HomeMy WebLinkAboutResolution 26-009 Adopt 6-Year Transportation Improvement Program TIPCITY OF SPOKANE VALLEY SPOKANE COUNTY, WASHINGTON RESOLUTION 26-009 A RESOLUTION OF THE CITY OF SPOKANE VALLEY, SPOKANE COUNTY, WASHINGTON, ADOPTING THE 2027-2032 TRANSPORTATION IMPROVEMENT PROGRAM FOR THE CITY OF SPOKANE VALLEY, AND OTHER MATTERS RELATING THERETO. WHEREAS, to provide for the proper and necessary development of the street system within the City of Spokane Valley, the City shall, pursuant to RCW 35.77.010, develop and adopt annually a Six -Year Transportation Improvement Program (Six -Year TIP) with such program acting as a guide for the coordinated development of the City's transportation system; and WHEREAS, the Six -Year TIP of the City shall specifically set forth those projects and programs of both City and regional significance that benefit the transportation system and promote public safety and efficient vehicle movements; and WHEREAS, the Six -Year TIP shall be consistent with the City's Comprehensive Plan and be adopted following one or more public hearings before the City Council; and WHEREAS, a draft copy of the Six -Year TIP was submitted to the Washington State Department of Commerce and has been reviewed and approved prior to the scheduled adoption of the TIP in accordance with RCW 36.70A.106; and WHEREAS, following adoption of the Six -Year TIP, the City will forward a copy to the Washington State Secretary of Transportation; and WHEREAS, the City Council conducted a public hearing on June 16, 2026, for the purpose of inviting and receiving public comment on the proposed Six -Year TIP. NOW THEREFORE, be it resolved by the City Council of the City of Spokane Valley, Spokane County, Washington, as follows: Section 1. The City Council hereby adopts the attached Six -Year TIP for the City of Spokane Valley for the purpose of guiding the design, development and construction of local and regional transportation improvements for the years 2027 through 2032. The City Clerk is directed to file the 2027- 2032 Six -Year TIP with the Washington State Secretary of Transportation before June 30, 2026. The Six - Year TIP shall be reviewed at least annually for the purpose of determining the work to be accomplished under the program and the City's transportation requirements. Projects and timeframes identified in the Six -Year TIP are to be considered estimates only, may change due to a variety of circumstances, and are not intended by the City to be relied upon by property owners or developers in making development decisions. In the event a railroad ceases to use rail right-of-way within the City, the City will utilize all reasonable options available under state or federal law to preserve the right-of-way for future rail purposes pursuant to RCW 35.77.010(3), Section 2. City Council acknowledges that the Six -Year TIP projects identified therein as being part of the City's Legislative Agenda have been extensively reviewed and determined by City Council to greatly benefit the community. By including a project in both the City's Legislative Agenda and Six -Year Resolution 26-009, Adopting Six -Year TIP TIP, City Council authorizes City staff to pursue any and all eligible funding avenues necessary to deliver the project without further action required by City Council so long as staff provide notification to City Council of the funding opportunities as they become available and are pursued by staff. Section 3. Effective Date. This Resolution shall be in full force and effect upon adoption. Adopted this 16" day of June 2026. ATTEST: Marci P tterson, Clerk Approved as to Form: O fice r e City ttorney City of Sp4ane Valley --- Laura Padden, Mayor Resolution 26-009, Adopting Six -Year TIP SCITY OF p Valley@) 6-Year Transportation Improvement Program (TIP) 2027-2032 City of Spokane Valley Public Works Department Spokane 2027-2032 Transportation Improvement Program (TIP) ,;000OValley Glossary & Abbreviations Fund Source Type Name • BIP Federal Bridge Investment Program • BUILD Federal Better Utilizing Investments to Leverage Develop. • City Non -Federal City Funds • CDBG Federal Community Development Block Grant • DEMO Federal Federal Appropriation Funds (Earmarks) • CMAQ Federal Congestion Mitigation & Air Quality Improvement • COM Non -Federal Washington State Department of Commerce • DEV Non -Federal Private Developer Funds • FMSIB Non -Federal Freight Mobility Strategic Investment Board • HSIP Federal Highway Safety Improvement Program • NHFP Federal National Highway Freight Program • NHS Federal National Highway System Asset Management • Other Varies Misc. Funding Source(s) • PBP Non -Federal Pedestrian/Bicycle Program • RCO Non -Federal Washington State Recreation Conservation Office • RR Non -Federal Railroad • SRTS Non -Federal Safe Routes to School • STORM Non -Federal City Stormwater Funds • STA Varies Spokane Transit Authority • STBG Federal Surface Transportation Block Grant (formerly STP) • STBG-SA Federal Surface Transportation Block Grant — Set Aside • TIB Non -Federal Transportation Improvement Board • Utility Varies Utility Purveyor Funds Project Phases • PE Preliminary Engineering • RW Right -of -Way • CN Construction 2027-2032 Transportation Spokane Improvement Program (TIP) �Valley- 1: Sprague Preservation (Bowdish to McDonald) Project Years: 2024-2026 Project Type: Closeout Description: Pavement preservation. 6-Year TIP Cost: $29,580 2: Barker Road Reconstruction (Sprague to Appleway) Project Years: 2024-2026 Project Type: Closeout 6-Year TIP Cost: $17,400 Description: Reconstruction to urban 3-lane section. This is a City Council identified legislative agenda project. 