10-033.00 Morgen & Oswood: Barker Bridge ReplacementWashhiWon State Change Order Department of Transportation Date 10/23/2009 Page I o f 2 Pages Contract Number 08 -017 (CIP -0003) Federal Aid Number BRM 4123(004) Contract Title Barker Road Bridge Replacement Change Order Number 7 Prime Contractor Morgen & Oswood Construction Co., Inc. ® Ordered by Engineer under the terms of Section 1 -04.4 of the Standard Specifications 0 Change proposed by Contractor Endorsed By Surety Consent TRA 03FANY OF AMERICA Contractor Attor act v ' Mrs 'L U3 to 03/05/2010 _ Date ' Date Original Contract Amount Current Contract Amount Estimated Net Change This Order Estimated Contract Total After Change 9,449,354.75 9,318,259.07 22,332.48 9,340,591.55 Approval Recommended ❑ Approved App o ed Project Engine pproving th ity per C.A. Agreement q--"> l d eu o Date Dat Approval Recommended ❑ Approved Other Approval When Required OL .- 2*- Lo /O By Signature Date nn Sf0 k 6 f'�le - rtQ l Ot U 71L°� Date Representing DOT Form 140 -005 EF Revised 4/06 (%o t0 -033 CHANGE ORDER Project: Barker Road Bridge Replacement Page 2 of 2 Contract No.: 08 -017 (CIP -0003) Change Order No. 7 Federal Aid Number: BRM 4123 (004) The Contract is revised as follows: Description of Work Schedule B - Group 3; Spokane County Sanitary Sewer Contractor shall install 6 -inch diameter ductile iron sewer pipe with joint restraint gaskets within the bridge supported pressure sewer casing pipe. Materials Ductile iron sewer pipe shall conform to Section 7 -17.2 of the Standard Specifications. Joint restraint gaskets shall be Field Lok® manufactured by U. S. Pipe and Foundry Company, or approved equal. Construction Requirements Construction shall conform to Section 7 -09 of the Special Provisions. Measurement No specific unit of measurement will apply to the lump sum item of "Change Order No. 7 - Ductile Iron Pressure Sewer Pipe, 6 -In. Diam." Payment Payment will be made for "Change Order No. 7 - Ductile Iron Pressure Sewer Pipe, 6 -In. Diam." in the lump sum amount of $20,545.06 plus applicable sales tax. The lump sum payment shall be full compensation for all costs incurred to furnish and install ductile iron pressure sewer pipe, joint restraint gaskets, testing, and flushing. Working Days The Contract time is unchanged. Attachments None.