CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 10 -014
DEPARTMENT OF PUBLIC WORKS
PROJECT: 44th Avenue Pathway Project CONTRACT DATE: 7/20/201C
CONTRACTOR: Red Diamond Construction, Inc CHANGE ORDER NO: 4
CAPITAL IMPROVEMENT PROJECT NO: 0054
BID NO.: 10 -014
DESCRIPTION OF CHANGES
This Change Order provides payment for removing River Rock, placing 2 Inches of CSTC; re- grading and ditching to drain north of the
pathway between 11411 and 11417 E 44th Ave. See attached Change Order 4 Exhibit.
Item No Description Unit Quanti Unit Price Total
CO-4 CRUSHED SURFACING TOP COURSE, 2 IN. DEPTH SY 44 $4.00 $176.00
Total Amount of this Change Order( incl. Tax): $176.00
SUBSTANTIAL COMPLETION
Original Date:
9/3/2010
Prior to this Change Order:
9/3/2010
Including this Change Order:
9/3/201C
Original Working Days:
20
Working Days Added by this CO:
2
Working Days including this CO:
2E
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT PRICE:
ORIGINAL TOTAL CONTRACT AMOUNT $ 270,497.50
.............................................................................................................................. ...............................
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 6,572.26
................................................................................................... ...............................
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $ 277,069.76
..................................... ...............................
NET THIS CHANGE ORDER $ 176.00
.............................................................................................................................. ...............................
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 277,245.76
i
CONTRACTOR ACCEPTANCE: #,oh
The contractor hereby accepts this adjustment under the terms of the original contract for all work perfomed.
RECOMMENDED BY:
APPROVED BY:
APPROVED BY:
Mike
DATE:
ATTACHMENTS:
Distribution:
ORIGINALS TO: Contractor, City of Spokane Valley Clerk's Office, PW Project File
COPIES TO: PW Project File P: Public Works /Purchaing /CO (9/26/2007)