3: S. Sullivan Rd. Preservation (8th to 24th) Project Years: 2024-2026 Project Type: Closeout 6-Year TIP Cost: $50,020 Description: Preservation project with sidewalk infill, midblock pedestrian crossing, stormwater upgrades, and ITS expansion. 4: Sullivan Preservation (UPRR to Kiernan) Project Years: 2025-2026 Project Type: Closeout 6-Year TIP Cost: $28,690 Description: Preservation and stormwater project excluding intersection of Euclid. 5: 32nd Ave Preservation (Pines to SR27) Project Years: 2025-2026 Project Type: Closeout 6-Year TIP Cost: $29,250 Description: Pavement preservation with Water District coordination. 6: Arterial School Crossings Project Years: 2025-2026 Project Type: Closeout 6-Year TIP Cost: $11,190 Description: New enchanced crossings on 32nd, Pines, and Broadway. 7: Pines (SR27) & BNSF Grade Separation Project Project Years: 2019-2027 Project Type: Bridge 6-Year TIP Cost: $2,004,400 Description: Construct Grade Separation at Pines(SR27)/BNSF RR/Trent (SR290). 8: Pines Preservation (32nd to 40th) Project Years: 2025-2027 Project Type: Preservation 6-Year TIP Cost: $1,500,000 Description: Pavement preservation with bike and pedestrian facilities. 9: Sullivan Preservation (Spokane River to UPRR) Project Years: 2025-2027 Project Type: Preservation 6-Year TIP Cost: $3,350,000 Description: Preservation project with new signal, park access roads, sidewalks and stormwater facilities. 10: S. Barker Corridor (Sprague to 8th) Project Years: 2025-2027 Project Type: Reconstruction 6-Year TIP Cost: $8,950,000 Description: Reconstruct street with three lanes, bikes lanes, sidewalks, and stormwater as needed. Roundabouts at 4th and 8th Ave. This is a City Council identified legislative agenda project. 11: Broadway Preservation (Havana to Fancher) Project Years: 2026-2027 Project Type: Preservation 6-Year TIP Cost: $4,325,000 Description: Pavement preservation with stormwater upgrades and consideration for mid -block crossing near fairgrounds access. 12: Thierman Preservation (Sprague to Broadway) Project Years: 2025-2027 Project Type: Preservation 6-Year TIP Cost: $735,000 Description: Pavement preservation in parternship with Spokane County Water District #3. 13: Appleway Trail & Stormwater (Farr to Dishman Mica) Project Years: 2025-2027 Project Type: Pedestrian/Bicycle 6-Year TIP Cost: $1,324,150 Description: Extension of the Appleway Trail and reconstruction of stormwater facilities. 14: Flora Cross Course Pedestrian Facilities Project Years: 2026-2028 Project Type: Pedestrian/Bicycle 6-Year TIP Cost: $600,000 Description: Improve Flora to make pedestrian connection between Flora Cross Course and Euclid Ave. Page 1 of 3 Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances. 15: Mansfield Pedestrian Crossings Project Years: 2026-2027 Project Type: Pedestrian/Bicycle Description: Installation of enhanced pedestrian crossings. 16: Indiana Preservation (190 ramp to Desmet) Project Years: 2027-2028 Project Type: Preservation Description: Pavement preservation. 17: Wellesley Preservation (Isenhart to Trent) Project Years: 2028-2029 Project Type: Preservation Description: Pavement preservation with Stormwater and multimodal. 18: Sprague Preservation Phase 2 (University to Bowdish) Project Years: 2026-2028 Project Type: Preservation Description: Pavement preservation with locations of full depth patching. 6-Year TIP Cost: $259,000 6-Year TIP Cost: $1,500,000 6-Year TIP Cost: $2,650,000 6-Year TIP Cost: $2,189,000 19: Sullivan & Trent Interchange Project Years: 2024-2030 Project Type: Bridge 6-Year TIP Cost: $48,702,000 Description: Phased reconstruction of interchange, including widening of Sullivan between Kiernan and Wellesley adding ITS, center turn lane, lighting, and shared use path. This is a City Council identified legislative agenda project. 20: Fancher Preservation (Sprague to Trent) Project Years: 2025-2029 Project Type: Preservation 6-Year TIP Cost: $6,110,000 Description: Phased preservation project with asphalt grind and inlay with stormwater retrofits. Broadway -Trent planned for 2027 and Sprague - Broadway planned for 2028. 21: SR-27 & 16th Intersection Project Years: 2026-2029 Project Type: Intersection 6-Year TIP Cost: $6,900,000 Description: Add traffic control at five -leg intersecton (potential roundabout) with multimodal. 22: Northeast Sewer Extension Project Years: 2026-2029 Project Type: Reconstruction 6-Year TIP Cost: $6,320,000 Description: Phased street reconstruction and sewer extension with Spokane Co.: 2027 Donwood community at Barker/Euciid, 2029 Flora and Tschirley (Euclid -Garland), Dalton (Flora-Tschirley) consider multimodal along Flora. 23: Argonne & 1-90 Bridge Project Years: 2025-2030 Project Type: Bridge 6-Year TIP Cost: $25,080,000 Description: Bridge reconstruction, rechannelization, signal rework and multimodal. Concrete reconstruction of Argonne from 190 to Montgomery and a southerly connection at Mission. This is a City Council identified legislative agenda project. 24: Carnahan Street & Stormwater (8th to South Limit) Project Years: 2026-2030 Project Type: Stormwater 6-Year TIP Cost: $3,540,000 Description: 2027 stormwater conveyance upgrades with potential for pavement preservation and addition of bike/ped facilities. 25: Ridgemont Estates Street & Stormwater Project Years: 2026-2030 Project Type: Stormwater 6-Year TIP Cost: $8,995,000 Description: Stormwater improvements and road reconstruction in City's southeast neighborhood. 