2008 Business Plan Spoka••0°'`4*, ft,
ne
\itlleyR
2008 Business Plan
City of Spokane Valley 2008 Business Plan
Table of Contents
Executive Summary 2
The Initial Plan 2
Business Plan Process 3
Strategic Service Delivery Areas 4
Departmental Business Plan 5
Future Business Plan Concepts 5
Executive & Legislative Support City Manager/City Clerk 6
Department: Executive & Legislative Support Office of the City Attorney 9
Operations & Administrative 12
Operations & Administrative Services —Finance &Information Technology 15
Community Development 18
Department: Parks & Recreation 22
Public Works 26
Citywide Business Plan 31
Pending Ideas 32
Appendix 34
Foundation of the City of Spokane Valley 34
Core Beliefs 34
Vision Statement 36
City of Spokane Valley Values 36
Customer Service 37
Information Input 38
Internal Input 38
External Input 39
Council Goals 40
- 1 -
City of Spokane Valley 2008 Business Plan
Executive Summary
The City of Spokane Valley's Fiscal Year 2008 Business Plan is the communication line connecting
the strategic planning process to the community priorities that will shape the future of our
community. One of the City Council's adopted 2007 budget goals was to create the City's first six-
year Business Plan, which will be updated on an annual basis. This 2008 Business Plan represents
the culmination of that goal.
Some recommendations of the Business Plan have already been integrated and adopted in the City's
2008 Budget. However, it is important to note that the plan is still the first iteration of the City's
efforts in this area. Since we are still in our five-year start-up mode, many of our programs and
services are still under development. In subsequent years, the business plan will continue to evolve.
The start-up mode also means there are some potential services we aren't doing at all right now and
on which we have not had the opportunity to initiate a policy discussion. To address this, the initial
plan is divided into two sections - first, the initial plan itself, which includes the issues and
associated staffing and cost proposals. The second section identifies pending ideas. These are a
heads up of issues and proposals that are worth further consideration.
The initial business plan includes thirteen new positions over the six year period. The estimated
annual cost spans from $360,000 in 2008 to $925,000 in 2013. The estimated cost includes
personnel, vehicles and equipment but does not include overhead such as office space and utilities.
The plan also does not include an in-depth review of contracted services which will be explored
more fully in future business plans.
The business plan looks at the trends in the changing landscape of Spokane Valley to anticipate
future needs. Financial resources are also forecast, taking into consideration economic indicators and
new legislation. The business plan is then able to focus on utilizing the available resources in the
most efficient manner to provide quality service to our customers while meeting the current and
future needs of the City.
The Initial Plan
In 2007, each department identified a six-year business plan including anticipated issues and goals
along with strategies for addressing them. In order to provide a perspective on the scope of the plan,
Table 1: Cost of Initial Plan, summarizes by department the costs (personnel, workstation, vehicle,
and equipment) of implementing the initial plan.
Table 1: Cost of Initial Plan
Department FTE 2008 2009 2010 2011 2012 2013
Executive/Legis Support .50 30,921 28,6711 30,534 32,519 33,332 34,166
Operations/Admin 2.50 165,500 212,683 220,306 245,038 252,938 241,207
Finance &Info Tech 4.00 70,481 124,470 209,848 219,228 315,506 326,061
Community Dev 1.00 0 85,340 65,327 69,574 74,096 75,948
Parks &Recreation 3.00 20,508 99,993 101,152 106,635 112,464 115,025
Public Works 2.00 73,257 69,499 74,016 78,827 80,798 82,818
General Government 0.00 2,000 0 0 0 0 50,000
Total 13.00 $362,667 $620,656 $701,183 $751,821 $869,134 $925,225
1 Drop in second year reflects one time start up costs
- 2 -
City of Spokane Valley 2008 Business Plan
Business Plan Process
This proposed six-year business plan for 2008-2013 was developed in 2007. However, the
foundation for the plan was initiated in 2004 with the adoption of the City's vision statement:
"A community of opportunity where individuals and families can grow and play and businesses can
flourish and prosper. "
Following the development of the vision statement, City Council, often with public participation,
worked to establish core beliefs, values, and annual budget goals, all of which provide the nexus for
the City's first six-year business plan. A comprehensive discussion of the Foundation of Spokane
Valley, City Council, and Core beliefs along with customer service and internal and external input
methodology is available in the Appendix.
As noted in Figure 1. Business Plan Process, the City Foundation established by City Council and
influenced by formal employee input, city plans, analysis and other forms of Internal Input, along
with citizen surveys, comment cards, focus groups and other External Input, has formed the basis of
the first six-year business plan. Each of the Strategic Service Delivery Areas is supported by a
Departmental Business Plan. The Departmental Business Plans were developed through
participatory meetings open to all City employees. A SWOT analysis identifying the strengths,
weaknesses, opportunities and threats of each department was conducted. Mission statements and
goals were established by employees. Department Directors and their staff, along with city
administration then developed the strategies outlined in the plan.
Figure 1. Business Plan Process
City Foundation
Core Beliefs. Vision Statement, Values, Customer Service Standards
1
Internal Input City Council External Input
Lunch w/City Manager -* Budget Goals 1- Citizen Survey
Employee Focus Groups Comment Cards
Commute Trip Reduction Survey Focus Groups
Resource Analysis Customer Correspondence
Comprehensive Plan Strategic Service-Delivery Areas
6-Year Transportation
Improvement Plan
6-Year Financial Plan
CenterPlace Marketing Plan Departmental Business Plans
Parks Master Plan Mission Statement
Audits Goals
Perfouuance Analysis Strategies
*Workload Indicators
*Performance Measurements
1
Citywide Business Plan
Encompasses All Items Above
* Future plan components
- 3 -
City of Spokane Valley 2008 Business Plan
Strategic Service Delivery Areas
The City of Spokane Valley is classified by five strategic service-delivery areas of one or more
Departments, as seen in Figure 2. Strategic Service-Delivery Areas and Respective Departments.
The five strategic service areas developed a mission statement that guides all the departments that
operate within the strategic area.
Additionally, within two of the Strategic Service Areas, divisions were further defined. Two of these
are notable in that they have developed mission statements and business plans specific to those
divisions. First, the Office of the City Attorney is a division within the Executive & Legislative
Support department, but provides City-wide legal services such as litigation, legislation, contracts,
and code enforcement. The second is the Finance & Information Technology division within the
Operations and Administrative Services Department.
Figure 2. Strategic Service-Delivery Areas and Respective Departments
Strategic Service Areas/Departments
Executive& Operations& Community Parks&Recreation Public Works
Legislative Support Administrative Development
Services
14 Office of the Finance&
City Attorney Information
Technology
- 4 -
City of Spokane Valley 2008 Business Plan
Departmental Business Plan
This initial Business Plan includes a Mission Statement for each strategic service-delivery area along
with the strategies, estimated budget and timelines necessary to implement the plan.
Each strategic area encompasses a general area of service delivery while the divisions within provide
a specific service to the customer. The divisions work closely together under the direction of the
manager of the strategic area, coordinating efforts to serve the mission of that area.
