Loading...
06-087.00 Eller Corporation: Barker Improvements Boone to Spokane RiverScrr,O~ne ..: . p Valley DEPARTMENT OF PUBLIC WORKS i ~r: CHANGE ORDER TO CONSTRUCTION CONTY2ACT NO: 04-003 (PROJECT: Barker Road Improvements CONTRACT DATE: 413!2006 I CONTRACTOR: Eller Corporation CHANGE ORDER NO: 9 (SCHEDULE A - Barker Road Improvements -Boone Ave. to Spokane River PROJECT NO: 323679.CM I SCHEDULE B - South Greenacres Sanitary Sewer Project No. 1036, Phase 2 DESCRIPTION OF CHAN Schedule A: Provide 24VDC irrigation system controllers instead of the specified 110VAC controllers at the three storm drainage infiltration ponds. This change causes the following credits: Delete Avista electrical service connection: $889.70 credit Delete applicable electrician costs: $1,700.00 credit Total Amount of this Change Order: $2,589.70 SUBSTANTIAL COMPLETION Original Date: 9!612006 Prior to this Change Order: 916!2006 Including this Change Order: 9/6/2006 ESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE (excluding sales tax): ORIGINAL CONTRACT AMOUNT $ TOTAL PRIOR CHANGE ORDER AMOUNT $ CONTRACT PRICE PRIOR TO THIS CHANGE ORDER {thru CO#8) $ NET THIS CHANGE ORDER $ CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 1,673,984.78 {50,678.67 1,623,306.11 (2,589.70 1,620,716.41 CONTRACTOR ACCEPTANCE: l.~c.~ ~r DATE: I j (D 0 v The contractor hereby accepts this adjustment in performanco, e, . nd compensation as a final and wmpleie equitable adjustment in tali accord and saUSfactl n of ag past, present, and future Ilabflldes originating under anydause of tho Contract by reason or ttte facts and circumstances giving rise ro this modification or by reason o! the cumufatlve Impact of all prevlousfy executed modifications to this contract. The Contractor agrees (hat the price to this change order, including profit or fee, shall be adjusted to exclude any signlflcant sums by which the City of Spokane Valley fmds that such price Has inueased because the Contractor-famished cost or pricing data was inaowr84e, incomplete or not current as of the date agreed upon betvreen the Ciry of Spokane Valley and the Contractor. RECOMMENDED BY: ~ - -_-_. for (Consultant) ACCEPTED BY: Not Applicable (Req'd for Schedule B Changes) Mark Stiltz, Spokane County Project hAanager APPROVED BY: DATE: ~ Ir, C7 ~ ?~~~ DATE: DATE: APPROVED BY: L City Manager DATE: U ~ f '?' O ~ ATTACHMENTS: Distribution: ORIGINALS TO: Contractor, City of Spokane Valley Clerk's Office, PW Project File COPIES TO: CH2A4 HILL Project Manager, CH2M HILL Resident Observer, Spokane County P:PW1Formslremplate,JCO {Apr 06) C06-87