26: Street Maintenance and Operations Costs (Annual) Project Years: Annual Project Type: Preservation 6-Year TIP Cost: $3,060,000 Description: Ongoing street maintenance and operations activities in Street Fund 101, including bridge and traffic infrastructure. 27: Barker & 1-90 Interchange (Mission to Appleway) Project Years: 2026-2032 Project Type: Bridge 6-Year TIP Cost: $47,845,000 Description: Phased interchange reconstruction, reconfiguration of adjacent intersections, and widening Barker to a 4/5-lane urban section with multimodal facilities. This is a City Council identified legislative agenda project. 28: Local Access Street Improvements Project Years: Annual Project Type: Preservation 6-Year TIP Cost: $9,000,000 Description: Surface treatments (not shown on map), grind/inlays, and reconstruction projects as annual funding allocations allow. Potential project neighbhorhoods: Midilome, Carnahan, Ponderosa, Hillcrest, Sprague, Vera Crest. Page 2 of 3 Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances. 29: Citywide Safety Projects Project Years: Annual Project Type: Safety 6-Year TIP Cost: $7,000,000 Description: Consistent with Local/Regional Safety Plans; including arterial pedestrian facilities/crossings citywide (i.e. Sprague or Valleyway), particularly near schools. Funded projects identified separately in TIP. 30: Street Preservation Projects Project Years: Annual Project Type: Preservation 6-Year TIP Cost: $15,000,000 Description: 4th, 8th, 16th, 24th (Dishman-Sullivan), Dishman Mica, Appleway (E of Corbin), Vista(Appleway-Mission), Marietta (Sullivan -Euclid), 3rd and 4th (Havana-Fancher), Thierman (8th-Broadway), Ponderosa Area (Schafer, 44th, Sands), Sprague (Fancher-Herald, McDonald -Sullivan), Evergreen (Sprague-32nd), Bowdish and University (Sprague -Mission), Pines (16th-32nd) 31: Citywide Multimodal Improvements Project Years: Annual Project Type: Pedestrian/Bicycle 6-Year TIP Cost: $5,418,000 Description: Consistent with Active Transportation Plan such as: Appleway Trail (Farr to Havana), Flora (Centennial Trail -Flora Cross Course), River Loop (Sullivan -Flora Parks), and Millwood Trail (Fancher to Vista) and other prioritized projects. 32: Sullivan & Kiernan Intersection Project Years: 2029-2031 Project Type: Intersection 6-Year TIP Cost: $3,000,000 Description: Improve channelization and signal operations at intersection and reconstruct intersection with concrete and improved multimodal. Coordinate with County sewer extension project. 33: Sullivan & Marietta Intersection Project Years: 2029-2031 Project Type: Intersection 6-Year TIP Cost: $3,000,000 Description: Improve channelization and signal operations at intersection and reconstruct intersection with concrete. 34: Mirabeau & Mansfield Intersection Project Years: 2030-2032 Project Type: Intersection 6-Year TIP Cost: $3,500,000 Description: New intersection control (signal or roundabout) with multimodal. 35: Bowdish Reconstruction (Sprague to Dishman Mica) Project Years: 2030-2040 Project Type: Reconstruction 6-Year TIP Cost: $2,800,000 Description: Phased projects to reconstruct Sprague to Dishman Mica as urban section with bicycle and pedestrian facilities. May also include intersection improvements at 32nd Ave. and ITS. 36: 8th & Carnahan Intersection Project Years: 2030-2033 Project Type: Intersection 6-Year TIP Cost: $425,000 Description: Add intersection control (turn lanes, potential signal) and improve multimodal. 37: Sprague & Pines Intersection Project Years: 2031-2034 Project Type: Intersection 6-Year TIP Cost: $450,000 Description: Install SB right turn lane, EB left turn lane, and intersection control (signal and channelization) and improve multimodal. 38: 8th & Park Intersection Project Years: 2031-2034 Project Type: Intersection 6-Year TIP Cost: $340,000 Description: Provide new traffic signal or roundabout and improve multimodal. 39: Broadway (Flora to Barker) Project Years: 2032-2035 Project Type: Reconstruction Description: Expand 3-lane urban section with and improve multimodal. 6-Year TIP Cost: $50,000 40: Park & Mission Intersection Project Years: 2032-2035 Project Type: Intersection 6-Year TIP Cost: $50,000 Description: Improve channelization and evaluate for signal operations. 41: Flora & SR 290 Intersection Project Years: 2032-2034 Project Type: Intersection 6-Year TIP Cost: $100,000 Description: Improved traffic control with added turn lanes or roundabout, per adopted Planned Action Ordinance, including multimodal. 6-Year Total TIP Cost: $236,237,681 6-Year Total TIP Cost - By Year 2027 2028 2029 2030 2031 2032 $41,571,680 $28,072,000 $42,993,000 $45,811,000 $41,320,500 $36,469,500 Page 3 of 3 Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances. 1: Sprague Preservation (Bowdish to McDonald) Spokan�``— Uai ky Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $0 $0 $0 $0 $0 $0 $0 RW Secured $0 $0 $0 $0 $0 $0 $0 CN Secured $29,580 $0 $0 $0 $0 $0 $29,580 TOTAL 1 1 $29,580 $0 $0 $0 $0 $0 $29,580 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Closeout Total Project Years: 2024-2026 Total Project Cost: $3,208,000 Project Description: Pavement preservation. Funding Sources SourceName Funding City $361,000 STBG $2,847,000 Funding Sources Legend ■ STBG 88.7% City 11.3% Pagel of 41 2: Barker Road Reconstruction (Sprague to Appleway) Spokan``— Val ley Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $0 $0 $0 $0 $0 $0 $0 RW Secured $0 $0 $0 $0 $0 $0 $0 CN Secured $17,400 $0 $0 $0 $0 $0 $17,400 TOTAL 1 1 $17,400 $0 $0 $0 $0 $0 $17,400 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Closeout Total Project Years: 2024-2026 Total Project Cost: $2,200,000 Project Description: Reconstruction to urban 