The following pages will start with each strategic area supplying a mission statement that states the
purpose of the strategic area as well as anticipated future accomplishments, while reflecting the
values of the employees providing the service. This is followed by a brief overview of the
Departments.
The next step in the departmental business plan process is a description of program areas.
Next, an organizational chart shows the staffing makeup of the department. This is followed by a 6-
year plan summary leading into the detailed list of department goals and strategies.
The goals are summarized in a 6-year timeline followed by a budget and staffing summary.
Future Business Plan Concepts
In the future (2009 Business Plan) the departmental plan will then identify, measure, and show
trends of workload measurements. Workload Indicators illustrate input into a department such as the
number of code enforcement complaints received and meaningful correlation of that data.
This step will be followed by the identification of Performance Measurements that determine the
effectiveness of strategies employed, such as response time per complaint and citizen satisfaction of
the complaint resolution. These Performance Measurements also gauge how successful the
department is in meeting its goals and whether we are inefficient or efficient in providing this
service. The measurement of these outcomes will provide accountability to the customers and gauge
for management to determine if services are running smoothly or if changes need to be made.
- 5 -
City of Spokane Valley 2008 Business Plan
Department: Executive & Legislative Support City Manager/City Clerk
Mission Statement
Our mission is to provide the City Council and employees with leadership, useful advice, and
implementation of best practices to achieve adopted goals and deliver quality services to the
community.
Overview
The Executive & Legislative Support Department is accountable to the City Council for the
operational results of the organization, effective support of elected officials in achieving their goals;
fulfillment of the statutory requirements of the City Manager, implementation of City Council
Policies, and provision of a communication linkage between citizens, the City Council, City
departments, and other government agencies.
Executive and Legislative Support includes the City Clerk and oversees the Police services contract
for the City. The Office of the City Attorney is included in the Department, but as it works directly
with all departments, it has its own Mission Statement and Goals following this section.
Description of Programs
City Manager — The City Manager recommends and implements policy and oversees the
operations of the City, develops and implements the budget. All employees report directly or
indirectly to the City Manager. The City Manager supervises and mentors Masters of Public
Administration (MPA)program interns.
City Clerk— The Clerk's office is the custodian of all the City records and oversees elections.
The Clerk administers the City Safety Committee and Risk Management functions.
Police Services — Police services are contracted through the Spokane County Sherriff s
Department. The City of Spokane Valley Police Chief reports to the City Manager.
2008 Organizational Chart
City Manager
Admin.Assistant—
Executive
City Manager
City Attorney City Clerk Admin.Assistant— Police Chief MPA
Executive (Contract Services) Interns
City Council ■
■Admin.Assistant Deputy City Clerk
1 .
Deputy City Attorney Rule 9 Legal Interns
i
- 6 -
City of Spokane Valley 2008 Business Plan
6-Year Goal Summary
• Facilitate the achievement of annually established Council Goals.
• Formulate a six-year Strategic Financial Plan by July 2008.
• Implement city-wide document management system.
Detailed Goal List
Goal 1
Facilitate the achievement of annually established Council Goals (all years)
Strategies (2008-2013)
• Annually develop objectives and strategies to accomplish Council goals.
• Report goal attainment progress to the community in the city manager's budget message.
Goal 2
Formulation of a Six-Year Strategic Financial Plan (SFP)by July 2008. The SFP would forecast
expected revenues and expenses; incorporate the fiscal elements of departmental business plans;
identify fiscal constraints; and, propose formulas for Council consideration in composing a budget-
balancing approach that itemizes necessary service reductions or increased revenues or a
combination thereof.
Strategies (2008 Only):
• Update the financial forecast on an ongoing basis.
• Facilitate the creation of departmental business plans.
• Calculate the fiscal impacts identified in business plans.
• Assess revenue and expenditure trends.
• Merge trend data with business plan cost data.
• Determine the financial delta.
• Develop best case and worst case scenarios.
• Formulate revenue and expenditure options.
• Determine affordable service levels.
• Select budget-balancing options to implement.
• Obtain Council authorization to proceed with selected option(s).
- 7 -
City of Spokane Valley 2008 Business Plan
Goal 3
Implement city-wide document management system.
Strategies:
2008
• Create an index of documents and forms on the City's website.
• Implement paperless agendas.
• Increase Deputy City Clerk from .5 FTE to 1.0 FTE.
• Create index of all public record documents.
• Implement full document imaging and archive all documents.
2009
• Create index of all public record documents.
• Implement full document imaging and archive all documents.
2011
• Install vault in new City Hall to house permanent historical records.
Summary
6-Year Timeline
GOAL 2008 2009 2010 2011 2012 2013
1
2
3
6-Year Budget and Staffing Impact Summary`
Executive & Legislative
Support FTE 2008 2009 2010 2011 2012 2013
Deputy City Clerk 0.50 doyd2 i �i/� r�
*Salary/Benefits and Personnel Startup Costs (work stations and vehicles)
1 Drop in second year rate the result of one-time start-up costs in year 1
The City has set aside $250,000 for implementation of a document imaging system. This plan does
not include additional systems funding.
- 8 -
City of Spokane Valley 2008 Business Plan
Department: Executive & Legislative Support Office of the City Attorney
Mission Statement
Implement Council policy by providing clear direction and meaningful assistance to employees
administering city government and citizens who use city government. Ensure that all City actions
are consistent, timely and helpful. Maintain a positive and creative workplace.
Overview
The Office of the City Attorney represents City's legal interests including oversight of claims and
litigation. The division manages the City's legal service agreements such as courts, prosecutors, and
probation. The City Attorney drafts ordinances and resolutions, negotiates contracts, leases, and
agreements and supports departments in enforcing associated laws. The Office of the City Attorney
also provides specialized employee training regarding existing law. The City Attorney supervises
and directs the work of Rule 9 Legal Interns.
Description of Programs -pending
Contract review and support—Review contracts prior to adoption and advise City
departments on issues related to administration of the contracts;
Code compliance support and litigation—Provide support to code compliance
department in analyzing cases; provide litigation support for cases that are not capable
of resolution by compliance officers;
Community Development support—Provide advice on broad spectrum of issues related
to development permitting in the City, and joint planning activities outside the City in
affected areas;
Legislative support—Draft legislative changes; provide advice to the City Council on
broad range of municipal issues.
2008 Organizational Chart
1
City Attorney
Administrative Assistant
1
r
Deputy City Attorney
i
Rule 9 Legal Interns
- 9 -
City of Spokane Valley 2008 Business Plan
6-Year Plan Summary
• Have a fully operational City Attorney's Office that is adequately staffed to handle the
workload and allows for timely client service.
• Assist other departments in analyzing and mapping existing processes to determine
compliance with the law and whether higher levels of customer service can be achieved.
Detailed Goal List
Goal 1
To have a fully operational City Attorney's Office that is adequately staffed to handle the workload
and allows for timely client service.
Strategies (2008-2013):
• Monitor workload changes
• Track response times
• Identify deficient areas
Goal 2
To assist other departments in analyzing and mapping existing processes to determine compliance
with the law and whether higher levels of customer service can be achieved.
Strategies:
2008
• Finalize an index for all public records from any department, with a corresponding electronic
directory system with a common format City-wide.
