HomeMy WebLinkAboutResolution 26-009 Adopt 6-Year Transportation Improvement Program TIPCITY OF SPOKANE VALLEY
SPOKANE COUNTY, WASHINGTON
RESOLUTION 26-009
A RESOLUTION OF THE CITY OF SPOKANE VALLEY, SPOKANE COUNTY,
WASHINGTON, ADOPTING THE 2027-2032 TRANSPORTATION IMPROVEMENT
PROGRAM FOR THE CITY OF SPOKANE VALLEY, AND OTHER MATTERS RELATING
THERETO.
WHEREAS, to provide for the proper and necessary development of the street system within the
City of Spokane Valley, the City shall, pursuant to RCW 35.77.010, develop and adopt annually a Six -Year
Transportation Improvement Program (Six -Year TIP) with such program acting as a guide for the
coordinated development of the City's transportation system; and
WHEREAS, the Six -Year TIP of the City shall specifically set forth those projects and programs
of both City and regional significance that benefit the transportation system and promote public safety and
efficient vehicle movements; and
WHEREAS, the Six -Year TIP shall be consistent with the City's Comprehensive Plan and be
adopted following one or more public hearings before the City Council; and
WHEREAS, a draft copy of the Six -Year TIP was submitted to the Washington State Department
of Commerce and has been reviewed and approved prior to the scheduled adoption of the TIP in accordance
with RCW 36.70A.106; and
WHEREAS, following adoption of the Six -Year TIP, the City will forward a copy to the
Washington State Secretary of Transportation; and
WHEREAS, the City Council conducted a public hearing on June 16, 2026, for the purpose of
inviting and receiving public comment on the proposed Six -Year TIP.
NOW THEREFORE, be it resolved by the City Council of the City of Spokane Valley, Spokane
County, Washington, as follows:
Section 1. The City Council hereby adopts the attached Six -Year TIP for the City of Spokane
Valley for the purpose of guiding the design, development and construction of local and regional
transportation improvements for the years 2027 through 2032. The City Clerk is directed to file the 2027-
2032 Six -Year TIP with the Washington State Secretary of Transportation before June 30, 2026. The Six -
Year TIP shall be reviewed at least annually for the purpose of determining the work to be accomplished
under the program and the City's transportation requirements.
Projects and timeframes identified in the Six -Year TIP are to be considered estimates only, may change due
to a variety of circumstances, and are not intended by the City to be relied upon by property owners or
developers in making development decisions.
In the event a railroad ceases to use rail right-of-way within the City, the City will utilize all reasonable
options available under state or federal law to preserve the right-of-way for future rail purposes pursuant to
RCW 35.77.010(3),
Section 2. City Council acknowledges that the Six -Year TIP projects identified therein as being
part of the City's Legislative Agenda have been extensively reviewed and determined by City Council to
greatly benefit the community. By including a project in both the City's Legislative Agenda and Six -Year
Resolution 26-009, Adopting Six -Year TIP
TIP, City Council authorizes City staff to pursue any and all eligible funding avenues necessary to deliver
the project without further action required by City Council so long as staff provide notification to City
Council of the funding opportunities as they become available and are pursued by staff.
Section 3. Effective Date. This Resolution shall be in full force and effect upon adoption.
Adopted this 16" day of June 2026.
ATTEST:
Marci P tterson, Clerk
Approved as to Form:
O fice r
e City ttorney
City of Sp4ane Valley ---
Laura Padden, Mayor
Resolution 26-009, Adopting Six -Year TIP
SCITY OF
p
Valley@)
6-Year Transportation
Improvement Program (TIP)
2027-2032
City of Spokane Valley
Public Works Department Spokane
2027-2032 Transportation Improvement Program (TIP) ,;000OValley
Glossary & Abbreviations
Fund Source
Type
Name
• BIP
Federal
Bridge Investment Program
• BUILD
Federal
Better Utilizing Investments to Leverage Develop.
• City
Non -Federal
City Funds
• CDBG
Federal
Community Development Block Grant
• DEMO
Federal
Federal Appropriation Funds (Earmarks)
• CMAQ
Federal
Congestion Mitigation & Air Quality Improvement
• COM
Non -Federal
Washington State Department of Commerce
• DEV
Non -Federal
Private Developer Funds
• FMSIB
Non -Federal
Freight Mobility Strategic Investment Board
• HSIP
Federal
Highway Safety Improvement Program
• NHFP
Federal
National Highway Freight Program
• NHS
Federal
National Highway System Asset Management
• Other
Varies
Misc. Funding Source(s)
• PBP
Non -Federal
Pedestrian/Bicycle Program
• RCO
Non -Federal
Washington State Recreation Conservation Office
• RR
Non -Federal
Railroad
• SRTS
Non -Federal
Safe Routes to School
• STORM
Non -Federal
City Stormwater Funds
• STA
Varies
Spokane Transit Authority
• STBG
Federal
Surface Transportation Block Grant (formerly STP)
• STBG-SA
Federal
Surface Transportation Block Grant — Set Aside
• TIB
Non -Federal
Transportation Improvement Board
• Utility
Varies
Utility Purveyor Funds
Project Phases
• PE Preliminary Engineering
• RW Right -of -Way
• CN Construction
2027-2032 Transportation Spokane
Improvement Program (TIP) �Valley-
1: Sprague Preservation (Bowdish to McDonald)
Project Years: 2024-2026 Project Type: Closeout
Description: Pavement preservation.
6-Year TIP Cost: $29,580
2: Barker Road Reconstruction (Sprague to Appleway)
Project Years: 2024-2026 Project Type: Closeout
6-Year TIP Cost: $17,400
Description: Reconstruction to urban 3-lane section. This is a City Council identified legislative agenda project.
3: S. Sullivan Rd. Preservation (8th to 24th)
Project Years: 2024-2026 Project Type: Closeout
6-Year TIP Cost: $50,020
Description: Preservation project with sidewalk infill, midblock pedestrian crossing, stormwater upgrades, and ITS expansion.
4: Sullivan Preservation (UPRR to Kiernan)
Project Years: 2025-2026 Project Type: Closeout
6-Year TIP Cost: $28,690
Description: Preservation and stormwater project excluding intersection of Euclid.
5: 32nd Ave Preservation (Pines to SR27)
Project Years: 2025-2026 Project Type: Closeout
6-Year TIP Cost: $29,250
Description: Pavement preservation with Water District coordination.