3-lane section. This is a City Council identified legislative agenda project. Funding Sources SourceName Funding City $62,100 FMSIB $1,740,000 STBG $397,900 Funding Sources Legend A4 FMSIB 79.1% ■ STBG 18.1 % City 2.8% Page 2 of 41 3: S. Sullivan Rd. Preservation (8th to 24th) Spokan�``1 >Uai ky Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $0 $0 $0 $0 $0 $0 $0 RW Secured $0 $0 $0 $0 $0 $0 $0 CN Secured $50,020 $0 $0 $0 $0 $0 $50,020 TOTAL 1 1 $50,020 $0 $0 $0 $0 $0 $50,020 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Closeout Total Project Years: 2024-2026 Total Project Cost: $5,643,000 Project Description: Preservation project with sidewalk infill, midblock pedestrian crossing, stormwater upgrades, and ITS expansion. Funding Sources SourceName Funding City $308,000 NHS $5,335,000 Funding Sources Legend E NHS 94.5% City 5.5% Page 3 of 41 4: Sullivan Preservation (UPRR to Kiernan) Spokan�``— Uai ky _ w Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $0 $0 $0 $0 $0 $0 $0 RW Secured $0 $0 $0 $0 $0 $0 $0 CN Secured $28,700 $0 $0 $0 $0 $0 $28,700 TOTAL 1 1 $28,690 $0 $0 $0 $0 $0 $28,690 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Closeout Total Project Years: 2025-2026 Total Project Cost: $3,070,000 Project Description: Preservation and stormwater project excluding intersection of Euclid. Funding Sources SourceName Funding City $1,570,000 STBG $1,500,000 Funding Sources Legend City 51.1% 0 STBG 48.9% 5: 32nd Ave Preservation (Pines to SR27) ne �'L�ailey. y it +" , E 29th Ave Y E 30th Ave � a, C i �j/1 fn E 31 St Ave E 32nd Ave N Ct _.* t.ilk � - m ,� +�.�� r• r `!� . ;. E 34th Ave U Spokane Valley ��, �, , , . L 0 a N N Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $0 $0 $0 $0 $0 $0 $0 RW Secured $0 $0 $0 $0 $0 $0 $0 CN Secured $29,250 $0 $0 $0 $0 $0 $29,250 TOTAL 1 1 $29,250 $0 $0 $0 $0 $0 $29,250 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Closeout Total Project Years: 2025-2026 Total Project Cost: $3,175,000 Project Description: Pavement preservation with Water District coordination. Funding Sources SourceName Funding City $875,000 NHS $2,300,000 Funding Sources Legend NHS 72.4% i City 27.6% Page 5 of 41 6: Arterial School Crossings >N7ailey- n� Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 W2031 2032 6-Year Total PE Secured $0 $0 $0 $0 $0 $0 $0 RW $0 $0 $0 $0 $0 $0 $0 CN Secured $11,917 $0 $0 $0 $0 $0 $11,917 TOTAL I 1 $11,190 $0 $0 $0 $0 $0 $11,190 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Closeout Total Project Years: 2025-2026 Total Project Cost: $1,191, 700 Project Description: New enchanced crossings on 32nd, Pines, and Broadway. Funding Sources SourceName Funding SRTS 1 $1,263,700 Funding Sources Legend SRTS 100.0% Page 6 of 41 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Closeout Total Project Years: 2025-2026 Total Project Cost: $1,191, 700 Project Description: New enchanced crossings on 32nd, Pines, and Broadway. Funding Sources SourceName Funding SRTS 1 $1,263,700 Funding Sources Legend SRTS 100.0% Page 6 of 41 7: Pines (SR27) & BNSF Grade Separation Project 'SW5„- .,;�Vailey Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $0 $0 $0 $0 $0 $0 $0 RW Secured $0 $0 $0 $0 $0 $0 $0 CN Secured $2,004,400 $0 $0 $0 $0 $0 $2,004,400 TOTAL 1 $2,004,400 $0 $0 $0 $0 $0 $2,004,400 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Bridge Total Project Years: 2019-2027 Total Project Cost: $47,839,000 Project Description: Construct Grade Separation at Pines(SR27)/BNSF RR/Trent (SR290). Funding Sources SourceName Funding BUILD $21,689,000 City $4,703,000 CMAQ $6,405,000 DEMO $6,247,000 Other State $5,000,000 STBG $3,795,000 Funding Sources Legend BUILD 45.3% ■ CMAQ 13.4% DEMO 13.1% ■ Other State 10.5% City 9.8% Page 7 of 41 8: Pines Preservation (32nd to 4Oth) k4e� -'PT" E 32nc' ar W1,W, NDi{dne �'L�ailey. ram. i" r r r fi s:'� Spokane Vallev 1 s I ,1 Current 6-Year TIP A Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $0 $0 $0 $0 $0 $0 $0 RW $0 $0 $0 $0 $0 $0 $0 CN Secured $1,500,000 $0 $0 $0 $0 $0 $1,500,000 TOTAL 1 1 $1,500,000 $0 $0 $0 $0 $0 $1,500,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Preservation Total Project Years: 2025-2027 Total Project Cost: $1,585,000 Project Description: Pavement preservation with bike and pedestrian facilities. Funding Sources SourceName Funding City 1 $1,585,000 Funding Sources Legend City 100.0% Page 8 of 41 9: Sullivan Preservation (Spokane River to UPRR) 1` 'L�alley. . e�, r • w, _ •mod-�`"'r �� � � .++ ``7^^ OF vJ z Spokane Valley E .. i + +► I F��Ora p' I Iv } Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $50,000 $0 $0 $0 $0 $0 $50,000 RW $0 $0 $0 $0 $0 $0 $0 CN Secured $3,300,000 $0 $0 $0 $0 $0 $3,300,000 TOTAL 1 1 $3,350,000 $0 $0 $0 $0 $0 $3,350,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Preservation Total Project Years: 2025-2027 Total Project Cost: $5,730,000 Project Description: Preservation project with new signal, park access roads, sidewalks and stormwater facilities. Funding Sources Funding Sources SourceName Funding City 1 $5,730,000 Legend City 100.0% Page 9 of 41 10: S. Barker Corridor (Sprague to 8th) Spokan``1 Ual[ey Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $0 $0 $0 $0 $0 $0 $0 RW Secured $0 $0 $0 $0 $0 $0 $0 CN Secured $8,950,000 $0 $0 $0 $0 $0 $8,950,000 TOTAL 1 1 $8,950,000 $0 $0 $0 $0 $0 $8,950,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Reconstruction Total Project Years: 2025-2027 Total Project Cost: $10,150,000 Project Description: Reconstruct street with three lanes, bikes lanes, sidewalks, and stormwater as needed. Roundabouts at 4th and 8th Ave. This