,4 Inch Depth,"per square yard. The unit Contract price per square yard for"HMA CL.3/8"PG 64H-28,4 Inch Depth" shall be full pay for furnishing all tools,labor,equipment,and materials required in accordance with the requirements of Section 5-04 and removing, scarifying and recompacting the existing base. Payment for new item#178"FWD#01 Storm Revisions,"lump sum. The lump sum Contract price for"FWD#01 Storm Revisions,"shall be full pay for all labor,materials,and equipment to install the ductile iron pipe, fittings,excavation, CDF and backfill in accordance with Field Work Directive#1 (FWD). Payment for new item#179"FWD#04 Storm Revisions," lump sum. The lump sum Contract price for"FWD#04 Storm Revisions",shall be full pay for all labor,materials,and equipment to install the ductile iron pipe,fittings, concrete inlet,excavation,and backfill in accordance with Field Work Directive#4. Summary of Quantities: Previous New Estimated Bid Item Description Unit Qt3. Qty Qty Unit Price Amount Change 115 REMOVE CEMENT CONCRETE S.Y. 299 346 +47 $6.00 $282.00 DRIVEWAY APPROACH 151 CEMENT CONCRETE S.Y. 29 76 +47 $135.00 $6,345.00 DRIVEWAY APPROACH 177 HMA CL.3/8"PG 34H-28,4 INCH S.Y. 89 +89 $300.00 $26,700.00 (New) DEPTH 178 FWD#01 STORM REVISIONS L.S. 1 +1 $3,272.07 $3,272.07 (New) 179 FWD#04 STORM REVISIONS L.S. 1 +1 $3,527.10 $3,527.10 (New) TOTAL $40,126.17 FEDERAL AID PROJECT NO.CM-4060(001)I SE i SE i SEC.9 T.25N.R.44E.W.M. A . 1' • I I• INSTALL ELBOW AS NEEDED J TO MODIFY ENTRY ANGLE TO !j A — PREVENT TEE FROM HITTING 0 , TOP OR SIDE OF STRUCTURE Q SII s I /° PVC TEE SPILL +y.N p I CONTROL SEPARATOR, �11 ; 1,_., E o x I /p/ I DIAMETER TO MATCH PIPE — l. II BACKFILL TRENCH ° _� WITH CDF MEETING I /°/ I DW2 , s WSDOT SPEC ° /° , IE.SHOWN ON PLANS 2-09.3(1)E.EXTEND CDF ° r `'�,-` Y ° 2-FOOT PAST GAS LINE/ r 4 °:/ I p/ PROPOSED------i, 1'-9"MIN $� , .�:: p/ x I I g DRAINAGE STRUCTURE, PROPOSED PIPE SIZE, x�a . . SEE PLANS v ` SLOPE AND MATERIAL • i $r' °�'" .`"�"`.z . I I SHOWN ON PLANS & �'.%�•y- SEE NOTE 1 I € b a I NOTES I - I I 1. IF DUCTILE IRON PIPE IS USED,THE CONTRACTOR SHALL WRAP A • L I CONTINUOUS SELF-ADHERING STRIP OF BUTYL RUBBER SEALANT AROUND I t'''; THE OUTSIDE OF THE PVC SPILL CONTROL SEPARATOR.INSERT THE SPILL :, _ s .•, . • CONTROL SEPARATOR INTO THE DIP ENSURING A SNUG,WATER-TIGHT SEAL;SEALANT SHALL MEET WSDOT SPEC 9-04.11. 2. ALL REQUIRED MATERIALS INCLUDING BUTYL RUBBER SEALANT ARE INCIDENTAL TO THE INSTALLATION OF THE SPILL CONTROL SEPARATOR. 3. WHEN PVC PIPE IS USED,A SAND COLLAR SHALL BE INSTALLED. 1 rs, A SPILL CONTROL SEPARATOR F c04 0 01 NTS N < +K J 21 M Co I-•-G.- BACKFILL TRENCH LL��Y o w rn N WITH NSF 2-FOOT PAST 5< F M. .._ THE GAS LINE -. a CO•-LC 4� OF WAsq��r.�col • 5.1 2035 SPILL - �,1 CONTROL // --SEPARATOR---- --Fiber - o--- 40.5 LF OF 8-INCH DUCTILE 4 ,I.4 ""��`, 'a`+i d 4 IRON PIPE @ 2.05%SLOPE _ �� iS ___T 1d'1Mbr INV CB:2034.18 _ ZONAL 2030 INV @ DW:2033.35 05/09/2024 i i 3 ° J SCALE FEET IS ji REVISIONS DRAWN BY LXKE PINES/MISSION INT.IMPROVEMENTS SHEET NO. DATE DESCRIPTION BY uI a � CITY PUBLICF WORKS DESIGNED BY ._xmo— kkaan COMMUNITY&PUBLIC WORKS DEPARTMENT CB3 TO DW2 0 1 e' 10210 EAST SPRAGUE AVENUE STORM DRAIN PROFILE /1 Know what's below . alley SPOKANE VALLEY,WA.99206 CONFORMED SET CLO/� ' Call before you dig. (509)720-5000 07-10-2023 MP 86.45 SR 27 OF 36 FEDERAL AID PROJECT NO.C M-4060(001)I SE 3 SE}SEC.B T.25N.R.44E.W.M. • 45094.0130 .: WOLFF PLACE.LLC & ,y,Ya u 0BEM860iAE ,- . N RON 3.50.1_._ LT .qr,,a ____ _ __2RALF3:ROSSM6301ffi :TEMPoRARY T BTA3N041,39d0 LT STA 4.35]L 3].14.LT EBMT 3.41.3T,40.E LTmM 4 ICONSTRUCTIONFA6EMENfEBYT]•4].b,3200 LT• A 4•d65.32.14'LT 61 -FA 9�NQ � 3 P . b1 O-M, ( ©N1Fl Owen�.