• Identify all types of permits, approvals, permissions or waivers granted by the City, and
specify the procedures to be followed for each item, including deadlines.
• Create a process whereby the basis for all conditions placed upon a development project is
identified, with a specific checklist to be followed prior to the imposition of each condition.
• Create and maintain a purchasing manual.
• Maintain and update all form contracts used by all departments.
2009
• Update and maintain all City franchises.
• Maintain and update all form contracts used by all departments.
2010-2013
• Maintain and update all form contracts used by all departments.
- 10 -
City of Spokane Valley 2008 Business Plan
Summary
6-Year Timeline
GOAL 2008 2009 2010 2011 2012 2013
1
2
6-Year Budget and Staffing Impact Summary
This plan does not include any additional funding and staff impact.
- 1 1 -
City of Spokane Valley 2008 Business Plan
Department: Operations & Administrative Services
Mission Statement
Operations and Administrative Services supports the organization and provides exceptional customer
service by assessing and addressing the needs of customers and employees, emphasizing public
accountability, fostering community involvement, and managing the delivery of services to the
citizenry.
Overview
The Operations & Administrative Services Department includes the human resources, central
reception, public information, contract administration, and finance functions of the City. This section
of the business plan reflects the Operations Oversight division of the Department.
Description of Programs
Human Resources—Provides services in compensation, benefits, training and
organizational development, staffing, employee relations, and communications.
Central Reception— Serves as the primary customer service representative for all
departments within the City, provides customer assistance and receives and assists the
public.
Public Information - Coordinates community and media relations to create public
awareness and understanding of City programs, policies, services, and initiatives
using a variety of communication channels.
Contract Administration — Negotiates service agreements; reviews charges; audits
usages; utilizes managed competition; and addresses customer concerns.
2008 Organizational Chart
r ,
Deputy City Manager
i
Administrative Assistant-
Executive
1 1 I 1 1
r 1 r 1 r 1 r 1 r 1
Sr.Administrative Analyst Public Information Officer Office Assistant I Office Assistant lI Human Resources Manager
Administrative Analyst Human Resources
Technician
- 12 -
City of Spokane Valley 2008 Business Plan
6-Year Plan Summary
• Respond to internal and external impacts on the City's human resources function in order
to recruit and retain a well-qualified workforce
• Enhance community involvement in City government
• Formalize public accountability in City operations through incorporating the Business Plan
into decision making, conducting a periodic community survey, and establishing a toolbox
for evaluating the City's contract services
Detailed Goal List
Goal 1
Respond to internal and external impacts on the City's human resources function in order to recruit
and retain a well-qualified workforce.
Strategies: (2008 —2013)
• Use more pro-active recruitment techniques
• Evaluate City's work environment to encourage retention of existing staff
• Expand new employee orientation and training
• Develop processes that improve employee access to information, and make the best use of
technology in order to be cost effective to administer
Goal 2
Enhance community involvement in City government. Two of the core values adopted by City
Council are to promote community identity and pride, and to focus on the future.
Strategies: (2008 —2013)
• Promote a unique, Spokane Valley identity especially for the celebration of City's five- and
ten-year anniversaries
• Develop reports on Spokane Valley demographic and economic trends
• Expand forums for informing and involving the public through the development of formal
customer service feedback system and enhancement of community communications
outreach program
Goal 3
Formalize public accountability in City operations through incorporating the Business Plan into
decision making, conducting a periodic community survey, and establishing a toolbox for evaluating
the City's contract services. An open, collaborative government is the third core value adopted by
City Council.
- 13 -
City of Spokane Valley 2008 Business Plan
Strategies:
• Incorporate the Business Plan in the City's decision-making process to enhance
accountability through implementation of performance measures
• Implement a periodic community survey to objectively monitor customer satisfaction
• Establish a toolbox for evaluating City's contract services
• Develop a formal contract audit program
• Finalize a managed competition process
Summary
6-Year Timeline
GOAL 2008 2009 2010 2011 2012 2013
1
2
3
6-Year Budget and Staffing Impact Summary*
Operations/Admin Services FTE 2008 2009 2010 2011 2012 2013
HR Technician 0.50 �,1��, �f�yg0 /.20�/; 40/405,
HR Assistant 1.00 0 0 60,000 59,640 63,517 67,645
Administrative Analyst 1.00 r AW/W9 ,805K<, , /85(44;
Community Inv/Public
Info i 0.00 J P 73,520 34,061 29,623 30,208 30,816
Contract Services 2 0.00 '". i 13,520 14,061 34,623 15,208 15,816
,
Other HR Services 3 0.00 ��� 25,000 5,000 7,000 27,000 7,000
Subtotal 2.50 165,500 212,683 220,306 245,038 252,938 241,207
*Salary/Benefits and Personnel Startup Costs (work stations and vehicles)
1 Publications, interactive web, community outreach, customer service feedback, PI intern
2 Community survey, intern
'City safety plan,paperless HR system, update website, enhance employee recognition, develop
marketing strategy, employee development/learning, comprehensive employee development model,
succession planning, healthy work/life // W
- 14 -
City of Spokane Valley 2008 Business Plan
Department: Operations & Administrative Services —Finance & Information
Technology
Mission Statement
The Finance and Information Technology Division is committed to excellence in customer service
by providing quality financial information to council, citizens and city departments. The
Information Technology Group (IT) seeks to understand technology and how it can best serve
internal and external IT users.
Overview
The Finance and Information Technology Division provides financial management and technology
services for all city departments. Programs include accounting and reporting, payroll, accounts
payable, purchasing, budgeting, financial planning, insurance, treasury and information technology.
This division exists within the Operations and Administrative Services Department.
Description of Programs
Finance—Provides assistance to departments on the annual budget, financial
reporting, payroll, accounts payable, and purchasing.
Information Technology — Provides assistance to departments regarding telephone
service, computers, printer/copiers, and the city's computer network.
2008 Organizational Chart
Finance Director
1 1 1 I
r Accounting Manager Accountant/Budget IT Specialist GIS/Database
Analyst (2.0 FTE) Administrator
i (3.0 FTE) i i \. i
I
Accounting
Technician
6-Year Plan Summary
• Assist in the implementation of the Sprague-Appleway Revitalization Plan, especially in the
area of City Hall, City Center, and other infrastructure financing.
• Assist in developing the financing of the Street Master Plan.
• Explore available telecommunications infrastructure accessible to the public.
• Maintain a consistent level of service in payroll, accounts payable, budget preparation and
information technology services during a period of high growth.
- 15 -
City of Spokane Valley 2008 Business Plan
Detailed Goal List
Goal 1
Assist in the implementation of the Sprague-Appleway Revitalization Plan, especially in the area of
City Hall, City Center, and other infrastructure financing.
Strategies (2008 —2009):
• Review list of needed improvements
• Determine cost of improvements
• Once agreement with developer is signed, determine who will provide improvements
• Determine timing of improvements
• Determine affect on city financial stability
• Determine financing options
• Prepare plan
Goal 2
Assist in developing the financing of the Street Master Plan.
Strategies:
2008
• Review consultant's plan
• Review list of needed improvements
• Should capital plan be different than operating plan?