is a City Council identified legislative agenda project. Funding Sources SourceName Funding City $1,664,992 DEMO $1,483,475 HSIP $1,500,000 PBP j $1,665,000 TIB 1 $3,836,533 Funding Sources Legend TIB 37.8% ■ PBP 16.4% ■ City 16.4% ■ HSIP 14.8% ■ DEMO 14.6% Page 10 of 41 11: Broadway Preservation (Havana to Fancher) Spokan�``— Uai ky Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $0 $0 $0 $0 $0 $0 $0 RW Secured $0 $0 $0 $0 $0 $0 $0 CN Secured $4,325,000 $0 $0 $0 $0 $0 $4,325,000 TOTAL 1 1 $4,325,000 $0 $0 $0 $0 $0 $4,325,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Preservation Total Project Years: 2026-2027 Total Project Cost: $4,500,000 Project Description: Pavement preservation with stormwater upgrades and consideration for mid -block crossing near fairgrounds access. Funding Sources SourceName Funding City $1,000,000 NHS $3,500,000 Funding Sources Legend NHS 77.8% ■ city 22.2% Page 11 of 41 12: Thierman Preservation (Sprague to Broadway) Spokatrl'`1 ,��1[ey- - — E-Broadway Ave a �I � �'- ingfield Ave' �° �e 'a" `'.r��' n OEM LU Yy 4 t a Fr F } ► ! t Kiaersiae Hae s Uniion.Racific ai roads -A -�t- y -{ `t E Sprague Ave, — Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $15,000 $0 $0 $0 $0 $0 $15,000 RW $0 $0 $0 $0 $0 $0 $0 CN Secured $720,000 $0 $0 $0 $0 $0 $720,000 TOTAL 1 1 $735,000 $0 $0 $0 $0 $0 $735,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Preservation Total Project Years: 2025-2027 Total Project Cost: $750,000 Project Description: Pavement preservation in parternship with Spokane County Water District #3. Funding Sources SourceName Funding City 1 $750,000 Funding Sources Legend City 100.0% Page 12 of 41 13: Appleway Trail & Stormwater (Farr to Dishman Mica) Spokane Ual[ey K - E 1st Ave 610 OL LL �.� k E Appleway Blvd vi 7 = } @ Spokane Valley 4" seeC—ar IF Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $24,150 $0 $0 $0 $0 $0 $24,150 RW $0 $0 $0 $0 $0 $0 $0 CN Secured $1,300,000 $0 $0 $0 $0 $0 $1,300,000 TOTAL 1 1 $1,324,150 $0 $0 $0 $0 $0 $1,324,150 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Pedestrian/Bicycle Total Project Years: 2025-2027 Total Project Cost: $1,405,000 Project Description: Extension of the Appleway Trail and reconstruction of stormwater facilities. Funding Sources SourceName Funding City $474,000 STBG-SA $931,000 Funding Sources Legend ■ STBG-SA 66.3% ■ City 33.7% Page 13 of 41 14: Flora Cross Course Pedestrian Facilities ��— .;W*VAtky- Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $100,000 $0 $0 $0 $0 $0 $100,000 RW Planned $100,000 $0 $0 $0 $0 $0 $100,000 CN Planned $0 $400,000 $0 $0 $0 $0 $400,000 TOTAL 1 1 $200,000 $400,000 $0 $0 $0 $0 $600,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Pedestrian/Bicycle Total Project Years: 2026-2028 Total Project Cost: $600,000 Project Description: Improve Flora to make pedestrian connection between Flora Cross Course and Euclid Ave. Funding Sources SourceName Funding Other 1 $600,000 Funding Sources Legend *k Other 100.0% Page 14 of 41 15: Mansfield Pedestrian Crossings Spokan�``— Uai ky Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $0 $0 $0 $0 $0 $0 $0 RW $0 $0 $0 $0 $0 $0 $0 CN Secured $259,000 $0 $0 $0 $0 $0 $259,000 TOTAL 1 1 $259,000 $0 $0 $0 $0 $0 $259,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Pedestrian/Bicycle Total Project Years: 2026-2027 Total Project Cost: $285,000 Project Description: Installation of enhanced pedestrian crossings. Funding Sources SourceName Funding PBP 1 $285,000 Funding Sources Legend lk PBP 100.0% Page 15 of 41 16: Indiana Preservation (190 ramp to Desmet) Spikan' a `' > Leal ley Current 6-Year TIP Phased Funding atus - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $50,000 $0 $0 $0 $0 $0 $50,000 RW $0 $0 $0 $0 $0 $0 $0 CN Planned $0 $1,450,000 $0 $0 $0 $0 $1,450,000 TOTAL j 1 $50,000 j $1,450,000 j $0 j $0 j $0 j $0 j $1,500,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Preservation Total Project Years: 2027-2028 Total Project Cost: $1,500,000 Project Description: Pavement preservation. Funding Sources SourceName Funding City 1 $1,500,000 Funding Sources Legend City 100.0% Page 16 of 41 17: Wellesley Preservation (Isenhart to Trent) Sprika . to Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $0 $150,000 $0 $0 $0 $0 $150,000 RW $0 $0 $0 $0 $0 $0 $0 CN Planned $0 $0 $2,500,000 $0 $0 $0 $2,500,000 TOTAL 1 $0 $150,000 $2,500,000 $0 $0 $0 $2,650,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Preservation Total Project Years: 2028-2029 Total Project Cost: $2,650,000 Project Description: Pavement preservation with Stormwater and multimodal. Funding Sources SourceName Funding City 1 $2,650,000 Funding Sources Legend City 100.0% Page 17 of 41 18: Sprague Preservation Phase 2 (University to Bowdish) S`11``- >Uai ky Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $0 $0 $0 $0 $0 $0 $0 RW Secured $80,000 $0 $0 $0 $0 $0 $80,000 CN Secured $0 $2,109,000 $0 $0 $0 $0 $2,109,000 TOTAL $80,000 $2,109,000 $0 $0 $0 $0 $2,189,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Preservation Total Project Years: 2026-2028 Total Project Cost: $2,287,000 Project Description: Pavement preservation with locations of full depth patching. Funding Sources SourceName Funding City $937,000 STBG $1,350,000 Funding Sources Legend ■ STBG 59.0% City 41.0% Page 18 of 41 19: Sullivan & Trent Interchange Spikan' a `' > Leal ley Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $543,000 $0 $0 $0 $0 $0 $543,000 RW Partial $3,800,000 $1,000,000 $0 $0 $0 $0 $4,800,000 CN Partial $0 $3,000,000 $3,000,000 $17,000,000 $20,000,000 $0 $43,359,000 TOTAL 1 1 $4,343,000 $4,000,000 $3,000,000 $17,000,000 $20,000,000 $0 $48,702,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Bridge Total Project Years: 2024-2030 Total Project Cost: $53,793,000 Project Description: Phased reconstruction of interchange, including widening of Sullivan between Kiernan and Wellesley adding ITS, center turn lane, lighting, and shared use path. This is a City Council identified legislative agenda project. Funding Sources SourceName Funding City $3,301,000 DEMO $9,650,000 NHFP $3,053,000 Other j $31,422,000 STBG 1 $6,367,000 Funding Sources Legend Other 58.4 % ■ DEMO 17.9 % ■ STBG 11.8 % ■ City 6.2% ■ NHFP 5.7% Page 19 of 41 20: Fancher Preservation (Sprague to Trent) Spokan�``— Uai ky Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $45,000 $15,000 $0 $0 $0 $0 $60,000 RW Secured $25,000 $25,000 $0 $0 $0 $0 $50,000 CN Secured $3,600,000 $2,400,000 $0 $0 $0 $0 $6,000,000 TOTAL 1 1 $3,670,000 $2,440,000 $0 $0 $0 $0 $6,110,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Preservation Total Project Years: 2025-2029 Total Project Cost: $6,200,000 Project Description: Phased preservation project with asphalt grind and inlay with stormwater retrofits. Broadway -Trent planned for 2027 and Sprague -Broadway planned for 2028. Funding Sources SourceName Funding City 1 $6,200,000 Funding Sources Legend City 100.0% Page 20 of 41 21: SR-27 & 16th Intersection *4 �'L�alley. Vurrent 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $150,000 $0 $0 $0 $0 $0 $150,000 RW Planned $0 $200,000 $0 $0 $0 $0 $200,000 CN Planned $0 $0 $6,550,000 $0 $0 $0 $6,550,000 TOTAL 1 1 $150,000 $200,000 $6,550,000 $0 $0 $0 $6,900,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Intersection Total Project Years: 2026-2029 Total Project Cost: $7,050,000 Project Description: Add traffic control at five -leg intersecton (potential roundabout) with multimodal. Funding Sources SourceName Funding DEV $300,000 Other $6,750,000 Funding Sources 1 in Legend Other 95.7% N DEV 4.3% Page 21 of 41 22: Northeast Sewer Extension Spikan' a `' .,;o*%I ky Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $100,000 $100,000 $0 $0 $0 $0 $200,000 RW $0 $0 $0 $0 $0 $0 $0 CN Partial $1,400,000 $0 $4,720,000 $0 $0 $0 $6,120,000 TOTAL 1 1 $1,500,000 $100,000 $4,720,000 $0 $0 $0 $6,320,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Reconstruction Total Project Years: 2026-2029 Total Project Cost: $6,450,000 Project Description: Phased street reconstruction and sewer extension with Spokane Co.: 2027 Donwood community at Barker/Euciid, 2029 Flora and Tschirley (Euclid -Garland), Dalton (Flora- Tschirley) consider multimodal along Flora. Funding Sources SourceName Funding City $1,000,000 Other $5,450,000 Funding Sources Legend ■ Other 84.5% ■ City 15.5% Page 22 of 41 23: Argonne & 1-90 Bridge ��� .,;o0%t1ey- Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $1,050,000 $0 $0 $0 $0 $0 $1,050,000 RW Partial $0 $30,000 $0 $0 $0 $0 $30,000 CN Partial $0 $0 $12,000,000 $12,000,000 $0 $0 $24,000,000 TOTAL 1 1 $1,050,000 $30,000 $12,000,000 $12,000,000 $0 $0 $25,080,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Bridge Total Project Years: 2025-2030 Total Project Cost: $27,530,000 Project Description: Bridge reconstruction, rechannel ization, signal rework and multimodal. Concrete reconstruction of Argonne from 190 to Montgomery and a southerly connection at Mission. This is a City Council identified legislative agenda project. Funding Sources SourceName Funding City $202,000 FMSIB $2,000,000 Other $24,030,000 STBG $1,298,000 Funding Sources Legend Other 87.3% ■ FMSIB 7.3% IM4 ■ STBG 4.7% City 0.7% Page 23 of 41 24: Carnahan Street & Stormwater (8th to South Limit) 8th Ave ir I •- _'.MM Current 6-Year TIP Phased Funding Status - By Year Spokane Ual[ey Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Partial $30,000 $210,000 $0 $0 $0 $0 $240,000 RW Planned $0 $0 $50,000 $0 $0 $0 $50,000 CN Planned $260,000 $0 $0 $2,990,000 $0 $0 $3,250,000 TOTAL 1 1 $290,000 $210,000 $50,000 $2,990,000 $0 $0 $3,540,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Stormwater Total Project Years: 2026-2030 Total Project Cost: $3,600,000 Project Description: 2027 stormwater conveyance upgrades with potential for pavement preservation and addition of bike/ped facilities. Funding Sources Funding Sources SourceName Funding City $350,000 Other $3,250,000 Legend ■ Other 90.3% ■ City 9.7% 4& 1 Page 24 of 41 25: Ridgemont Estates Street & Stormwater *4n -- .O Valley Current 6-Fear i W Pt, A Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Secured $60,000 $40,000 $60,000 $0 $0 $0 $160,000 RW $0 $0 $0 $0 $0 $0 $0 CN Partial $2,325,000 $1,860,000 $0 $4,650,000 $0 $0 $8,835,000 TOTAL 1 1 $2,385,000 $1,900,000 $60,000 $4,650,000 $0 $0 $8,995,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Stormwater Total Project Years: 2026-2030 Total Project Cost: $9,500,000 Project Description: Stormwater improvements and road reconstruction in City's southeast neighborhood. Funding Sources SourceName Funding City 1 $9,500,000 Funding Sources Legend City 100.0% 26: Street Maintenance and Operations Costs (Annual) an- ,.