}�T._ e%%% XXXXXXXXXXX X 2a,Y Y.YXX XXXXX-PINIFeignaitr9 f#! X 21 f• � Z. •�j 6r Og f PXOPOBED FIOWIII£OFGUTTER MI9.56 30 T� , / EX FIBER TOP:2033..33 E�.0ab � }Y9•--- 9 1S1*,1f1A.�. hNf'w'R g�y FIBER BTN:ZO3A9] Y°` S f: " v y f err a. �� Wefts. Nya, ew . sr u-u br•-TM.s -:1v: ` a`\l\ wily arwNorooc ce IE 2039.85 /RON PMOBABMAWLOPE- a .�• al -3n aH•.__yn�.__yT. %IE-2031]5 \ % \`` - IX.FIBER PACK lOP:303338 .aom - ° ` __J EXISTINGDRYWELL EX.FIBER PACK BTM.3mt.ro Mii1 BOMB 2120 E MISSION MO cNT ^2 1eL O. v„ ...TIT STA 5415,19,n.]6 RT / ___ 6TM•4S1,31.70 RT ! CTO earn.OLO JOart RETAIN AND 1EXIS STORM PROFILE 81/2BTRACT O BTA 5 OPPORTUNITY NI4.SB,2].6Y RT PROTECT VAULT F1 2 TELECOM VAI TI . - • •TIO - • N ,N REFER TO PLAN SHEETS 5&7 OF 36 FOR SITE PREPARATION AND IMPROVEMENT KEY NOTES 46094 01. 42Ba10135 NgLFF PLACE LLC I NGLFF PLACE N TH COMB MLET PE 1 t 3309E MI6510N AVE 12313E MIMI' 50 O 8'0 UCTILE M NATO D AND TYPE RATE 3 TRACT 3 ROB 84110301ffi TEMPORARY PROP09ED RIGHT COWAN' TRACT 1 RO6 0 STORM PIPE PER 6T0 MANS S 1YS115 EASEMENT CONSTRUCTION EXISTING RIGHT OF WAY ORATE L3035 BS - -'-c O ! (!. ESM 31]31� _ 40. ,2].LLT q�EMP - _ _c _.-.c - -- c- .. % . PIPEEE 303985 TOP 3383 ORZ AP ET ]3BT ° -0 le e3l: c O E W E - G 0 I 6 EXISTING O 1 BTM 9 ADJUST B 3031 es 9•A W ROW 3�28 9300 LT 6 �_ C BTfl G ATE B R 3 BOX / EA LOb LT,A L 11T- 0 9 MIO I Ip i2)1 LT ti0 YI •_ ,k� PE IE M3]5 ER PA TO 9330 20 805 F r N il_i _ _ ._. • t>t!w��`I w- _... w _. w ...BERM 263n1 .. wwx 6 - ,. _ r Ex BER PACK t 2 1 _ __ .. - ��rp�� - UT t` EX. TOP:30N.03-�_, �r - a i(_}_. wA O. w :n T _-_.- A 'R4�`4 C �, -- �3 D .-_ DD pd OWL( V 1T. _ nve _z—D to ,M„p ST 1.10 799& I4.W' ^ "a / F� d �:l (`--'ham\ :� ll L7� D 4]SD D D .s.n 2rrL D a w __as a: ,I. _'^- --n J_/\v �- 3s a a `WTc�E%. ur ° JOINT - MATdIIX. a 3 j s1 .� j0_. _ —�ADHESIVE Mu WO ]OM41 T04 IDM.RPo N!' e'4.OXQA% d d N30.lDPo 6 ST ',eg0 STA S 3T 2B(_ n:w :my G , __F—.Iw nrx -KY :— ww ,,„ e�1 X-/ MATCH EX. +••J MI30b F0 Mb3 FG -JL— A ._. MI•T6.51 FG 1038.N FO \ MATCH EXISTING / J" A] -+yi, JJJ u --: •� —, _ �w , . _CCUT SAD,URB A9 NEEDED EXISTING 30%.38 FG ' „�' Nw. ��Ysri� 3,N jbye.eaaa y}" FDnsloEwaKtzsx ' � b;,„0 A133 AD D6TEK6 NG D o,l3.lPoAMEANDLDVER 0 0 MATCH 0TING ,�� i Temporary !AVE Tem ra Access k% 18OFNNW1F CURB ELEVATION E Permit(TAP)Limits § SEE-WEST DRIVEWAY DETAIL'THIS SHEET WEST DRIVEWAY DETAIL IMPROVEMENT PLAN REVISIONS DRAWN BY XME PINES/MISSION INT.IMPROVEMENTS SHEET NO. DATE DESCRIPTION BY CITY OF SPOKANE VALLEY CITv W DESIGNED BY KMQ s bliane COMMUNITY&PUBLIC WORKS DEPARTMENT REMOVE AND REPLACE o �7�1 10210EASTSPRAGUEAVENUE WEST DRIVEWAY APPROACH CL05 Know%bars below 1V�1ey° SPOKANE VALLEY,WA.99206 CONFORMED SET Call before you dig. (509)720.5000 07-30-2023 MP 86.45 SR 27 OF 36