Loading...
06-037.00 Eller Corporation: Barker Improvements Boone to Spokane RiverSpokane Valley DEPARTMENT OF PUBLIC WORKS PROJECT: Barker Road Improvements CONTRACT DATE: 4/3/2006 CONTRACTOR: Eller Corporation CHANGE ORDER NO: 2 SCHEDULE A - Barker Road Improvements -Boone Ave. to Spokane River PROJECT NO: 323679.CM SCHEDULE B - South Greenacres Sanitary Sewer Project No. 1036, Phase 2 DESCRIPTION OF CHANGES Credits (unit price reductions) are provided from the Contractor for the following Schedule B bid items to correct bidding errors: - Bid Item #15, Side Sewer Riser 4-Inch; a $3,350.00 credit per each is provided effectively changing the unit price from $3,500.00 to $150.00 per each. (19 quantity x $3,350.00 = $63,650.00 credit) - Bid Item #16, Side Sewer Riser 6-Inch; a $3,400.00 credit per each is provided effectively changing the unit price from 53,600.00 to 200.00 per each. (4 quantity x $3,400.00 = $13,600.00 credit) Total Amount of this Change Order: ($77,250.00) SUBSTANTIAL COMPLETION Original Date: 9/612006 Prior to this Change Order: 9/6/2006 Including this Change Order: 9/612006 ESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE (excluding sales tax): ORIGINAL CONTRACT AMOUNT $ 1,673,984.78 TOTAL PRIOR CHANGE ORDER AMOUNT $ 3,962.70 CONTRACT PRICE PRIOR TO THIS CHANGE ORDER (through CO#2~ $- 1 677,947.48 I NET THIS CHANGE ORDER $ (77,250.00)I CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 1,600,697.48 CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 04-003 CONTRACTOR ACCEPTANCE: ~~' ~ ~ ~ x^"'ZJ ~ ~~ °~ ~ . DATE: ~~~ ~~- Q,~ The contractor hereby accepts this adjustment in performance, Gme, and wmpensation as a final and complete eRuftabae adjustment In full accord and satisfaction of all Past. presets, and future rWbilities originating under arty clause of the Contract by reasoa~ of the facts and circumstances giving rise to this modificalion or by reason of tho cumulative impaU of all previously executed modifications to this contract. The Contractor agrees that the prlCe to thFS change order, including proftt or fco, shall be adjusted to exclude any sigrufxznt sums by which the City of Spokane Valley finds that such price was Irxxeased because the Contractor-furnished cost or pricing data was Fnaeturate, irteomplele or nod aurrCnt ns o! tho datc agret5d upon botvoen ifte Clty Of Spokane Valley and Ehe Convector. RECOMMENDED BY: DATE: ~ ?.o O>~, DATE: ~ /9 Z~ •~ APPROVED B/:~ ~ /~~- 'CG~c, Spokane CQUnty APPROVED BY: ~~ ,/ DATE: APPROVED BY: -~ ! @.~ DATE: 31 O City t,Aanaget ATTACHMENTS: Dlstrrbution: ORIGINALS TO: Contractor, City of Spokane Valley Clerk's Office, PW Project File COPIES TO: CH2M HILL Project Manager, CH2M HILL Resident Observer, Spokane County P:PWJFarmsrremplatesJCO (Apr 06) COF~-37