• Determine costs
• Determine timing
• Determine affect on city financial stability
• Determine options
• Prepare plan
Goal 3
Explore available telecommunications infrastructure accessible to the public.
- 16 -
City of Spokane Valley 2008 Business Plan
Strategies:
2008 - 2009
• Develop questionnaire for use when meeting with community representatives including
colleges, hospitals, school districts, City of Spokane, Spokane County to share information.
• Coordinate meetings with Greater Spokane Incorporated to share ideas.
• Discuss common interests with businesses in the area and data providers.
• Seek information from developers, real estate consultants.
• Based on information gathered, determine potential benefit of enhanced infrastructure and/or
needs of community.
• Prepare cost/benefit analysis.
Goals 4
Maintain a consistent level of service in payroll, accounts payable, budget preparation and
information technology services during a period of high growth.
Strategies: (2008 —2013)
• Add admin. assistant& accountant in early 2008 as number of projects increase
• Add information technology positions as needed (2009 & 2012)
• Upgrade telephone, network and fiber infrastructure
Summary
6-Year Timeline
GOAL 2008 2009 2010 2011 2012 2013
1
2
3 -
4
6-Year Budget and Staffing Impact Summary*
Finance & Information
Technology FTE 2008 2009 2010 2011 2012 2013
Administrative Assistant 1.00 0 53,668 52,897 1 56,335 59,997 61,497
Accountant/Bgt Analyst 1.00 (d4W ,r8 , 9i! �i IY//51 WA
IT Specialist 1.00 0 0 81,547 82,588 87,956 93,673
IT Specialist 1.00 0 0 0 0 85,240 86,520
Subtotal 4.00 70,481 124,470 209,848 219,228 315,506 326,061
*Salary/Benefits and Personnel Startup Costs (work stations and vehicles)
Drop second f f X � J�9 ,
- 17 -
City of Spokane Valley 2008 Business Plan
Department: Community Development
Mission Statement
The mission of the Community Development Department is to provide planning, permitting and
code compliance services in a responsive and efficient manner to ensure the safety, health and
welfare of our citizens, and to encourage orderly development and economic sustainability.
Overview
Community Development maintains the City's Comprehensive Plan; administers the Uniform
Development Code and adopted Building Codes; and assists citizens and business owners with code-
related issued.
Description of Programs
Planning—Make recommendations for the updates and maintenance of the City's
Comprehensive Plan, participates in regional planning policy issues, provides the
state with mandated information regarding growth of residential capacity and
employment trends, administers the Uniform Development Code including the State
Environmental Policy Act(SEPA), Shoreline Management Act and the Growth
Management Act(GMA).
Permitting—Review and issuance of construction and land use permits according to
the City's Uniform Development Code which includes the disciplines of Building,
Planning, and Development Engineering and is completed through inspections of
these three areas of development.
Code Compliance—Responds to City complaints for compliance to City codes.
Geographic Information Systems—Maintains the City's geographic database in order
to provide infonnation to make decisions and monitor land use trends.
- 18 -
City of Spokane Valley 2008 Business Plan
2008 Organizational Chart
i
Community
Development
Director
J
Admin. "\ Office
Assistant — Assistant I
J ` J
Planning Building "1 Senior
Manager Official Engineer
Development
.1 \. J
Senior Assistant Sr.Plans Code Sr.Pe rmit ROW OW 1 Office
Planner Planner Examiner Compliance Specialist Inspector Assistant I
(2.0 FTE) (3.0 FTE) Officer (2.0 FTE)
J l J \. J \. (2.0 FTE) J J \. J
Associate r Planning c Plans C Building -N C Permit Office Engineer Construction
Planner Tech Examiner — Inspector II Specialist Assistant II (1.5 FTE) — Inspector
(2.0 FTE) (.75 FTE) (4.0 FTE) (2.0 FTE)
J l J \ J ` J ` J ` J l J
Assistant , Engineering,
Engineer Tech
(2.0 FTE) (2.0 FTE)
J ` J
6-Year Plan Summary
• Complete the Sprague-Appleway Revitalization Plan
• Implement the Sprague-Appleway Revitalization Plan
• Complete the Shoreline Master Program update
• Evaluate the Code Compliance Program
• Update Urban Growth Area(UGA) boundaries through regional process
• Complete Street Standards Manual
• Continue to improve customer service in permit processing
- 19 -
City of Spokane Valley 2008 Business Plan
Detailed Goal List
Goal 1
Complete the Sprague-Appleway Revitalization Plan.
Strategies: (through mid-2008)
• Prepare environmental analysis for Plan
• Public Outreach(Community meetings)
• Make revisions based on public input
• Planning Commission Public Hearings
• City Council adoption
Goal 2
Implement the Sprague-Appleway Revitalization Plan as determined by the City Council.
Strategies: (2008 —2010)
• Work with the City Council, consultants, and other department staff to determine the scope
of City Center plan.
• Put together timeline and costs for improvements and work with council to determine city's
portion of costs.
• Prepare Planned Action SEPA Ordinance.
• Refine site plan with library, property owners and consultants.
• Close property transaction for City Hall.
• Work with consultants and property owner to secure a developer.
• Review plans for city hall permit and issue.
Goal 3
Complete the Shoreline Master Program update subject to obtaining grant funding. Washington State
mandates adoption of an updated Shoreline Master Program by 2013.
Strategies: (March—December 2008)
• Determine work program, cost, and timeline for completion deadline.
• Apply for grant funding if it becomes available.
Goal 4
Evaluate the Code Compliance Program to determine if community needs are being met at
acceptable levels.
- 20 -
City of Spokane Valley 2008 Business Plan
Strategies: (all 2008)
• Determine existing case levels and response times.
• Review current practices to determine if improvements can be made to resolve cases sooner.
• Conduct an assessment of pro-active issues that are not being addressed.
• Make recommendation to City Manager and City Council about future level of service.
Goal 5
Update UGA boundaries through regional process.
Strategies: (all 2008)
• Develop work program
• Amend Comprehensive Plan to identify UGA's
• Work through regional process to have UGA's/Joint Planning Areas assigned
Goal 6
Complete Street Standards Manual
Strategies: (through 2008)
• Develop review draft of document
• Conduct follow up public meetings
• Prepare final draft document
• Begin adoption process with planning commission
• City council adoption
Goal 7
Continue to improve customer service in permitting process.
Strategies: (all year)
• Implement recommendations of the development stakeholders group.
• Update and improve customer handouts.
• Complete staff training of the UDC.
• Complete staff training of the Sprague Appleway Plan and form based development
regulations.
• Prepare staff policy & procedure manual.
- 21 -
City of Spokane Valley 2008 Business Plan
Summary
6-Year Timeline
GOAL 2008 2009 2010 2011 2012 2013
1
2
3
4
6
6
6-Year Budget and Staffing Impact Summary*
Community Development FTE 2008 2009 2010 2011 2012 2013
Code Compliance Officer 1.00 0 85,340 65,3271 69,574 74,096 75,948
*Salary/Benefits and Personnel Startup Costs (work stations and vehicles)
1 Drop in second year is the result of one-time start-up costs in year 1
Department: Parks & Recreation
Mission Statement
To acquire, develop, operate and maintain a diverse park and recreation system that enhances our
community.