6: Arterial School Crossings
Project Years: 2025-2026 Project Type: Closeout
6-Year TIP Cost: $11,190
Description: New enchanced crossings on 32nd, Pines, and Broadway.
7: Pines (SR27) & BNSF Grade Separation Project
Project Years: 2019-2027 Project Type: Bridge
6-Year TIP Cost: $2,004,400
Description: Construct Grade Separation at Pines(SR27)/BNSF RR/Trent (SR290).
8: Pines Preservation (32nd to 40th)
Project Years: 2025-2027 Project Type: Preservation
6-Year TIP Cost: $1,500,000
Description: Pavement preservation with bike and pedestrian facilities.
9: Sullivan Preservation (Spokane River to UPRR)
Project Years: 2025-2027 Project Type: Preservation
6-Year TIP Cost: $3,350,000
Description: Preservation project with new signal, park access roads, sidewalks and stormwater facilities.
10: S. Barker Corridor (Sprague to 8th)
Project Years: 2025-2027 Project Type: Reconstruction
6-Year TIP Cost: $8,950,000
Description: Reconstruct street with three lanes, bikes lanes, sidewalks, and stormwater as needed. Roundabouts at 4th and 8th Ave. This is a City
Council identified legislative agenda project.
11: Broadway Preservation (Havana to Fancher)
Project Years: 2026-2027 Project Type: Preservation
6-Year TIP Cost: $4,325,000
Description: Pavement preservation with stormwater upgrades and consideration for mid -block crossing near fairgrounds access.
12: Thierman Preservation (Sprague to Broadway)
Project Years: 2025-2027 Project Type: Preservation
6-Year TIP Cost: $735,000
Description: Pavement preservation in parternship with Spokane County Water District #3.
13: Appleway Trail & Stormwater (Farr to Dishman Mica)
Project Years: 2025-2027 Project Type: Pedestrian/Bicycle
6-Year TIP Cost: $1,324,150
Description: Extension of the Appleway Trail and reconstruction of stormwater facilities.
14: Flora Cross Course Pedestrian Facilities
Project Years: 2026-2028 Project Type: Pedestrian/Bicycle
6-Year TIP Cost: $600,000
Description: Improve Flora to make pedestrian connection between Flora Cross Course and Euclid Ave.
Page 1 of 3
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances.
15: Mansfield Pedestrian Crossings
Project Years: 2026-2027 Project Type: Pedestrian/Bicycle
Description: Installation of enhanced pedestrian crossings.
16: Indiana Preservation (190 ramp to Desmet)
Project Years: 2027-2028 Project Type: Preservation
Description: Pavement preservation.
17: Wellesley Preservation (Isenhart to Trent)
Project Years: 2028-2029 Project Type: Preservation
Description: Pavement preservation with Stormwater and multimodal.
18: Sprague Preservation Phase 2 (University to Bowdish)
Project Years: 2026-2028 Project Type: Preservation
Description: Pavement preservation with locations of full depth patching.
6-Year TIP Cost: $259,000
6-Year TIP Cost: $1,500,000
6-Year TIP Cost: $2,650,000
6-Year TIP Cost: $2,189,000
19: Sullivan & Trent Interchange
Project Years: 2024-2030 Project Type: Bridge 6-Year TIP Cost: $48,702,000
Description: Phased reconstruction of interchange, including widening of Sullivan between Kiernan and Wellesley adding ITS, center turn lane,
lighting, and shared use path. This is a City Council identified legislative agenda project.
20: Fancher Preservation (Sprague to Trent)
Project Years: 2025-2029 Project Type: Preservation 6-Year TIP Cost: $6,110,000
Description: Phased preservation project with asphalt grind and inlay with stormwater retrofits. Broadway -Trent planned for 2027 and Sprague -
Broadway planned for 2028.
21: SR-27 & 16th Intersection
Project Years: 2026-2029 Project Type: Intersection 6-Year TIP Cost: $6,900,000
Description: Add traffic control at five -leg intersecton (potential roundabout) with multimodal.
22: Northeast Sewer Extension
Project Years: 2026-2029 Project Type: Reconstruction 6-Year TIP Cost: $6,320,000
Description: Phased street reconstruction and sewer extension with Spokane Co.: 2027 Donwood community at Barker/Euciid, 2029 Flora and
Tschirley (Euclid -Garland), Dalton (Flora-Tschirley) consider multimodal along Flora.
23: Argonne & 1-90 Bridge
Project Years: 2025-2030 Project Type: Bridge 6-Year TIP Cost: $25,080,000
Description: Bridge reconstruction, rechannelization, signal rework and multimodal. Concrete reconstruction of Argonne from 190 to Montgomery and
a southerly connection at Mission. This is a City Council identified legislative agenda project.
24: Carnahan Street & Stormwater (8th to South Limit)
Project Years: 2026-2030 Project Type: Stormwater 6-Year TIP Cost: $3,540,000
Description: 2027 stormwater conveyance upgrades with potential for pavement preservation and addition of bike/ped facilities.
25: Ridgemont Estates Street & Stormwater
Project Years: 2026-2030 Project Type: Stormwater 6-Year TIP Cost: $8,995,000
Description: Stormwater improvements and road reconstruction in City's southeast neighborhood.
26: Street Maintenance and Operations Costs (Annual)
Project Years: Annual Project Type: Preservation 6-Year TIP Cost: $3,060,000
Description: Ongoing street maintenance and operations activities in Street Fund 101, including bridge and traffic infrastructure.
27: Barker & 1-90 Interchange (Mission to Appleway)
Project Years: 2026-2032 Project Type: Bridge 6-Year TIP Cost: $47,845,000
Description: Phased interchange reconstruction, reconfiguration of adjacent intersections, and widening Barker to a 4/5-lane urban section with
multimodal facilities. This is a City Council identified legislative agenda project.
28: Local Access Street Improvements
Project Years: Annual Project Type: Preservation 6-Year TIP Cost: $9,000,000
Description: Surface treatments (not shown on map), grind/inlays, and reconstruction projects as annual funding allocations allow. Potential project
neighbhorhoods: Midilome, Carnahan, Ponderosa, Hillcrest, Sprague, Vera Crest.
Page 2 of 3
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances.
29: Citywide Safety Projects
Project Years: Annual Project Type: Safety 6-Year TIP Cost: $7,000,000
Description: Consistent with Local/Regional Safety Plans; including arterial pedestrian facilities/crossings citywide (i.e. Sprague or Valleyway),
particularly near schools. Funded projects identified separately in TIP.