�Vailey Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE $0 $0 $0 $0 $0 $0 $0 RW $0 $0 $0 $0 $0 $0 $0 CN Secured $510,000 $510,000 $510,000 $510,000 $510,000 $510,000 $3,060,000 TOTAL 1 1 $510,000 $510,000 $510,000 $510,000 $510,000 $510,000 $3,060,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Preservation Total Project Years: Annual Total Project Cost: $3,060,000 Project Description: Ongoing street maintenance and operations activities in Street Fund 101, including bridge and traffic infrastructure. Funding Sources SourceName Funding City 1 $3,060,000 Funding Sources Legend City 100.0% Page 26 of 41 27: Barker & 1-90 Interchange (Mission to Appleway) ��— .,;o0%t1ey- Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Partial $1,230,000 $3,000,000 $1,000,000 $0 $0 $0 $5,230,000 RW Planned $2,000,000 $5,000,000 $500,000 $500,000 $0 $0 $8,000,000 CN Planned $0 $0 $6,865,000 $0 $5,750,000 $22,000,000 $34,615,000 TOTAL 1 $3,230,000 $8,000,000 $8,365,000 $500,000 $5,750,000 $22,000,000 $47,845,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Bridge Total Project Years: 2026-2032 Total Project Cost: $71,757,000 Project Description: Phased interchange reconstruction, reconfiguration of adjacent intersections, and widening Barker to a 4/5-lane urban section with multimodal facilities. This is a City Council identified legislative agenda project. Funding Sources SourceName Funding City $468,000 DEMO $1,517,000 FMSIB $1,260,000 Other j $68,600,000 Funding Sources Legend Other 95.5% ® DEMO 2.1 % FMSIB 1.8% City 0.7% Page 27 of 41 28: Local Access Street Improvements Spokan�``— Uai ky Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $100,000 $100,000 $100,000 $100,000 $100,000 $100,000 $600,000 RW $0 $0 $0 $0 $0 $0 CN Planned $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $8,400,000 TOTAL 1 1 $1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000 $9,000,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Preservation Total Project Years: Annual Total Project Cost: $9,000,000 Project Description: Surface treatments (not shown on map), grind/inlays, and reconstruction projects as annual funding allocations allow. Potential project neighbhorhoods: Midilome, Carnahan, Ponderosa, Hillcrest, Sprague, Vera Crest. Funding Sources SourceName Funding City 1 $9,000,000 Funding Sources Legend City 100.0% Page 28 of 41 29: Citywide Safety Projects Spokan�``— L7ai ky Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $0 $18,000 $48,000 $18,000 $48,000 $18,000 $150,000 RW $0 $0 $0 $0 $0 $0 $0 CN Planned $0 $2,055,000 $342,500 $2,055,000 $342,500 $2,055,000 $6,850,000 TOTAL 1 1 $0 $2,073,000 $390,500 $2,073,000 $390,500 $2,073,000 1$7,000,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Safety Total Project Years: Annual Total Project Cost: $7,000,000 Project Description: Consistent with Local/Regional Safety Plans; including arterial pedestrian facilities/crossings citywide (i.e. Sprague or Valleyway), particularly near schools. Funded projects identified separately in TIP. Funding Sources SourceName Funding City $700,000 HSIP $6,300,000 Funding Sources Legend HSIP 90.0% City 10.0% Page 29 of 41 30: Street Preservation Projects >N7aiky n� Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $0 $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 RW $0 $0 $0 $0 $0 $0 $0 CN Planned $0 $2,900,000 $2,900,000 $2,900,000 $2,900,000 $2,900,000 $14,500,000 TOTAL 1 1 $0 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $15,000,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Preservation Total Project Years: Annual Total Project Cost: $15,000,000 Project Description: 4th, 8th, 16th, 24th (Dish man -Su llivan), Dishman Mica, Appleway(E of Corbin), Vista(Appleway-Mission), Marietta(Sullivan-Euclid), 3rd and 4th (Havana-Fancher), Thierman(8th-Broadway), Ponderosa Area (Schafer, 44th, Sands), Sprague (Fancher-Herald, McDonald -Sullivan), Evergreen (Sprague-32nd), Bowdish and University (Sprague -Mission), Pines (16th-32nd) Funding Sources SourceName Funding City 1 $15,000,000 Funding Sources Legend City 100.0% Page 30 of 41 31: Citywide Multimodal Improvements Spikan' a `' > Leal ley Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $0 $0 $187,500 $187,500 $187,500 $187,500 $750,000 RW Planned $0 $0 $0 $198,000 $0 $0 $198,000 CN Planned $0 $0 $0 $0 $4,470,000 $0 $4,470,000 TOTAL I I $0 $0 $187,500 $385,500 $4,657,500 $187,500 $5,418,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Pedestrian/Bicycle Total Project Years: Annual Total Project Cost: $24,200,000 Project Description: Consistent with Active Transportation Plan such as: Appleway Trail (Farr to Havana), Flora (Centennial Trail -Flora Cross Course), River Loop (Sullivan -Flora Parks), and Millwood Trail (Fancher to Vista) and other prioritized projects. Funding Sources SourceName Funding Other 1 $24,200,000 Funding Sources Legend Other 100.0% Page 31 of 41 32: Sullivan & Kiernan Intersection Spokan�``1 Uai ky Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $0 $0 $80,000 $20,000 $0 $0 $100,000 RW Planned $0 $0 $0 $400,000 $100,000 $0 $500,000 CN Planned $0 $0 $0 $0 $2,400,000 $0 $2,400,000 TOTAL I I $0 $0 $80,000 $420,000 $2,500,000 $0 $3,000,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Intersection Total Project Years: 2029-2031 Total Project Cost: $3,000,000 Project Description: Improve channelization and signal operations at intersection and reconstruct intersection with concrete and improved multimodal. Coordinate with County sewer extension project. Funding Sources SourceName Funding Other 1 $3,000,000 Funding Sources lotLegend Other 100.0% Page 32 of 41 33: Sullivan & Marietta Intersection *4n -- �'L�alley Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $0 $0 $80,000 $20,000 $0 $0 $100,000 RW Planned $0 $0 $0 $400,000 $100,000 $0 $500,000 CN Planned $0 $0 $0 $0 $2,400,000 $0 $2,400,000 TOTAL I I $0 $0 $80,000 $420,000 $2,500,000 $0 $3,000,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Intersection Total Project Years: 2029-2031 Total Project Cost: $3,000,000 Project Description: Improve channelization and signal