11-158.00 Solid Structures: Salt Storage BuildingSPO.Kane ,,;0oWX7a11ey- DEPARTMENT OF PUBLIC WORKS CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 11 -027 PROJECT. Salt Storage Building CONTRACT DATE: 1012812011 CONTRACTOR: Solid Structures CHANGE ORDER NO: 2 CAPITAL IMPROVEMENT PROJECT NO: BID NO.: 11 -027 DESCRIPTION OF CHANGES This Change Order pays for the additional concrete required for post placement due to the soil ccnditolns and metal debris excavated per post hole. This includes all additional excavation, concrete and labor Item No Descriptlon Unit uant! Unit Prico Total CO2 Post Concrete LS LS $2,246.83 $2,246.83 Total Amount of this Change Order( Incl. Tax): 52,246.83 THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT PRICE: ORIGINAL TOTAL CONTRACT AMOUNT $ 55,784.84 _ .. ...___........ .. ......... .._.,. _,...._,_..._ . ,..._.__ ....._...... -- TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT 3,303.12 TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $ 59,087.96 NET THIS CHANGE ORDER 2,246.83 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 61,334.79 CONTRACTOR ACCEPTANCE: DATE: %C The contractor hereby accepts this adjustment under the teams of the original contract for all work perfomed. RECOMMENDED BY: -/ &ei 11r, DATE: l% l APPROVED BY: Nell Kersten, PumcL APPROVED BY: City Manager ATTACHMENTS: Distribution: DATE: DATE: ORIGINALS TO: Contractor, City of Spokane Valley Clerk's Office, PW Project File COPIESTO: PWProjectFile P. Pubt :cWorksrpo-:drrng1CO(Mel20'J7) (01( - I Z'd ££ZLLZ£609 63, i-lio iisanos dL0: 60 16 9Z 100 Oct 24 11 10:06a SOLIDSTRUCTURES 5093277233 p.2 Solid Sfructures CH"GE OZWER AGWEEffNT To Original Construction Alzreemertt Each c�� orderto � o �iatiee to Ova conformance vyw the eta Solid ,men# m>$f be m wry and des a � � and is m conditions as specked AU tv�$ SbM be under the same tetras and b weer the Owner and Brander unless otizerwisse stapu]a2ed M tivr it�a Faah +age Order de�7s all s to the tfre Cor�truetiot} A p� The � `�' thai r�esnit in a revision of Price o aim (mm and g��der must 1� is sEa�d bel= r m mete Agreement additional find at the amo= ofthe er and receive verfi�on that buildia c=uw a Off, nor available fiomthe 1 r orhave been deposited in the g bef�e work can. €� started- -- ar.t • a ■ - � • � t . • IA t t t . r _i •=+n vti t .ass t t i tit L. F. lit i. . r - a �� _ , w s.p ••-�:!t i1 concerning the property locate. at: 1 � p o �, E- Eon �� �� ; q of �au� The Builder and the Owner A.UY agr� as follows: 1- Changes in the Work OrighlaW Agreed To Are As Fellows: a M: N��0, 4. ao Grand Tom: ; 5 . R $ roe fete Pro - B (date) CHANGE ORDER ,¢ TMJ Propertks -1 Ovgerfsl "Pro-Val (am) (am) SCITY OF pollne� ,,�oOValleyv Memorandum Date: October 28, 2011 To: Neil Kersten Public Works Department Capital Improvement Program 11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206 509.921.1000 ♦ Fax: 509.921.1008 ♦ cityhatt@spokanevalley.org From: Shane Arlt Q �, Re: Change Order /1 and 2 for Salt Storage Building Change Order 1 is for the addition of 7/16" OSB and felt paper located under the roof material to prevent condensation from dripping from the metal roof. A barrier was not included in the original scope of work. Materials and installation of the vapor barrier is $3,303.12. Change Order 2 pays for the additional concrete required for post placement due to the soil conditions and metal debris excavated per post hole. The design called for .88 yards per post for a total of 17.6 yards. A total of 40.6 yards were used. The additional yardage with tax amounted to $2,246.83. This includes all additional excavation, concrete and labor. Original Contract amount = $55,784.84 Previous Change Order Cost = $0.00 Change Order #1 Cost = $3,303.12 Change OrderJWCost = $2,246.83 '71 Project Cost including Change Orders $61,334.79 Max Public Works Director Contract authority = $75,000.00 Change Order Cost to date = $5,549.95 Remaining P.W. Director Contract Authority after CO #2 $69,450.05 tn _ �� #e Public Worr ector Project Manager Cc: City Mana Fina nce Department