Overview
With offices located in the CenterPlace Regional Events Center, the Parks and Recreation
Department consists of five divisions: Parks Administration and Maintenance; Recreation; Aquatics;
Senior Center; and CenterPlace. The Department is comprised of nine FTEs. Parks Maintenance and
Aquatics services are contracted with external businesses/agencies. The Parks & Recreation
Department also maintains a database of local recreation programs and services to help match
citizens with existing services.
Description of Programs
Parks Administration & Maintenance - The Administration Division provides direction and
leadership for the Parks and Recreation Department in implementing the goals and objectives
of the City Council and facilitates the general upkeep of parks and public areas of the City.
The City uses contractual services for the operations and maintenance of City parks.
Recreation — The Recreation Division coordinates and facilitates the delivery of recreation
programs and services throughout the City and the City's park system.
Aquatics — The City of Spokane Valley owns three swimming pools which provide
opportunities for Open Swim, Swim Lessons, Swim Team, and facility rentals. In addition,
the City leases a portion of Valley Mission Park for a water park.
- 22 -
City of Spokane Valley 2008 Business Plan
The City currently is contracting with the YMCA for all aquatic activities within the City.
The YMCA provides the lifeguards and maintains the pools during the season.
Senior Center — The City of Spokane Valley assumed operational control of the Valley
Senior Center in 2003. Through the Spokane Valley Senior Citizens Association, the Senior
Center promotes fellowship, health, recreation, social, and educational opportunities for
persons fifty years and older.
In cooperation with the Community Colleges of Spokane the Senior Center offers classes
ranging from aerobics to Spanish. The Senior Center is also a recreational hub for area
seniors to play billiards, ping pong, and pickleball, and join in weekly dances, theme dances,
and line dancing.
CenterPlace - Construction of Mirabeau Point CenterPlace was completed mid-year 2005.
The project represents the culmination of eight years of planning and fundraising by
Mirabeau Point Inc. and the joint involvement of the City and Spokane County. The
approximately 54,000 square foot facility houses the City of Spokane Valley Senior Center, a
great room (banquet facility), numerous meeting rooms, multi-purpose rooms, and a high
tech lecture hall. The facility combines with Mirabeau Meadows Park and Mirabeau Springs
to form a regional focal point for Northeast Washington, Northern Idaho and Western
Montana.
2008 Organizational Chart
Parks&Recreation
Director
Parks Operations& 1 Aquatics Activates&
Maintenance Maintenance
(Contract Services) (Contract Services)
Administrative Assistant
1 1 1 1
CenterPlace CenterPlace CenterPlace
Senior Center Specialist Recreation Coordinator Customer Maintenance Worker— Custodian
Relations/Facilities Facilities 2.0 FTE or Contract
Coordinator 2.0 FTE Services TBD
J \ J \ J \ J \ J
CenterPlace
Administrative Assistant
2.O FTE
- 23 -
City of Spokane Valley 2008 Business Plan
6-Year Plan Summary
• Implement recommendations of the Parks and Recreation Master Plan
• Implement the CenterPlace Regional Marketing and Communications Plan
• Make facility improvements to CenterPlace
• Expand senior services to serve changing needs and expectations of the senior population
• Work with Centennial Trail partners to develop 20 year plan
Detailed Goal List
Goal 1
Implement recommendations of the Parks and Recreation Master Plan. Based on contracted planning
services and relying on Public Works Department for construction projects.
Strategies: (2008 —2013)
• Implement Parks and Recreation Master Plan
• Explore options for major sources of funding
• Pursue park acquisitions and development
• Develop formal agreements for"school parks"
• Build department identity
• Partner with local jurisdictions to look at feasibility of indoor aquatics center
Goal 2
Implement the CenterPlace Regional Marketing and Communications Plan.
Strategies: (2008)
• Increase seasonal staffing to accommodate a higher level of service for events
• Professional training for our host staff— alcohol, CPR, team work
• Develop "CenterPlace's Partner Services" with local event planners
• Explore contracting with food and beverage service providers
• Contract marketing services to help implement marketing plan
Goal 3
Make facility improvements to CenterPlace.
Strategies: (2008 —2009)
• Schedule preventative maintenance and facility updates to maintain CenterPlace in new
condition
• Explore opportunities to provide additional services
• Explore contractual janitorial services vs. conversion of janitorial staff to FTEs
- 24 -
City of Spokane Valley 2008 Business Plan
Goal 4
Expand senior services to serve changing needs and expectations of the senior population.
Strategies: (2008 —2009)
• Challenge to serve current age demographics and to attract new participants
• Add new, active programming
• Hire half-time intern to assist with scheduling classes and seminars
• Increase involvement with neighboring retirement communities
• Educate the community at-large about the purpose and potential of the Senior Center
• Focus on health and wellness
Goal 5
Work with Centennial Trail partners to develop 20 year plan.
Strategies: (2009)
• Seek grant opportunities
• Develop a long range maintenance plan
• Implement Plan
Summary
6-Year Timeline
GOAL 2008 2009 2010 2011 2012 2013
1
2
3
4 ■
5
6- Year Budget and Staffing Impact Summary`
Parks & Recreation FTE 2008 2009 2010 2011 2012 2013
Operations Coordinator 1.00 0 79,222 80,112 85,319 90,865 93,136
Custodian (convert from temp) 2.00 '' • y 1 i i i : 1, ` . . t
CenterPlace Services 0.00
Sr. Center Services 0.00 ►+ ! i '*Fir
Offset 0.00 � ��d�, �!�.��I�� A_ 11t �l1 '� •� �� �61
Subtotal 3.00 .•fr.! ., 99,993 101,152 106,635 112,464 115,025
*Salary/Benefits and Personnel Startup Costs (work stations and vehicles)
** 0 fset due to increased revenues and conversion to in-house om contract services'
- 25 -
City of Spokane Valley 2008 Business Plan
Department: Public Works
Mission Statement
The mission of the Public Works Department for the City of Spokane Valley is to provide overall
planning, construction operations and maintenance of the city's public works infrastructure and
facilities.
• The mission of the Administration is to provide direction, support, and coordination to Public
Works staff facilitating their delivery of service throughout the community; and coordination
with providers of solid waste, wastewater and other regional public works issues.
• The mission of the Capital Projects group is to plan, design and construct new facilities
which are under the ownership of the City of Spokane Valley. These projects include roads,
bridges, park facilities, civic and community buildings. This requires careful prioritized long-
range planning, acquisition and management of state and federal grant funding, coordination
with stakeholder groups, and proficient project management.
• The mission of the Street Maintenance Division is to
1. Provide responsive and effective management and maintenance of city streets, snow
and ice control, and debris removal, allowing for safe transportation throughout the
community.
2. Provide Traffic Engineering for safe and efficient multi faceted transportation
systems throughout the city.
• The mission of the Stormwater Division is to protect the environment by minimizing the
degradation of water quality and reducing the potential for flooding and erosion by
maintaining and installing stormwater management systems.
Overview
Public Works oversees the City's transportation system, which includes construction and
maintenance of streets and related stormwater systems, operations and maintenance of traffic signs
and signals, regional and neighborhood transportation planning. The Department also provides
coordination with other city departments on the planning, design and construction of city parks and
civil facilities, along with participation in regional public works issues such as solid waste,
wastewater, and high-capacity transportation.