30: Street Preservation Projects
Project Years: Annual Project Type: Preservation 6-Year TIP Cost: $15,000,000
Description: 4th, 8th, 16th, 24th (Dishman-Sullivan), Dishman Mica, Appleway (E of Corbin), Vista(Appleway-Mission), Marietta (Sullivan -Euclid), 3rd
and 4th (Havana-Fancher), Thierman (8th-Broadway), Ponderosa Area (Schafer, 44th, Sands), Sprague (Fancher-Herald, McDonald -Sullivan),
Evergreen (Sprague-32nd), Bowdish and University (Sprague -Mission), Pines (16th-32nd)
31: Citywide Multimodal Improvements
Project Years: Annual Project Type: Pedestrian/Bicycle 6-Year TIP Cost: $5,418,000
Description: Consistent with Active Transportation Plan such as: Appleway Trail (Farr to Havana), Flora (Centennial Trail -Flora Cross Course), River
Loop (Sullivan -Flora Parks), and Millwood Trail (Fancher to Vista) and other prioritized projects.
32: Sullivan & Kiernan Intersection
Project Years: 2029-2031 Project Type: Intersection 6-Year TIP Cost: $3,000,000
Description: Improve channelization and signal operations at intersection and reconstruct intersection with concrete and improved multimodal.
Coordinate with County sewer extension project.
33: Sullivan & Marietta Intersection
Project Years: 2029-2031 Project Type: Intersection 6-Year TIP Cost: $3,000,000
Description: Improve channelization and signal operations at intersection and reconstruct intersection with concrete.
34: Mirabeau & Mansfield Intersection
Project Years: 2030-2032 Project Type: Intersection 6-Year TIP Cost: $3,500,000
Description: New intersection control (signal or roundabout) with multimodal.
35: Bowdish Reconstruction (Sprague to Dishman Mica)
Project Years: 2030-2040 Project Type: Reconstruction 6-Year TIP Cost: $2,800,000
Description: Phased projects to reconstruct Sprague to Dishman Mica as urban section with bicycle and pedestrian facilities. May also include
intersection improvements at 32nd Ave. and ITS.
36: 8th & Carnahan Intersection
Project Years: 2030-2033 Project Type: Intersection 6-Year TIP Cost: $425,000
Description: Add intersection control (turn lanes, potential signal) and improve multimodal.
37: Sprague & Pines Intersection
Project Years: 2031-2034 Project Type: Intersection 6-Year TIP Cost: $450,000
Description: Install SB right turn lane, EB left turn lane, and intersection control (signal and channelization) and improve multimodal.
38: 8th & Park Intersection
Project Years: 2031-2034 Project Type: Intersection 6-Year TIP Cost: $340,000
Description: Provide new traffic signal or roundabout and improve multimodal.
39: Broadway (Flora to Barker)
Project Years: 2032-2035 Project Type: Reconstruction
Description: Expand 3-lane urban section with and improve multimodal.
6-Year TIP Cost: $50,000
40: Park & Mission Intersection
Project Years: 2032-2035 Project Type: Intersection 6-Year TIP Cost: $50,000
Description: Improve channelization and evaluate for signal operations.
41: Flora & SR 290 Intersection
Project Years: 2032-2034 Project Type: Intersection 6-Year TIP Cost: $100,000
Description: Improved traffic control with added turn lanes or roundabout, per adopted Planned Action Ordinance, including multimodal.
6-Year Total TIP Cost: $236,237,681
6-Year Total TIP Cost - By Year
2027
2028
2029
2030
2031
2032
$41,571,680
$28,072,000
$42,993,000
$45,811,000
$41,320,500
$36,469,500
Page 3 of 3
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances.
1: Sprague Preservation (Bowdish to McDonald) Spokan�``—
Uai ky
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$0
$0
$0
$0
$0
$0
$0
RW
Secured
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$29,580
$0
$0
$0
$0
$0
$29,580
TOTAL
1
1 $29,580
$0
$0
$0
$0
$0
$29,580
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Closeout
Total Project Years: 2024-2026
Total Project Cost: $3,208,000
Project Description: Pavement preservation.
Funding Sources
SourceName
Funding
City
$361,000
STBG
$2,847,000
Funding Sources
Legend
■ STBG 88.7%
City 11.3%
Pagel of 41
2: Barker Road Reconstruction (Sprague to Appleway) Spokan``—
Val ley
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$0
$0
$0
$0
$0
$0
$0
RW
Secured
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$17,400
$0
$0
$0
$0
$0
$17,400
TOTAL
1
1 $17,400
$0
$0
$0
$0
$0
$17,400
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Closeout
Total Project Years: 2024-2026
Total Project Cost: $2,200,000
Project Description: Reconstruction to urban 3-lane section. This is a City Council identified legislative
agenda project.
Funding Sources
SourceName
Funding
City
$62,100
FMSIB
$1,740,000
STBG
$397,900
Funding Sources
Legend
A4 FMSIB 79.1%
■ STBG 18.1 %
City 2.8%
Page 2 of 41
3: S. Sullivan Rd. Preservation (8th to 24th) Spokan�``1
>Uai ky
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$0
$0
$0
$0
$0
$0
$0
RW
Secured
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$50,020
$0
$0
$0
$0
$0
$50,020
TOTAL
1
1 $50,020
$0
$0
$0
$0
$0
$50,020
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Closeout
Total Project Years: 2024-2026
Total Project Cost: $5,643,000
Project Description: Preservation project with sidewalk infill, midblock pedestrian crossing, stormwater
upgrades, and ITS expansion.
Funding Sources
SourceName
Funding
City
$308,000
NHS
$5,335,000
Funding Sources
Legend
E NHS 94.5%
City 5.5%
Page 3 of 41
4: Sullivan Preservation (UPRR to Kiernan) Spokan�``—
Uai ky
_ w
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$0
$0
$0
$0
$0
$0
$0
RW
Secured
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$28,700
$0
$0
$0
$0
$0
$28,700
TOTAL
1
1 $28,690
$0
$0
$0
$0
$0
$28,690
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Closeout
Total Project Years: 2025-2026
Total Project Cost: $3,070,000
Project Description: Preservation and stormwater project excluding intersection of Euclid.
