11-088.00 Spokane Rock Products: Indiana Ave Extension_ e A.0 %
(Ytl'rlf
JL 1iane.
ley CHANGE= ORDER TO CONSTRUCTION CONTRACT NO 11-012
DEPARTMENT OF PUBLIC WORKS CONTRACT DATE: 4119/2011
PROJECT: Indiana Avenue Extension Project P.14ANGE ORDER NO; 6
CAPITAL IMPROVEMENT PROJECT N0; 0112
BID NO,' 11.012 �..
This 00 adds additional days to the contract to settle three claims. it also pays $650 for additional Contractor Surveying Cost resulting
from City Survey error. See 3 attached SRP letters dated 6128111, 6128111 & 711!11 and North Englneerlpg Standby Time Spreadsheet.
By signing this Change Order the Contractor agrees to seek no additional time or monetary compansollon for these Issues.
Item No
90 c
CO 6 - A
MAY 17 & JUNE 2 WEATHER DAYS
CO 6 - 8.1
JUNE 27 & 28 SURVEY ERROR COST
CO e. 8.2
JUNE 27 & 28 SURVEY ERROR DELAY
CO 6 - C
JULY 6 & 6 AVISTA GAS XING DELAY
gua
uan
JU
t e
791at
DAYS
2.0
$0100
$0.00
LS
110
$498.46
$498.46
DAYS
1.6
$0.00
$0.00
DAYS
2.0
$0.00
Total Amount of this
Change Order( Incl. Tax):
$498.46
SUBSTANTIAL COMPLETION
Original Date: 7/1212011 Prior to thls Change Order; 7115/2011 Including this Change Order: 7/18/2011
.... Fn wniklnn Dave, Added by this CO' 6.6
Working Days Including this CO:
b9A
CHANGER RFSUI -T IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT PRICE' $ 1,049,282.
ORIGINAL TOTAL CONTRACT AMOUNT ...A,. »,;...,.. »......_ . » » -• .., », » - ._. »,., �...,....,
............_..»...,»».. .,..._,......_. .............:.. 87,167
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT
. ».._. ».... � ...............„ ...,....................,, ., 1,136,449
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER _:..,...__. »._,...........�Y
$ 498
NET THIS CHANGE ORD1 =R ,. - " "_ `�
u... . ....................._...._.... __...;:.,... »............... $ 1,136,947
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER
DATE:
CONTRACTOR ACCEPTANCE
The contractor hereby accepts this adjustment under the terms of the ortglnsl contract for all v+ork psrfomed.
Indiana Avenue Extension Project
CIP 0112
Change Order 6
North Engineering Standby Time on June 27 Survey Problem Resolution
Personnel Hours Rate Cost
Professional Land Surveyor 2 $110.00 $220.00
Party Chief 2 $62.50 $125.00
Total $345.00
29% Labor Markup $100.05
Subcontractor Total $445.05
12 %Prime Contractor Mark -up $53.41
Total Cost $498.46