11-169.00 Poe Asphalt Paving: Broadway Ave Safety�
, r
DEPARTMENT OF PUBLIC WORKS
CHANGE ORDER TO CONTRACT NO:
11 -015
I PROJECT: Broadway Ave Safety Project CONTRACT DATE: 7120/2011
CONTRACTOR: Poe Asphalt Pavinq CHANGE ORDER NO: 7
DESCRIPTION OF CHANGES
Adds eleven working days to contract time and pro -rated traffic control due to delays in delivery of traffic signal equipment
Total Amount of this Change Order: $ 7,062.77
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE:
ORIGINAL CONTRACT AMOUNT $ 1,012,469.73
---------------------------------
TOTAL PRIOR CHANGE ORDER AMOUNT $ (35,585.77)
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER (through CO# 6) ----------- - $ 976,883.96
NET THIS CHANGE ORDER $ 7,062.77
---------------------------------
CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 983,946.73
--------------- - - - --
CONTRACTOR ACCEPTANCE: N DATE:
The contractor hereby accepts this adjustment under the terms of the original contract for all work perfomed.
RECOMMENDED BY: DATE:
APPROVED BY:
Neil Karsten, Public
DATE:
APPROVED BY: xIA -, DATE:
Mike Jackson, City M ager
ATTACHMENTS:
Distribution:
ORIGINALS TO: Contractor, City of Spokane Valley Clerk's Office
COPIES TO: PW Project File, City Manager, Finance