Funding Sources
SourceName
Funding
City
$1,570,000
STBG
$1,500,000
Funding Sources
Legend
City 51.1%
0 STBG 48.9%
5: 32nd Ave Preservation (Pines to SR27)
ne
�'L�ailey.
y
it +"
,
E 29th Ave
Y
E 30th Ave �
a,
C
i
�j/1
fn
E 31 St Ave
E 32nd Ave
N
Ct
_.*
t.ilk
� -
m
,� +�.��
r•
r
`!� . ;.
E 34th Ave
U
Spokane Valley
��, �,
,
,
.
L
0
a
N
N
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$0
$0
$0
$0
$0
$0
$0
RW
Secured
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$29,250
$0
$0
$0
$0
$0
$29,250
TOTAL
1
1 $29,250
$0
$0
$0
$0
$0
$29,250
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Closeout
Total Project Years: 2025-2026
Total Project Cost: $3,175,000
Project Description: Pavement preservation with Water District coordination.
Funding Sources
SourceName
Funding
City
$875,000
NHS
$2,300,000
Funding Sources
Legend
NHS 72.4%
i City 27.6%
Page 5 of 41
6: Arterial School Crossings >N7ailey-
n�
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status 2027 2028 2029 2030 W2031 2032 6-Year Total
PE Secured $0 $0 $0 $0 $0 $0 $0
RW $0 $0 $0 $0 $0 $0 $0
CN Secured $11,917 $0 $0 $0 $0 $0 $11,917
TOTAL I 1 $11,190 $0 $0 $0 $0 $0 $11,190
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Closeout
Total Project Years: 2025-2026
Total Project Cost: $1,191, 700
Project Description: New enchanced crossings on 32nd, Pines, and Broadway.
Funding Sources
SourceName Funding
SRTS 1 $1,263,700
Funding Sources
Legend
SRTS 100.0%
Page 6 of 41
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Closeout
Total Project Years: 2025-2026
Total Project Cost: $1,191, 700
Project Description: New enchanced crossings on 32nd, Pines, and Broadway.
Funding Sources
SourceName Funding
SRTS 1 $1,263,700
Funding Sources
Legend
SRTS 100.0%
Page 6 of 41
7: Pines (SR27) & BNSF Grade Separation Project 'SW5„-
.,;�Vailey
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$0
$0
$0
$0
$0
$0
$0
RW
Secured
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$2,004,400
$0
$0
$0
$0
$0
$2,004,400
TOTAL
1
$2,004,400
$0
$0
$0
$0
$0
$2,004,400
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Bridge
Total Project Years: 2019-2027
Total Project Cost: $47,839,000
Project Description: Construct Grade Separation at Pines(SR27)/BNSF RR/Trent (SR290).
Funding Sources
SourceName
Funding
BUILD
$21,689,000
City
$4,703,000
CMAQ
$6,405,000
DEMO
$6,247,000
Other State
$5,000,000
STBG
$3,795,000
Funding Sources
Legend
BUILD 45.3%
■ CMAQ 13.4%
DEMO 13.1%
■ Other State 10.5%
City 9.8%
Page 7 of 41
8: Pines Preservation (32nd to 4Oth)
k4e�
-'PT"
E 32nc'
ar
W1,W,
NDi{dne
�'L�ailey.
ram. i" r
r r
fi
s:'� Spokane Vallev
1 s I
,1
Current 6-Year TIP A Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$0
$0
$0
$0
$0
$0
$0
RW
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$1,500,000
$0
$0
$0
$0
$0
$1,500,000
TOTAL
1
1 $1,500,000
$0
$0
$0
$0
$0
$1,500,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Preservation
Total Project Years: 2025-2027
Total Project Cost: $1,585,000
Project Description: Pavement preservation with bike and pedestrian facilities.
Funding Sources
SourceName Funding
City 1 $1,585,000
Funding Sources
Legend
City 100.0%
Page 8 of 41
9: Sullivan Preservation (Spokane River to UPRR)
1`
'L�alley.
. e�, r • w,
_ •mod-�`"'r �� � �
.++
``7^^ OF
vJ
z
Spokane Valley
E .. i
+ +► I F��Ora p' I Iv
}
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$50,000
$0
$0
$0
$0
$0
$50,000
RW
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$3,300,000
$0
$0
$0
$0
$0
$3,300,000
TOTAL
1
1 $3,350,000
$0
$0
$0
$0
$0
$3,350,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Preservation
Total Project Years: 2025-2027
Total Project Cost: $5,730,000
Project Description: Preservation project with new signal, park access roads, sidewalks and
stormwater facilities.
Funding Sources Funding Sources
SourceName Funding
City 1 $5,730,000
Legend
City 100.0%
Page 9 of 41
10: S. Barker Corridor (Sprague to 8th) Spokan``1
Ual[ey
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$0
$0
$0
$0
$0
$0
$0
RW
Secured
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$8,950,000
$0
$0
$0
$0
$0
$8,950,000
TOTAL
1
1 $8,950,000
$0
$0
$0
$0
$0
$8,950,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Reconstruction
Total Project Years: 2025-2027
Total Project Cost: $10,150,000
Project Description: Reconstruct street with three lanes, bikes lanes, sidewalks, and stormwater as
needed. Roundabouts at 4th and 8th Ave. This is a City Council identified legislative agenda project.
Funding Sources
SourceName
Funding
City
$1,664,992
DEMO
$1,483,475
HSIP
$1,500,000
PBP
j $1,665,000
TIB
1 $3,836,533
Funding Sources
Legend
TIB 37.8%
■ PBP 16.4%
■ City 16.4%
■ HSIP 14.8%
■ DEMO 14.6%
Page 10 of 41
11: Broadway Preservation (Havana to Fancher) Spokan�``—
Uai ky
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$0
$0
$0
$0
$0
$0
$0
RW
Secured
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$4,325,000
$0
$0
$0
$0
$0
$4,325,000
TOTAL
1
1 $4,325,000
$0
$0
$0
$0
$0
$4,325,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Preservation
Total Project Years: 2026-2027
Total Project Cost: $4,500,000
Project Description: Pavement preservation with stormwater upgrades and consideration for mid -block
crossing near fairgrounds access.