operations at intersection and reconstruct intersection with concrete. Funding Sources SourceName Funding Other 1 $3,000,000 Funding Sources Legend 19 Other 100.0% Page 33 of 41 34: Mirabeau & Mansfield Intersection +y Ze 5;2 r, Scale: 1:1,000 � "' Current 6-Year TIP Phased Funding Status - By Year 1 Spokane Ual[ey • Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Partial $0 $0 $0 $75,000 $75,000 $0 $150,000 RW Planned $0 $0 $0 $0 $50,000 $50,000 $100,000 CN Planned $0 $0 $0 $0 $0 $3,250,000 $3,250,000 TOTAL I I $0 $0 $0 $75,000 $125,000 $3,300,000 $3,500,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Intersection Total Project Years: 2030-2032 Total Project Cost: $3,500,000 Project Description: New intersection control (signal or roundabout) with multimodal. Funding Sources Funding Sources SourceName Funding DEV $75,000 Other $3,425,000 Legend Other 97.9% ® DEV 2.1 % Page 34 of 41 35: Bowdish Reconstruction (Sprague to Dishman Mica) 'SW5„- .,Vatley Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $0 $0 $0 $200,000 $0 $200,000 $400,000 RW Planned $0 $0 $0 $0 $100,000 $0 $100,000 CN Planned $0 $0 $0 $0 $0 $2,300,000 $2,300,000 TOTAL I $0 $0 $0 $200,000 $100,000 $2,500,000 $2,800,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Reconstruction Total Project Years: 2030-2040 Total Project Cost: $13,000,000 Project Description: Phased projects to reconstruct Sprague to Dishman Mica as urban section with bicycle and pedestrian facilities. May also include intersection improvements at 32nd Ave. and ITS. Funding Sources SourceName Funding Other 1 $13,000,000 Funding Sources Legend Other 100.0% Page 35 of 41 36: 8th & Carnahan Intersection Spokan�``— >Uai ky Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $0 $0 $0 $87,500 $87,500 $0 $175,000 RW Planned $0 $0 $0 $0 $0 $250,000 $250,000 CN Planned $0 $0 $0 $0 $0 $0 $0 TOTAL I I $0 $0 $0 $87,500 $87,500 $250,000 $425,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Intersection Total Project Years: 2030-2033 Total Project Cost: $3,000,000 Project Description: Add intersection control (turn lanes, potential signal) and improve multimodal. Funding Sources SourceName Funding Other 1 $3,000,000 Funding Sources Legend Other 100.0% Page 36 of 41 37: Sprague & Pines Intersection Ilk 4L IL It 4 Or M. IlkIt 1 � - .kAN " 41 4 Ave E spragueor N r `yam Current 6-Year TIP Phased Funding Status - By Year 1` 'L�alley. Spokane Valley N A Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $0 $0 $0 $0 $150,000 $150,000 $300,000 RW Planned $0 $0 $0 $0 $0 $150,000 $150,000 CN Planned $0 $0 $0 $0 $0 $0 $0 TOTAL I I $0 $0 $0 $0 $150,000 $300,000 $450,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Intersection Total Project Years: 2031-2034 Total Project Cost: $2,600,000 Project Description: Install SB right turn lane, EB left turn lane, and intersection control (signal and channelization) and improve multimodal. Funding Sources SourceName Funding Other 1 $2,600,000 Funding Sources Legend Other 100.0% Page 37 of 41 38: 8th & Park Intersection *4 �'L�alley. Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $0 $0 $0 $0 $50,000 $50,000 $100,000 RW Planned $0 $0 $0 $0 $0 $240,000 $240,000 CN Planned $0 $0 $0 $0 $0 $0 $0 TOTAL I I $0 $0 $0 $0 $50,000 $290,000 $340,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Intersection Total Project Years: 2031-2034 Total Project Cost: $3,000,000 Project Description: Provide new traffic signal or roundabout and improve multimodal. Funding Sources SourceName Funding Other 1 $3,000,000 Funding Sources Legend *k Other 100.0% Page 38 of 41 39: Broadway (Flora to Barker) Spokan�``— Ual[ey Doo - - Mo-�, 3y 31111L `. ~rV • w ,. [2 . 0 0liiYlly �j . Or e 0.0 iq 6 Scale:-1-8 000 Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Partial $0 $0 $0 $0 $0 $50,000 $50,000 RW Partial $0 $0 $0 $0 $0 $0 $0 CN Partial $0 $0 $0 $0 $0 $0 $0 TOTAL I I $0 $0 $0 $0 $0 $50,000 $50,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Reconstruction Total Project Years: 2032-2035 Total Project Cost: $5,000,000 Project Description: Expand 3-lane urban section with and improve multimodal. Funding Sources Funding Sources SourceName Funding Other 1 $5,000,000 Legend Other 100.0% Page 39 of 41 40: Park & Mission Intersection 4 ° j y Mission, A _ L Current 6-Year TIP Phased Funding Status - By Year ne �'L�ailey. Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $0 $0 $0 $0 $0 $50,000 $50,000 RW Planned $0 $0 $0 $0 $0 $0 $0 CN Planned $0 $0 $0 $0 $0 $0 $0 TOTAL I $0 $0 $0 $0 $0 $50,000 $50,000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Intersection Total Project Years: 2032-2035 Total Project Cost: $2,500,000 Project Description: Improve channelization and evaluate for signal operations. Funding Sources SourceName Funding Other 1 $2,500,000 Funding Sources Legend Other 100.0% Page 40 of 41 41: Flora & SR 290 Intersection *4 �'L�alley. . 3 1� * An r� 7 Ito w 29 Spokanf e , s9r!� d4— Current 6-Year TIP Phased Funding Status - By Year Phase Status 2027 2028 2029 2030 2031 2032 6-Year Total PE Planned $0 $0 $0 $0 $0 $100,000 $100,000 RW Planned $0 $0 $0 $0 $0 $0 $0 CN Planned $0 $0 $0 $0 $0 $0 $0 TOTAL I $0 $0 $0 $0 $0 $100,000 $100-000 Project Summary Summary information is for the entire project and may extend beyond the 6-Year TIP time frame. Project Type: Intersection Total Project Years: 2032-2034 Total Project Cost: $4,000,000 Project Description: Improved traffic control with added turn lanes or roundabout, per adopted Planned Action Ordinance, including multimodal. Funding Sources SourceName Funding Other 1 $4,000,000 Funding Sources Legend Other 100.0%