10-139.00 Acme Concrete Paving: Sprague Sullivan PCCP IntersectionS#6g' ane
,,;,0Va11ey
CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 10 -015
DEPARTMENT OF PUBLIC WORKS
PROJECT: Sprague Sullivan PCCP Intersection Project CONTRACT DATE: 7/2/2010
CONTRACTOR: Acme Concrete Paving Inc CHANGE ORDER NO: 7
CAPITAL IMPROVEMENT PROJECT NO: 0065
BID NO.: 10.016
DESCRIPTION OF CHANGES
Item No
Description
Unit
Quantity
Unit ice
Tota
1
Mobilization
LS
1
$500.00
$500,00
9
Remove PCC Curb and Gutter
LF
18
$6.00
$108.00
10
Remove PCC SW / Driveway Approach
SY
10
$7.00
$70.00
41
Cement Concrete Traffic Curb and Gutter
LF
18
$19.00
$342.00
42
Cement Concrete Sidewalk
SY
10
$29.00
$290,00
72
Temporary Traffic Control
LS
1
$500.00
$500.00
73
Sawcut PCC Curb and Gutter or Sidewalk
LF -IN
84
S2.00
$168.00
74
Curb Ramp Detectable Warning Surface
SF
8
$20.00
$160,00
Total Amount of this
Change Order( Incl. Tax):
$2,138.00
Change Order 7 pays for relocation of the north pedestrian ramp at the SE corner of the Intersection. The revised design will align
the crosswalk and pedestrian ramp In conformance with ADA requirements.
SUBSTANTIAL COMPLETION
Original Date: 8/6/2010 Prior to this Change Order; 8/6/2010 Including this Change Order: 8/6/2010
Original Working Days: 15 Working Days Added by this CO: 0 Working Days Including this CO: 15.375
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT PRICE:
ORIGINAL TOTAL CONTRACT AMOUNT _ S,. 635,000.00
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 32,187,59
...... .. _ ............. ..-,,,,... _ .....,,..._. ___.
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $ 867,187.59
NET THIS CHANGE ORDER .... ......... ............ ___ __.,....___............_._..... __ ..._._..__.V..,,,....... - ..,,__$, 2,138.00
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 869,325.69
CONTRACTOR ACCEPTANCE:
The contractor hereby accepts this a
terms or the original contract for all work perfomed.
t
RECOMMENDED BY:
APPROVED BY:
DATE:
DATE: l ' 1 7' f
DATE: fl
APPROVED BY: DATE:
Mike Jackson, Ma ger
ATTACHMENTS;
ORIGINALS TO: Contractor, City of Spokane Valley Clark's Office, PW Project File
I COPIES TO: PW ProleCt File P:Pub':c WodcsiPurchatngrCO ( s/ 2a 2007
r
SPRAGUE AVE_
z
INSTALL 2'x 4' TRUNCATED DOME
CURB TO HAVE 3" REVEAL
AT THIS 5' SECTION
SAWCUTAT
EXISTING JOINT
5'
�m
REMOVE AND REPLACE 18 LF
OF PCC CURB AND GUTTER
SAWCUT 6" EAST OF
6 1 -= / EXISTING JOINT
EXISTING SIDEWALK
REMOVE EXISTING 2'x 5'
o \ / DETECTABLE WARNING
000 �� PATTERN AND REMOVE 10 SY
00 0
INSTALL 10 SY PCC SIDEWALK
/ PCC SIDEWALK
Y/ SE CORNER SIDEWALK DETAIL
/ % CHANCE ORDER #7