Funding Sources
SourceName
Funding
City
$1,000,000
NHS
$3,500,000
Funding Sources
Legend
NHS 77.8%
■ city 22.2%
Page 11 of 41
12: Thierman Preservation (Sprague to Broadway)
Spokatrl'`1
,��1[ey-
- —
E-Broadway Ave a �I
�
�'-
ingfield Ave' �° �e 'a" `'.r��' n
OEM
LU
Yy 4 t
a
Fr F
} ► !
t Kiaersiae Hae s
Uniion.Racific ai roads
-A -�t-
y -{
`t E Sprague Ave, —
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$15,000
$0
$0
$0
$0
$0
$15,000
RW
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$720,000
$0
$0
$0
$0
$0
$720,000
TOTAL
1
1 $735,000
$0
$0
$0
$0
$0
$735,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Preservation
Total Project Years: 2025-2027
Total Project Cost: $750,000
Project Description: Pavement preservation in parternship with Spokane County Water District #3.
Funding Sources
SourceName Funding
City 1 $750,000
Funding Sources
Legend
City 100.0%
Page 12 of 41
13: Appleway Trail & Stormwater (Farr to Dishman Mica)
Spokane
Ual[ey
K -
E 1st Ave
610
OL
LL
�.� k E Appleway Blvd
vi 7 = } @ Spokane Valley
4"
seeC—ar IF
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$24,150
$0
$0
$0
$0
$0
$24,150
RW
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$1,300,000
$0
$0
$0
$0
$0
$1,300,000
TOTAL
1
1 $1,324,150
$0
$0
$0
$0
$0
$1,324,150
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Pedestrian/Bicycle
Total Project Years: 2025-2027
Total Project Cost: $1,405,000
Project Description: Extension of the Appleway Trail and reconstruction of stormwater facilities.
Funding Sources
SourceName
Funding
City
$474,000
STBG-SA
$931,000
Funding Sources
Legend
■ STBG-SA 66.3%
■ City 33.7%
Page 13 of 41
14: Flora Cross Course Pedestrian Facilities ��—
.;W*VAtky-
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$100,000
$0
$0
$0
$0
$0
$100,000
RW
Planned
$100,000
$0
$0
$0
$0
$0
$100,000
CN
Planned
$0
$400,000
$0
$0
$0
$0
$400,000
TOTAL
1
1 $200,000
$400,000
$0
$0
$0
$0
$600,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Pedestrian/Bicycle
Total Project Years: 2026-2028
Total Project Cost: $600,000
Project Description: Improve Flora to make pedestrian connection between Flora Cross Course and
Euclid Ave.
Funding Sources
SourceName Funding
Other 1 $600,000
Funding Sources
Legend
*k Other 100.0%
Page 14 of 41
15: Mansfield Pedestrian Crossings Spokan�``—
Uai ky
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$0
$0
$0
$0
$0
$0
$0
RW
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$259,000
$0
$0
$0
$0
$0
$259,000
TOTAL
1
1 $259,000
$0
$0
$0
$0
$0
$259,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Pedestrian/Bicycle
Total Project Years: 2026-2027
Total Project Cost: $285,000
Project Description: Installation of enhanced pedestrian crossings.
Funding Sources
SourceName Funding
PBP 1 $285,000
Funding Sources
Legend
lk PBP 100.0%
Page 15 of 41
16: Indiana Preservation (190 ramp to Desmet) Spikan' a `'
> Leal ley
Current 6-Year TIP Phased Funding atus - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$50,000
$0
$0
$0
$0
$0
$50,000
RW
$0
$0
$0
$0
$0
$0
$0
CN
Planned
$0
$1,450,000
$0
$0
$0
$0
$1,450,000
TOTAL
j
1 $50,000
j $1,450,000
j $0
j $0
j $0
j $0
j $1,500,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Preservation
Total Project Years: 2027-2028
Total Project Cost: $1,500,000
Project Description: Pavement preservation.
Funding Sources
SourceName Funding
City 1 $1,500,000
Funding Sources
Legend
City 100.0%
Page 16 of 41
17: Wellesley Preservation (Isenhart to Trent) Sprika
. to
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$0
$150,000
$0
$0
$0
$0
$150,000
RW
$0
$0
$0
$0
$0
$0
$0
CN
Planned
$0
$0
$2,500,000
$0
$0
$0
$2,500,000
TOTAL
1
$0
$150,000
$2,500,000
$0
$0
$0
$2,650,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Preservation
Total Project Years: 2028-2029
Total Project Cost: $2,650,000
Project Description: Pavement preservation with Stormwater and multimodal.
Funding Sources
SourceName Funding
City 1 $2,650,000
Funding Sources
Legend
City 100.0%
Page 17 of 41
18: Sprague Preservation Phase 2 (University to Bowdish) S`11``-
>Uai ky
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$0
$0
$0
$0
$0
$0
$0
RW
Secured
$80,000
$0
$0
$0
$0
$0
$80,000
CN
Secured
$0
$2,109,000
$0
$0
$0
$0
$2,109,000
TOTAL
$80,000
$2,109,000
$0
$0
$0
$0
$2,189,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Preservation
Total Project Years: 2026-2028
Total Project Cost: $2,287,000
Project Description: Pavement preservation with locations of full depth patching.
Funding Sources
SourceName
Funding
City
$937,000
STBG
$1,350,000
Funding Sources
Legend
■ STBG 59.0%
City 41.0%
Page 18 of 41
19: Sullivan & Trent Interchange Spikan' a `'
> Leal ley
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$543,000
$0
$0
$0
$0
$0
$543,000
RW
Partial
$3,800,000
$1,000,000
$0
$0
$0
$0
$4,800,000
CN
Partial
$0
$3,000,000
$3,000,000
$17,000,000
$20,000,000
$0
$43,359,000
TOTAL
1
1 $4,343,000
$4,000,000
$3,000,000
$17,000,000
$20,000,000
$0
$48,702,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Bridge
Total Project Years: 2024-2030
Total Project Cost: $53,793,000
Project Description: Phased reconstruction of interchange, including widening of Sullivan between
Kiernan and Wellesley adding ITS, center turn lane, lighting, and shared use path. This is a City Council
identified legislative agenda project.
Funding Sources
SourceName
Funding
City
$3,301,000
DEMO
$9,650,000
NHFP
$3,053,000
Other
j $31,422,000
STBG
1 $6,367,000
Funding Sources
Legend
Other 58.4 %
■ DEMO 17.9 %
■ STBG 11.8 %
■ City 6.2%
■ NHFP 5.7%
Page 19 of 41
20: Fancher Preservation (Sprague to Trent) Spokan�``—
Uai ky
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$45,000
$15,000
$0
$0
$0
$0
$60,000
RW
Secured
$25,000
$25,000
$0
$0
$0
$0
$50,000
CN
Secured
$3,600,000
$2,400,000
$0
$0
$0
$0
$6,000,000
TOTAL
1
1 $3,670,000
$2,440,000
$0
$0
$0
$0
$6,110,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Preservation
Total Project Years: 2025-2029
Total Project Cost: $6,200,000
Project Description: Phased preservation project with asphalt grind and inlay with stormwater retrofits.