Description of Programs
Street Operating Program - The Street Operating program is established to provide
efficient and safe movement of both motorized and non-motorized vehicles as
well as pedestrians within the limits of the City and coordinate convenient
interconnect to the regional transportation system.
- 26 -
City of Spokane Valley 2008 Business Plan
The transportation networks, under this program, are designed, constructed, and
maintained to improve the quality of life while providing the efficient movement of
commerce.
Stormwater Management-Provides stormwater construction and management
through both the Street Department and Spokane County.
Street Maintenance—Responsible for maintenance of public streets.
2008 Organizational Chart
Public Works
Director
l
Administrative
Assistant
\ l
I 1 1 I
Street Maintenance, Engineer- , r Senior Engineer—"1 Senior Engineer—-\
Superintendent Stormwater CIP Manager Traffic
l \ l \ l \ l
14 Maintenance/Const, Assistant Engineer, Engineering Tech I, ' Administrative
Inspector Assistant
2.0 FTE
l ■ l \. l \
r Senior Engineer—1 r Senior.Engineer—1
Project Manager Project Manager
\ l l
4 '
E
Assistant Engineer
l
4 Engineering Tech.I, Engineering Tech.I
l \
- 27 -
City of Spokane Valley 2008 Business Plan
6-Year Plan Summary
• Implement the Street Master Plan (once adopted by Council)
• Continue development of a long range plan for street maintenance
• Continue optimization of the city's traffic signal plan
• Continue implementation of the stormwater program
• Implement public infrastructure aspects of Sprague-Appleway Revitalization Plan, including
City Center
• Implement Capital Improvement Projects as approved by Council
• Manage and coordinate the planning, design and construction of the City Hall project
• Continue involvement with the County and DOE regarding the TMDL and Wastewater
Treatment Plan
Detailed Goal List
Goal 1
Implement the Street Master Plan (once adopted by Council)Phase I
Strategies:
• Continue engineering contract with JUB for 2008 plan update
• Identify funding for recommended Pavement Management Program and Transportation
Improvement Plan (TIP)
Goal 2
Continue development of a long range plan for street maintenance
Strategies:
• Purchase site and facility for equipment and materials
• Consider options for winter snow maintenance
Goal 3
Continue optimization of the city's traffic signal system
Strategies:
• Update and revise signal timing plans for the city's major intersections
• Coordinate the design of the funded ITS projects
• Continue providing traffic related services on new development proposals
- 28 -
City of Spokane Valley 2008 Business Plan
Goal 4
Continue implementation of the stormwater program
Strategies:
• Develop a six-year capital program for needed stormwater facilities.
• Develop a six-year plan for compliance with the Underground Injection Control (UIC)
program
• Develop and coordinate with other departments a plan for compliance with the National
Pollution Discharge Elimination System (NPDES) Phase II permit
Goal 5
Implement public infrastructure aspects of Sprague-Appleway Revitalization Plan, including City
Center
Strategies:
• Determine phasing, cost estimates and funding alternatives for the subarea plan
recommendations
• Design and construct the first phase(s) of the public infrastructure to support the development
of the city center
• Design and construct the first phase(s) of the Sprague/Appleway improvements to support
the revitalization of the corridor
Goal 6
Implement Capital Improvement Projects as approved by Council
Strategies:
• Continue to monitor, update, and implement the Transportation Improvement Plan (TIP)
• Pursue additional funding opportunities for capital projects
• Continue coordination with other departments on non-transportation capital projects
• Continue to request additional staffing for ROW, design, construction and accounting to
facilitate project implementation
Goal 7
Manage and coordinate the planning, design and construction of the City Hall project
Strategies:
• Continue Programming Phase in 2008
• Beginning Planning and Design Phase in 2008 subject to acquisition of project site
- 29 -
City of Spokane Valley 2008 Business Plan
Goal 8
Continue involvement with the County and DOE regarding the TMDL and Wastewater Treatment
Plan
Strategies:
• Participate in the County DBO Selection Committee
• Participate in DOE Spokane River Dissolved Oxygen TMDL Advisory Group
Summary
6-Year Timeline
Goal 2008 2009 2010 2011 2012 2013
1
2
3
4
5
6
7
8
6-Year Budget and Staffing Impact Summary*
Public Works FTE 2008 2009 2010 2011 2012 2013
Capital Project Engineer 1.00 7: 1
Admin Assistant 1.00 �A� � e
i ' !
Offset 2 0.00 ��.I e 11. AA
2.00 ' rjrirr)
*Salary Benefits and Personnel Startup Costs (work stations and vehicles)
1 Drop in second year is the result of one-time start-up costs in year 1
Anticipated federal funding to offset percentage of project specific salaries
- 30 -
City of Spokane Valley 2008 Business Plan
Citywide Business Plan
In 2008, all departmental business plans for 2008 — 2013 will have been completed and compiled in
the citywide business plan. This business plan pulls all the functions of the City together into one
common purpose - to achieve service-delivery goals. The Citywide Business Plan allows decision
makers to view the interrelationship and impact of all departments and programs.
Planning is the strength of government and is vital to ensure future community needs can be met.
Planning is continually taking place in the City in areas such as transportation improvement, finance,
parks and recreation, and the ongoing comprehensive plan. These plans flow into strategic goals of
departmental plans.
Once the plans are in place and steps are taken to carry out these plans, measurements can be taken
to assess the City's performance in the execution of these strategic plans. Measurements can be
assessed through electronic data gathering or through report cards provided through citizen surveys.
Measurements will be integrated into the first business plan revision to be conducted in 2008 for the
timeframe of 2009- 2014.
Therefore, the business plan is not a once-a-year process but rather it is continually being monitored
and refined. Departments meet on a regular basis to assess measurements and maintain focus on
their goals. Employees let the City Manager know how things are going at the customer interaction
level while citizens let the Council and Mayor know how they perceive the strategies are working.
Figure 3: Business Plan Cycle illustrates the ongoing process.
Figure 3. Business Plan Cycle
Plan Measure Monitor
Comprehensive Plan
Business Plan
Budget Process Performance Measures Quarterly Reports
6-Year Transportation Plan Customer Satisfaction Lunch w/City Manager
6-Year Financial Plan Survey Conversations with the
Parks Master Plan Community
CenterPlace Regional Customer Comments
Marketing Plan
Focus Groups
- 31 -
City of Spokane Valley 2008 Business Plan
Pending Ideas
There are many ideas that warrant further consideration, but have not reached a point of maturity
such that an informed decision can be made to include them in this first iteration of the Business
Plan. They are described in Table 2: Pending Ideas List below, as notice of future policy
discussions. The ideas are listed in the order of lead department—they are not prioritized.
The programs/services are either multi-year or ongoing in nature. The table lists the proposed first
year of implementation and an estimation of the first year's cost. The cost of some of the programs
may partially or completely offset, either by specific revenue sources, or by reductions in other
expenses. The table indicates whether there is an offset, but does not identify the amount and does
not include capital project or land acquisition costs.
