10-090.00 Morgen & Oswood: Barker Bridge ReplacementVjb~on State
Deparbnent of Transportation
Change Order
Date 6/1/2010
Page 1 of 3 Pages
Contract Number 08 -017 (CIP -0003) Federal Aid Number BRM 4123(004)
Contract Title Barker Road Bridge Replacement
Change Order Number 8
Prime Contractor morgen & USWood Construction Co., Inc.
® Ordered by Engineer under the terms of Section 1 -04.4 of the Standard Specifications
❑ Chanae proposed by Contractor
Endorsed By Surety Consent
TTRAVFIJERS Ty SS ANY OF AMERICA
of
Contractor Attorne a JOHN D. LEAF
, JULY 20, 2010
Date Date
Original Contract Amount
Current Contract Amount
Estimated Net Change This Order
9,449,354.
9,340,591.55
- 2,606.00
Estimated Contract Total After Change 9,337,985.55
Approval Recommended Approved
Approve
Project Engine
pproving Auth city per C.A. Agreement
Date —^ `
Date
7 Approval Recommended ❑Approved
Other Approval When Required
B
Signature Date
26 JUL`/ 21IN6
Date
Representing
DOT Form 140.005 EF
Revised 4106
CHANGE ORDER
Project: Barker Road Bridge Replacement
Contract No.: 08 -017 (CIP -0003)
Federal Aid Number: BRM 4123 (004)
The Contract is revised as follows:
Description of Work
Page 2 of 3
Change Order No. 8
Schedule C - Group 6; City of Spokane Valley
The artwork form liner work specified in Section 6-02 of the Special Provisions is deleted
from the Contract.
the following Section 6 -02 Special Provisions are incorporated into the Contract:
Finishing Concrete Surfaces
Section 6 -02.3(14) is supplemented with the following:
Artwork images shall be etched into the bridge traffic barrier concrete at the
locations shown on the Drawings up to 1/4 -inch depth by sandblasting. Use
stencil material that will achieve a clean, sharp line between sandblasted and
non - sandblasted areas.
Prepare concrete and apply stain to etched images per manufacturer's
recommendations. Concrete shall be cured 28 days minimum prior to
sandblasting. Stain shall be Proline EZ Accent stain, or approved equal. Stain
color options shall be submitted to the City for selection_ Apply sealer to stained
concrete per manufacturer's recommendations. Sealer shall be Proline EZ Accent
sealer, or approved equal.
Provide 2 -foot by 4 -foot sample of sandblast and stain finish prior to
construction.
Measurement
No specific unit of measurement will apply to the lump sum item of " "Bridge Traffic
Barrier Artwork Sandblasting and Staining."
Payment
Section 6 -02.5 is supplemented with the following:
Payment Item No. 57, "Cl - bridge 'Traffic barrier Artwork," is deleted from the
Contract. The associated deduct amount is $28,000.00_
Payment for "Bridge Traffic Barrier Artwork Sandblasting and Staining" will be
made in the lump sum amount of $25,394.00. The lump sum payment shall
constitute full compensation for all labor, materials, and equipment to complete
the work as shown on the plans and as specified. No separate payment will be
made for the sample panel.
n r
CHANGE ORDER
Project: Barker Road Bridge Replacement
Contract No.: 08 -017 (CIP -0003)
Federal Aid Number: BRM 4123 (004)
Working Days
The Contract time is extended by ten (10) working days.
Attachments
None.
Page 3 of 3
Change Order No. S