Broadway -Trent planned for 2027 and Sprague -Broadway planned for 2028.
Funding Sources
SourceName Funding
City 1 $6,200,000
Funding Sources
Legend
City 100.0%
Page 20 of 41
21: SR-27 & 16th Intersection *4
�'L�alley.
Vurrent 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$150,000
$0
$0
$0
$0
$0
$150,000
RW
Planned
$0
$200,000
$0
$0
$0
$0
$200,000
CN
Planned
$0
$0
$6,550,000
$0
$0
$0
$6,550,000
TOTAL
1
1 $150,000
$200,000
$6,550,000
$0
$0
$0
$6,900,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Intersection
Total Project Years: 2026-2029
Total Project Cost: $7,050,000
Project Description: Add traffic control at five -leg intersecton (potential roundabout) with multimodal.
Funding Sources
SourceName
Funding
DEV
$300,000
Other
$6,750,000
Funding Sources
1
in
Legend
Other 95.7%
N DEV 4.3%
Page 21 of 41
22: Northeast Sewer Extension Spikan' a `'
.,;o*%I ky
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$100,000
$100,000
$0
$0
$0
$0
$200,000
RW
$0
$0
$0
$0
$0
$0
$0
CN
Partial
$1,400,000
$0
$4,720,000
$0
$0
$0
$6,120,000
TOTAL
1
1 $1,500,000
$100,000
$4,720,000
$0
$0
$0
$6,320,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Reconstruction
Total Project Years: 2026-2029
Total Project Cost: $6,450,000
Project Description: Phased street reconstruction and sewer extension with Spokane Co.: 2027
Donwood community at Barker/Euciid, 2029 Flora and Tschirley (Euclid -Garland), Dalton (Flora-
Tschirley) consider multimodal along Flora.
Funding Sources
SourceName
Funding
City
$1,000,000
Other
$5,450,000
Funding Sources
Legend
■ Other 84.5%
■ City 15.5%
Page 22 of 41
23: Argonne & 1-90 Bridge ���
.,;o0%t1ey-
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$1,050,000
$0
$0
$0
$0
$0
$1,050,000
RW
Partial
$0
$30,000
$0
$0
$0
$0
$30,000
CN
Partial
$0
$0
$12,000,000
$12,000,000
$0
$0
$24,000,000
TOTAL
1
1 $1,050,000
$30,000
$12,000,000
$12,000,000
$0
$0
$25,080,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Bridge
Total Project Years: 2025-2030
Total Project Cost: $27,530,000
Project Description: Bridge reconstruction, rechannel ization, signal rework and multimodal. Concrete
reconstruction of Argonne from 190 to Montgomery and a southerly connection at Mission. This is a City
Council identified legislative agenda project.
Funding Sources
SourceName
Funding
City
$202,000
FMSIB
$2,000,000
Other
$24,030,000
STBG
$1,298,000
Funding Sources
Legend
Other 87.3%
■ FMSIB 7.3%
IM4
■ STBG 4.7%
City 0.7%
Page 23 of 41
24: Carnahan Street & Stormwater (8th to South Limit)
8th Ave
ir
I •- _'.MM
Current 6-Year TIP Phased Funding Status - By Year
Spokane
Ual[ey
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Partial
$30,000
$210,000
$0
$0
$0
$0
$240,000
RW
Planned
$0
$0
$50,000
$0
$0
$0
$50,000
CN
Planned
$260,000
$0
$0
$2,990,000
$0
$0
$3,250,000
TOTAL
1
1 $290,000
$210,000
$50,000
$2,990,000
$0
$0
$3,540,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Stormwater
Total Project Years: 2026-2030
Total Project Cost: $3,600,000
Project Description: 2027 stormwater conveyance upgrades with potential for pavement preservation
and addition of bike/ped facilities.
Funding Sources Funding Sources
SourceName
Funding
City
$350,000
Other
$3,250,000
Legend
■ Other 90.3%
■ City 9.7%
4& 1
Page 24 of 41
25: Ridgemont Estates Street & Stormwater *4n --
.O Valley
Current 6-Fear i W Pt, A Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Secured
$60,000
$40,000
$60,000
$0
$0
$0
$160,000
RW
$0
$0
$0
$0
$0
$0
$0
CN
Partial
$2,325,000
$1,860,000
$0
$4,650,000
$0
$0
$8,835,000
TOTAL
1
1 $2,385,000
$1,900,000
$60,000
$4,650,000
$0
$0
$8,995,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Stormwater
Total Project Years: 2026-2030
Total Project Cost: $9,500,000
Project Description: Stormwater improvements and road reconstruction in City's southeast
neighborhood.
Funding Sources
SourceName Funding
City 1 $9,500,000
Funding Sources
Legend
City 100.0%
26: Street Maintenance and Operations Costs (Annual) an-
,.�Vailey
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
$0
$0
$0
$0
$0
$0
$0
RW
$0
$0
$0
$0
$0
$0
$0
CN
Secured
$510,000
$510,000
$510,000
$510,000
$510,000
$510,000
$3,060,000
TOTAL
1
1 $510,000
$510,000
$510,000
$510,000
$510,000
$510,000
$3,060,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Preservation
Total Project Years: Annual
Total Project Cost: $3,060,000
Project Description: Ongoing street maintenance and operations activities in Street Fund 101,
including bridge and traffic infrastructure.
Funding Sources
SourceName Funding
City 1 $3,060,000
Funding Sources
Legend
City 100.0%
Page 26 of 41
27: Barker & 1-90 Interchange (Mission to Appleway) ��—
.,;o0%t1ey-
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Partial
$1,230,000
$3,000,000
$1,000,000
$0
$0
$0
$5,230,000
RW
Planned
$2,000,000
$5,000,000
$500,000
$500,000
$0
$0
$8,000,000
CN
Planned
$0
$0
$6,865,000
$0
$5,750,000
$22,000,000
$34,615,000
TOTAL
1
$3,230,000
$8,000,000
$8,365,000
$500,000
$5,750,000
$22,000,000
$47,845,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Bridge
Total Project Years: 2026-2032
Total Project Cost: $71,757,000
Project Description: Phased interchange reconstruction, reconfiguration of adjacent intersections, and
widening Barker to a 4/5-lane urban section with multimodal facilities. This is a City Council identified
legislative agenda project.