- 32 -
City of Spokane Valley 2008 Business Plan
Table 2: Pending Ideas List
Item Lead First Year: Cost Offset? Comment
Dept Date Cost Yes No
Public Info Assistance O&A 2009 $59,000 ♦ Additional PI staff will be needed if the City chooses
to be significantly more proactive regarding public
information and involvement.
Program Mgr— CD 2008 82,000 ♦ Depending on how active a role the City chooses to
Sprague-Appleway take with SARP, a dedicated program manager will
Revitalization Plan be needed to coordinate the wide variety of
(SARP) * associated projects.
Community Dev. Block CD 2012 142,15 H) ♦ The City currently participates with Spokane County
Grant(CDBG) and others. Every three years,the City has the
Entitlement City I opportunity to decide if it wishes to have a stand-
Designation alone CDBG program. June 2008 is the next chance
to do so.
In
Enhanced Geographic CD 2009 134,000 ♦ The City,other jurisdictions, and the public are
Info System(GIS) limited in the use of GIS. Additional staffing would
allow for a richer level of data to be input and
maintained. It could aid in the decision making for
anything property based,including public safety,
• utilities,land use, and parks.
Forestry Program P&R 2009 1 72,000 ♦ A forestry program would be an investment in the
natural beauty of the community, and could include
Tree City USA status.
Enhanced Recreation P&R 2010 105,000 ♦ The Parks&Rec Master Plan identified potential
Services recreation opportunities for all ages.
Park Ranger Program P&R 2010 60,000 ♦ This position would enhance the safety and
enjoyment of park visitors by patrolling for
1 vandalism,illegal consumption of drugs and alcohol,
abandoned vehicles,vagrancy,etc.
Street Master Plan PW 2009 203,000 ♦ Staff will be required to maintain the inventory
Implementation database; and manage the associated capital projects,
including funding and design.
Right-of-Way/Property PW 2009 a 82,000 ♦ The City's real property assets are growing and need
Management more consolidated management. A ROW program
would oversee existing assets,coordinate property
acquisition(e.g.,parks or capital projects), and
proactively acquire property for known future
projects so purchases are as economical as possible.
Capital Project Design PW 2009 294,000 ♦ The City contracts for design,project management,
and Inspection Teams • and inspection of capital projects. An in-house team
I assigned to a percentage of the capital projects would
be more cost effective,if set at a conservatively
sustainable level.
*This position is included in the 2008 Budget
- 33 -
City of Spokane Valley 2008 Business Plan
Appendix
Foundation of the City of Spokane Valley
The City of Spokane Valley sprung forth from a mixture of neighborhoods on March 31, 2003. The
new city government was charged with providing services to 82,000 people.
- The City leaders knew that a clear direction with a
IL .'la 1011, consistent message was needed to be successful in
. ,� J this endeavor. This new City had a different
`l i mentality than the other government operations in
a , )`.0 '" the area and City leaders knew how important it
C was to solidify that different way of thinking from\\, the very beginning.
, , �. This City was to be responsive, focused on
In customer service, open to the public, progressive,
efficient, lean, fair, and committed to providing a
high quality of life.
Core Beliefs
Section 1. We believe that Spokane Valley should be a visionary city encouraging its citizens
and their government to look to the future beyond the present generation and to bring
such ideas to public discussion and to enhance a sense of community identity.
Section 2. We believe that elected body decision-making is the only lawful and effective way to
conduct the public's legislative business and that careful observance of a clear set of
Governance Coordination rules of procedure can best enhance public participation
and decision making.
Section 3. We believe in the City Council as policy leaders of the City. One or more City
Councilmembers are encouraged to take the lead, where practical, in sponsoring
Ordinances or Resolutions excepting quasi-judicial or other public hearings and the
statutory duties of the City Manager as set forth in RCW 35A.13.020.
Section 4. We believe in hearing the public view. We affirm that members of the public should
be encouraged to speak and be heard through reasonable rules of procedure when the
public business is being considered, thus giving elected officials the broadest
perspectives from which to make decisions.
- 34 -
City of Spokane Valley 2008 Business Plan
Section 5. We believe that the City of Spokane Valley's governance should be known as "user
friendly," and that governance practices and general operations should consider how
citizens will be served in the most responsive, effective and courteous manner.
Section 6. We believe that the economic and commercial job base of the community should be
preserved and encouraged to grow as an alternative to increasing property taxes. We
believe it imperative to have an expanded and diverse economic base.
Section 7. We believe that Councilmembers set the tone for civic discussion and should set an
example by:
(a) Setting high standards of decorum and civility.
(b) Encourage open and productive conversation amongst themselves and with the community
about legislative matters.
(c) Demonstrating respect for divergent points of view expressed by citizens, fellow
Councilmembers and the staff.
(d) Honoring each other and the public by debating issues with City Hall and the Community
without casting aspersions on members of Council, the staff, or the public.
(e) Accepting the principle of majority rule and working to advance the success of"corporate"
decisions.
Section 8. We solicit the City Manager's support in conducting the affairs of the city with due
regard for:
(a) Promoting mutual respect between the Citizens, City staff and the City Council by creating
the organizational teamwork necessary for effective, responsive and open government.
(b) Providing the City Council and public reasonable advance notice when issues are to be
brought forward for discussion.
(c) Establishing and maintaining a formal city-wide customer service program with emphasis on
timely response, a user-friendly atmosphere, and an attitude of facilitation and
accommodation within the bounds of responsibility, integrity, and financial capability of the
city, including organizational and job description documents while pursuing "best practices"
in customer service.
(d) Seeking creative ways to contain or impede the rising cost of governmental services,
including examination of private sector alternatives in lieu of governmentally provided
services.
(e) Providing a data base of future projects and dreams for the new City of Spokane Valley so
that good ideas from its citizens and leaders are not lost and the status of projects can be
readily determined.
- 35 -
City of Spokane Valley 2008 Business Plan
Vision Statement
The first step was to establish a vision statement. That sets the City in motion on a course of
success.
Our Council believes that all people in Spokane Valley should have an opportunity to succeed, both
in work and in personal lives. A well-balanced community ensures that a strong economy will exist
to allow residents to enjoy life. The following vision statement was adopted to signify this belief.
"A community of opportunity where individuals and families can grow and play and businesses can
flourish and prosper. "
City of Spokane Valley Values
Next, the City founders and leaders felt it was important to provide direction to the new City
government organization and ensure that this community is unique. Developing the following
values for the City accomplished these goals.
Community Identity and Pride. Spokane Valley promotes an environment that supports the home
and family, and job and education opportunities.
Highlight areas:
• A friendly, wholesome, safe place to live and raise a family
• A City Center and economically healthy, diverse downtown area
• Preservation of neighborhoods
Focus on the Future. Spokane Valley is a visionary city encouraging its citizens and their
government to look to the future beyond the present generation, and to bring such ideas to public
discussion, enhancing a sense of community identity.
Highlight areas:
• A balanced approach to growth and development
• Stewardship of land and resources, such as parks, recreation and natural areas
• Preservation and growth of the economic and commercial job base of the community
Open, Collaborative Government. Spokane Valley values a "user-friendly" government, in which
governance practices and general operations consider how citizens will be served in the most
responsive, effective and courteous manner.
