08-096.00 Knife River: Appleway Ave Reconstruction Washington State Department of Transportation Change Order 6 Date August 2, 2008 'aoe 1 of 3 Paaes Contract Number TA-2922 Federal Aid Number STPUL-3842 (002) Contract Title Appleway Avenue Reconstruction Project Change Order Number 6 Prime Contractor Knife River Q"Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications ^ Proposed by Contractor Endorsed Surety Consent Contras Attorney of Fact g rr o ~ Data Dat® Original Contract Amount 8 4,565,859.95 ¢, 7'96, X1.2.57 8~-- Current Contract Amount $,4,~9~1~$:~ Estimated Net Change This Change S 1,912.16 798, 75~ ~ 73 ~ Estimated Contract Total After Change 8~'3+~;336~3 Approval Required Region ^ Olympia Service Center ~ocal Agency If the amount authorized in the Local Agency Agreement is exceeded and federal funds are not available for this change, the Local Agency will assume the total cost of this Change Order. X App al Recommended ^Approved Approved Project Engineer g ~ og Approvin uthority per C.A. Agreement Date Date Approval Recommended Approved Appr By pproving uthority per C.A. Agreeme Date Date C08-96, CHANG ~ ORDER Page 2 of 3 Contract No: TA-2922 This Contract is revised as follows: Description of Work Change Order No. 6 An electrical meter will need to be provided and installed and the main power supply energized for the irrigation controller on the Appleway Project. Aztech Electric, the electrical subcontractor on the project can provide a meter and make the proper connections to the irrigation controller. The installation of the meter and providing power to the irrigation system was not included in the plans and specifications. Materials The Materials shall meet the requirements of the 2006 Standard Specifications and the attached Special Provisions. Construction Requirements Work shall meet the requirements of the 2006 Standard Specifications and the attached Special Provisions. Measurement "Electrical Service Connection for Irrigation Controller", Lump Sum. Payment "Electrical Service Connection for Irrigation Controller", Lump Sum. CHA-~iGE ORU~R Page 3 of 3 Contract No: TA-2922 Item No. Item Description Change Order No. 6 Unit Unit Price Est. Qty. Est. Amt.. Measure Change Change N/A INSTALL ELECTRICAL METER CONTRACTOR MARKUP (12%) LS $1,707.29 1 $1,707.29 S 204.57 TOTAL $1,912.16