Funding Sources
SourceName
Funding
City
$468,000
DEMO
$1,517,000
FMSIB
$1,260,000
Other
j $68,600,000
Funding Sources
Legend
Other 95.5%
® DEMO 2.1 %
FMSIB 1.8%
City 0.7%
Page 27 of 41
28: Local Access Street Improvements Spokan�``—
Uai ky
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$100,000
$100,000
$100,000
$100,000
$100,000
$100,000
$600,000
RW
$0
$0
$0
$0
$0
$0
CN
Planned
$1,400,000
$1,400,000
$1,400,000
$1,400,000
$1,400,000
$1,400,000
$8,400,000
TOTAL
1
1 $1,500,000
$1,500,000
$1,500,000
$1,500,000
$1,500,000
$1,500,000
$9,000,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Preservation
Total Project Years: Annual
Total Project Cost: $9,000,000
Project Description: Surface treatments (not shown on map), grind/inlays, and reconstruction projects
as annual funding allocations allow. Potential project neighbhorhoods: Midilome, Carnahan, Ponderosa,
Hillcrest, Sprague, Vera Crest.
Funding Sources
SourceName Funding
City 1 $9,000,000
Funding Sources
Legend
City 100.0%
Page 28 of 41
29: Citywide Safety Projects Spokan�``—
L7ai ky
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$0
$18,000
$48,000
$18,000
$48,000
$18,000
$150,000
RW
$0
$0
$0
$0
$0
$0
$0
CN
Planned
$0
$2,055,000
$342,500
$2,055,000
$342,500
$2,055,000
$6,850,000
TOTAL
1
1 $0
$2,073,000
$390,500
$2,073,000
$390,500
$2,073,000
1$7,000,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Safety
Total Project Years: Annual
Total Project Cost: $7,000,000
Project Description: Consistent with Local/Regional Safety Plans; including arterial pedestrian
facilities/crossings citywide (i.e. Sprague or Valleyway), particularly near schools. Funded projects
identified separately in TIP.
Funding Sources
SourceName
Funding
City
$700,000
HSIP
$6,300,000
Funding Sources
Legend
HSIP 90.0%
City 10.0%
Page 29 of 41
30: Street Preservation Projects >N7aiky
n�
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$0
$100,000
$100,000
$100,000
$100,000
$100,000
$500,000
RW
$0
$0
$0
$0
$0
$0
$0
CN
Planned
$0
$2,900,000
$2,900,000
$2,900,000
$2,900,000
$2,900,000
$14,500,000
TOTAL
1
1 $0
$3,000,000
$3,000,000
$3,000,000
$3,000,000
$3,000,000
$15,000,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Preservation
Total Project Years: Annual
Total Project Cost: $15,000,000
Project Description: 4th, 8th, 16th, 24th (Dish man -Su llivan), Dishman Mica, Appleway(E of Corbin),
Vista(Appleway-Mission), Marietta(Sullivan-Euclid), 3rd and 4th (Havana-Fancher), Thierman(8th-Broadway),
Ponderosa Area (Schafer, 44th, Sands), Sprague (Fancher-Herald, McDonald -Sullivan), Evergreen (Sprague-32nd),
Bowdish and University (Sprague -Mission), Pines (16th-32nd)
Funding Sources
SourceName Funding
City 1 $15,000,000
Funding Sources
Legend
City 100.0%
Page 30 of 41
31: Citywide Multimodal Improvements Spikan' a `'
> Leal ley
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$0
$0
$187,500
$187,500
$187,500
$187,500
$750,000
RW
Planned
$0
$0
$0
$198,000
$0
$0
$198,000
CN
Planned
$0
$0
$0
$0
$4,470,000
$0
$4,470,000
TOTAL
I
I $0
$0
$187,500
$385,500
$4,657,500
$187,500
$5,418,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Pedestrian/Bicycle
Total Project Years: Annual
Total Project Cost: $24,200,000
Project Description: Consistent with Active Transportation Plan such as: Appleway Trail (Farr to
Havana), Flora (Centennial Trail -Flora Cross Course), River Loop (Sullivan -Flora Parks), and Millwood
Trail (Fancher to Vista) and other prioritized projects.
Funding Sources
SourceName Funding
Other 1 $24,200,000
Funding Sources
Legend
Other 100.0%
Page 31 of 41
32: Sullivan & Kiernan Intersection Spokan�``1
Uai ky
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$0
$0
$80,000
$20,000
$0
$0
$100,000
RW
Planned
$0
$0
$0
$400,000
$100,000
$0
$500,000
CN
Planned
$0
$0
$0
$0
$2,400,000
$0
$2,400,000
TOTAL
I
I $0
$0
$80,000
$420,000
$2,500,000
$0
$3,000,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Intersection
Total Project Years: 2029-2031
Total Project Cost: $3,000,000
Project Description: Improve channelization and signal operations at intersection and reconstruct
intersection with concrete and improved multimodal. Coordinate with County sewer extension project.
Funding Sources
SourceName Funding
Other 1 $3,000,000
Funding Sources
lotLegend
Other 100.0%
Page 32 of 41
33: Sullivan & Marietta Intersection *4n --
�'L�alley
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$0
$0
$80,000
$20,000
$0
$0
$100,000
RW
Planned
$0
$0
$0
$400,000
$100,000
$0
$500,000
CN
Planned
$0
$0
$0
$0
$2,400,000
$0
$2,400,000
TOTAL
I
I $0
$0
$80,000
$420,000
$2,500,000
$0
$3,000,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Intersection
Total Project Years: 2029-2031
Total Project Cost: $3,000,000
Project Description: Improve channelization and signal operations at intersection and reconstruct
intersection with concrete.
