08-096.00 Knife River: Appleway Ave Reconstruction
Washington State
Department of Transportation
Change Order 6
Date August 2, 2008
'aoe 1 of 3 Paaes
Contract Number TA-2922
Federal Aid Number STPUL-3842 (002)
Contract Title Appleway Avenue Reconstruction Project
Change Order Number 6
Prime Contractor Knife River
Q"Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications
^ Proposed by Contractor
Endorsed Surety Consent
Contras Attorney of Fact
g rr o ~
Data Dat®
Original Contract Amount 8 4,565,859.95
¢, 7'96, X1.2.57 8~--
Current Contract Amount $,4,~9~1~$:~
Estimated Net Change This Change S 1,912.16
798, 75~ ~ 73 ~
Estimated Contract Total After Change 8~'3+~;336~3
Approval Required Region ^ Olympia Service Center ~ocal Agency
If the amount authorized in the Local Agency Agreement is exceeded and federal funds are not available for this
change, the Local Agency will assume the total cost of this Change Order.
X App al Recommended ^Approved Approved
Project Engineer
g ~ og Approvin uthority per C.A. Agreement
Date Date
Approval Recommended Approved Appr
By pproving uthority per C.A. Agreeme
Date Date
C08-96,
CHANG ~ ORDER
Page 2 of 3
Contract No: TA-2922
This Contract is revised as follows:
Description of Work
Change Order No. 6
An electrical meter will need to be provided and installed and the main power supply
energized for the irrigation controller on the Appleway Project. Aztech Electric, the
electrical subcontractor on the project can provide a meter and make the proper
connections to the irrigation controller. The installation of the meter and providing
power to the irrigation system was not included in the plans and specifications.
Materials
The Materials shall meet the requirements of the 2006 Standard Specifications and the
attached Special Provisions.
Construction Requirements
Work shall meet the requirements of the 2006 Standard Specifications and the attached
Special Provisions.
Measurement
"Electrical Service Connection for Irrigation Controller", Lump Sum.
Payment
"Electrical Service Connection for Irrigation Controller", Lump Sum.
CHA-~iGE ORU~R
Page 3 of 3
Contract No: TA-2922
Item No. Item Description
Change Order No. 6
Unit Unit Price Est. Qty. Est. Amt..
Measure Change Change
N/A INSTALL ELECTRICAL METER
CONTRACTOR MARKUP (12%)
LS $1,707.29
1 $1,707.29
S 204.57
TOTAL $1,912.16