Highlight areas:
• Citizen participation in the decision-making process
• Strategic use of public/private and other partnerships
• A Can-Do attitude on the part of City employees, and fair and consistent interpretation and
implementation of regulations
- 36 -
City of Spokane Valley 2008 Business Plan
With these values, the City's foundation begins to take shape. The City now knows how it will
operate. This will be a government that encourages participation, promotes a collaborative approach
to problem-solving, inspires creativity, cultivating respect, and providing the highest level of
services without over-burdening its citizens or businesses.
Customer Service
The City of Spokane Valley established a level of commitment to customer service that will help the
City achieve all future goals.
CITY OF SPOKANE VALLEY CUSTOMER SERVICE PROGRAM
Our goal is to deliver service that is complete, consistent, and equitable to all our customers, and is
based on the principles of integrity, respect, and responsiveness. Regardless of the reason for, or the
method or frequency of contact, our customers will be treated with courtesy, respect, and
professionalism.
L Identify Our Customers
II. Define Customer Service
III. Communicate Our Goals and Standards
IV. Assessment and Improvement
CUSTOMER SERVICE DEFINITION
Customer Service Key Statement: The City of Spokane Valley strives to provide service
in a respectful, knowledgeable, and welcoming manner.
Respectful Knowledgeable Welcoming
➢ Demonstrating courtesy and ➢ Fostering a team-oriented ➢ Acknowledging customers
professionalism approach when they enter
➢ Listening effectively ➢ Providing alternatives ➢ Steering customers in the right
➢ Responding in a timely manner ➢ Anticipating questions direction
➢ Exemplifying a no-surprises ➢ Having/knowing your resources ➢ Promoting an enjoyable work
atmosphere ➢ Being organized environment
➢ Maintaining a clean and
uncluttered work environment
➢ Treating people as individuals
The foundation is now set. The City staff, management, and Council now have a clear
understanding of what is expected of them and they have a solid support structure to give them
confidence in the performance of their duties.
- 37 -
City of Spokane Valley 2008 Business Plan
Information Input
Information will come from inside the organization, from staff and management, as well as from
outside the organization from citizens, business-owners and others who frequent our community
(workers, tourists, etc.).
Internal Input
Council utilizes information from employees in a number of ways.
Employee Feedback
Employees are often the information conduit from the customers to the Council, relaying demands or
changing trends and they can often bring forward innovative way of providing efficient service-
delivery. Information from employees can be received in a variety of ways, from lunch with the
City Manager to employee surveys. Following is a list of employee feedback tools, some that are
currently utilized and some that may be used in the future.
• Lunch with City Manager
• Employee Survey (Future)
• Internal Customer Survey (Future, for departments that serve employees)
• CTR Survey (Commute Trip Reduction)
Staff Analysis
The City of Spokane Valley government is comprised of knowledgeable professionals. Staff is
charged with providing the specialized knowledge that allows the Council to make informed
decisions. From demand analysis, which determines when the workload is heaviest and how to best
accommodate it, to staff reports that consider alternative methods of service delivery or other cost-
saving measures, employees are invaluable in providing complex information. In the future, an audit
program can be utilized to ensure efficiency of service delivery for both in-house services and
contracted services. In addition, as a future piece of the business plan, performance measure results
will be analyzed, looking at multi-year and performance and comparing to targets as well as making
comparisons to other entities.
• Demand Analysis
• Staff Reports
• Audits (Future)
• Performance Analysis (Future)
- 38 -
City of Spokane Valley 2008 Business Plan
Strategic Planning
There are several long-range plans that are continually updated that look at current trends to make
future forecasts. Much public input goes into these documents but the forecasting and planning is
done by skilled staff-members who must create innovative ways of achieving our future vision while
meeting current needs, complying with the law, and operating within financial constraints.
• Comprehensive Plan
• 6-Year Transportation Improvement Plan
• 6-Year Financial Plan
• Business Plan
External Input
The City Council represents the citizens of Spokane Valley and must form policy that most fairly
represents all segments of our community. In addition, it is necessary to provide service to those
conducting business in our community and those visiting our City. In order to maintain the balance
that exists in serving the different needs that exist in Spokane Valley, it is necessary to receive
feedback from customers and constituents.
The City has already utilized citizen surveys as part of the development of the comprehensive plan
and for the needs assessment portion to the cable franchising process. In the future, citizen surveys
can be utilized in an ongoing basis as part of strategic planning and performance measurement that
are integral components of the business plan. Customer surveys can also play an important role by
polling individuals and businesses that have had a recent interaction with the City.
Comment Cards and Correspondence through phone calls and e-mails provide an easy way for
customers to relay their experience to Council and management. These unfiltered accounts of
interaction with City staff allow those in charge of keeping the City on course to react immediately if
necessary or to further cultivate and reward if a process is working well.
The public can also choose to take a more active role in participation through public forums such as
public hearings and open house functions as well as through serving on advisory committees. In the
future, focus groups may be utilized to allow for a more concentrated effort on a particular subject so
that Council and staff can get a better feel for how a particular subject is received in the community
and to allow customers to play an active role in guiding the way a service is delivered.
• Customer Survey (Future)
• Citizen Survey
• Comment Cards
• Conversations with the Community
• Public Forums
• Advisory Committees
• Focus Groups (Future)
• Customer Correspondence
- 39 -
Admin.
Assistant
City of Spokane Valley 2008 Business Plan
Council Goals
Once the information has been gathered it can be input into the policy-making process machine. The
City Council first takes a look at where we need to go based on the feedback from the community.
Then they must determine the best way to get there based on input from employees and customers.
The most challenging phase for the Council is to then allocate available resources in a way that
ensures that all components are well-maintained and stay in good-working order so that we reach our
goals as quickly and efficiently as possible while still adhering to the high-standards set by the over-
arching principles of the City.
New goals will be set by Council annually while the progress of previous year goals will be
measured. Though the goals are set by Council they represent the goals of the citizens of the
community.
Major Goal Statements for 2008
The 2008 budget reflects the distribution of resources consistent with the Council's determination of
core services priorities. The following goals represent just the very broad areas of concentration
important to the well being of the community.
Continue monitoring wastewater issues, including governance of wastewater facilities, and pursuit
of the most efficient and economical methods to ensure the continuation of wastewater discharges
licenses.
Refine initial departmental six-year business plans in order to identify and incorporate fiscal
impacts into a strategic financial plan.
Formulate a Six-Year Strategic Financial Plan by July 2008 that forecasts expected revenues and
expenses; incorporates the cost elements of departmental business plans; identifies fiscal constraints;
and proposes formulas for Council consideration that institute sustainable budget-balancing
approaches and itemizes necessary service reductions or revenue increases or combinations thereof
Initiate implementation of the sub-area plan for the Sprague/Appleway Revitalization Plan.
Adopt area-wide rezoning proposals consistent with the comprehensive plan that reflect
appropriate adjustments in zoning designations.
Perform an analysis of land owner initiated requests for annexation.
Develop a Shoreline Master Program as required by the State of Washington to provide additional
regulatory protection for waters of statewide significance, i.e. Spokane River, Shelley Lake.
- 40 -