Funding Sources
SourceName Funding
Other 1 $3,000,000
Funding Sources
Legend
19 Other 100.0%
Page 33 of 41
34: Mirabeau & Mansfield Intersection
+y Ze
5;2 r,
Scale: 1:1,000 � "'
Current 6-Year TIP Phased Funding Status - By Year
1
Spokane
Ual[ey
•
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Partial
$0
$0
$0
$75,000
$75,000
$0
$150,000
RW
Planned
$0
$0
$0
$0
$50,000
$50,000
$100,000
CN
Planned
$0
$0
$0
$0
$0
$3,250,000
$3,250,000
TOTAL
I
I $0
$0
$0
$75,000
$125,000
$3,300,000
$3,500,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Intersection
Total Project Years: 2030-2032
Total Project Cost: $3,500,000
Project Description: New intersection control (signal or roundabout) with multimodal.
Funding Sources Funding Sources
SourceName
Funding
DEV
$75,000
Other
$3,425,000
Legend
Other 97.9%
® DEV 2.1 %
Page 34 of 41
35: Bowdish Reconstruction (Sprague to Dishman Mica) 'SW5„-
.,Vatley
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$0
$0
$0
$200,000
$0
$200,000
$400,000
RW
Planned
$0
$0
$0
$0
$100,000
$0
$100,000
CN
Planned
$0
$0
$0
$0
$0
$2,300,000
$2,300,000
TOTAL
I
$0
$0
$0
$200,000
$100,000
$2,500,000
$2,800,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Reconstruction
Total Project Years: 2030-2040
Total Project Cost: $13,000,000
Project Description: Phased projects to reconstruct Sprague to Dishman Mica as urban section with
bicycle and pedestrian facilities. May also include intersection improvements at 32nd Ave. and ITS.
Funding Sources
SourceName Funding
Other 1 $13,000,000
Funding Sources
Legend
Other 100.0%
Page 35 of 41
36: 8th & Carnahan Intersection Spokan�``—
>Uai ky
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$0
$0
$0
$87,500
$87,500
$0
$175,000
RW
Planned
$0
$0
$0
$0
$0
$250,000
$250,000
CN
Planned
$0
$0
$0
$0
$0
$0
$0
TOTAL
I
I $0
$0
$0
$87,500
$87,500
$250,000
$425,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Intersection
Total Project Years: 2030-2033
Total Project Cost: $3,000,000
Project Description: Add intersection control (turn lanes, potential signal) and improve multimodal.
Funding Sources
SourceName Funding
Other 1 $3,000,000
Funding Sources
Legend
Other 100.0%
Page 36 of 41
37: Sprague & Pines Intersection
Ilk 4L IL It 4
Or
M. IlkIt
1 � -
.kAN
"
41
4
Ave
E spragueor
N
r
`yam
Current 6-Year TIP Phased Funding Status - By Year
1`
'L�alley.
Spokane Valley
N
A
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$0
$0
$0
$0
$150,000
$150,000
$300,000
RW
Planned
$0
$0
$0
$0
$0
$150,000
$150,000
CN
Planned
$0
$0
$0
$0
$0
$0
$0
TOTAL
I
I $0
$0
$0
$0
$150,000
$300,000
$450,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Intersection
Total Project Years: 2031-2034
Total Project Cost: $2,600,000
Project Description: Install SB right turn lane, EB left turn lane, and intersection control (signal and
channelization) and improve multimodal.
Funding Sources
SourceName Funding
Other 1 $2,600,000
Funding Sources
Legend
Other 100.0%
Page 37 of 41
38: 8th & Park Intersection *4
�'L�alley.
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$0
$0
$0
$0
$50,000
$50,000
$100,000
RW
Planned
$0
$0
$0
$0
$0
$240,000
$240,000
CN
Planned
$0
$0
$0
$0
$0
$0
$0
TOTAL
I
I $0
$0
$0
$0
$50,000
$290,000
$340,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Intersection
Total Project Years: 2031-2034
Total Project Cost: $3,000,000
Project Description: Provide new traffic signal or roundabout and improve multimodal.
Funding Sources
SourceName Funding
Other 1 $3,000,000
Funding Sources
Legend
*k Other 100.0%
Page 38 of 41
39: Broadway (Flora to Barker) Spokan�``—
Ual[ey
Doo
-
- Mo-�,
3y
31111L
`.
~rV
• w
,.
[2 . 0 0liiYlly
�j .
Or
e 0.0
iq
6
Scale:-1-8
000
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Partial
$0
$0
$0
$0
$0
$50,000
$50,000
RW
Partial
$0
$0
$0
$0
$0
$0
$0
CN
Partial
$0
$0
$0
$0
$0
$0
$0
TOTAL
I
I $0
$0
$0
$0
$0
$50,000
$50,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Reconstruction
Total Project Years: 2032-2035
Total Project Cost: $5,000,000
Project Description: Expand 3-lane urban section with and improve multimodal.
Funding Sources Funding Sources
SourceName Funding
Other 1 $5,000,000
Legend
Other 100.0%
Page 39 of 41
40: Park & Mission Intersection
4 °
j y
Mission, A
_ L
Current 6-Year TIP Phased Funding Status - By Year
ne
�'L�ailey.
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$0
$0
$0
$0
$0
$50,000
$50,000
RW
Planned
$0
$0
$0
$0
$0
$0
$0
CN
Planned
$0
$0
$0
$0
$0
$0
$0
TOTAL
I
$0
$0
$0
$0
$0
$50,000
$50,000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Intersection
Total Project Years: 2032-2035
Total Project Cost: $2,500,000
Project Description: Improve channelization and evaluate for signal operations.
Funding Sources
SourceName Funding
Other 1 $2,500,000
Funding Sources
Legend
Other 100.0%
Page 40 of 41
41: Flora & SR 290 Intersection *4
�'L�alley.
. 3
1� * An r�
7
Ito
w
29 Spokanf
e , s9r!� d4—
Current 6-Year TIP Phased Funding Status - By Year
Phase
Status
2027
2028
2029
2030
2031
2032
6-Year Total
PE
Planned
$0
$0
$0
$0
$0
$100,000
$100,000
RW
Planned
$0
$0
$0
$0
$0
$0
$0
CN
Planned
$0
$0
$0
$0
$0
$0
$0
TOTAL
I
$0
$0
$0
$0
$0
$100,000
$100-000
Project Summary
Summary information is for the entire project and may extend beyond the 6-Year TIP time frame.
Project Type: Intersection
Total Project Years: 2032-2034
Total Project Cost: $4,000,000
Project Description: Improved traffic control with added turn lanes or roundabout, per adopted Planned
Action Ordinance, including multimodal.
Funding Sources
SourceName Funding
Other 1 $4,000,000
Funding Sources
Legend
Other 100.0%