13-075.00 Aztech Electric: Sprague/Sullivan ITS glmw okane 4000-Valley. CHANGE ORDER TO CONTRACT NO: 12-035 DEPARTMENT OF PUBLIC WORKS PROJECT: Sprague/Sullivan ITS CONTRACT DATE: 10/16/2012 CONTRACTOR: Aztech Electric, Inc. CHANGE ORDER NO: 1 DESCRIPTION OF CHANGES Conduit obstruction repair and installation of locate wire Total Amount of this Change Order: $ 3,117.08 THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE: ORIGINAL CONTRACT AMOUNT $ 202,531.21 TOTAL PRIOR CHANGE ORDER AMOUNT $ - CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $ 202,531.21 NET THIS CHANGE ORDER $ 3,117.08 CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 205,648.29 CONTRACTOR ACCEPTANCE: DATE: April 25,2013 Todd M. Booth, President The contractor hereby accepts this adjustment under the terms of the original contract for all work perfomed. RECOMMENDED BY: G9 DATE: Z 9 AP2.003 APPROVED BY: .4� DATE: 3—// /is ric Guth,P.E.,Public Works Director APPROVED BY: A-J7/4 DATE: (((( Mike Jackson,City Manager ATTACHMENTS: Distribution: ORIGINALS TO Contractor, City of Spokane Valley Clerk's Office COPIES TO: PW Project File CEO r —076 CHANGE ORDER Page 2 of 4 Contract No: 12-035 Change Order No. 1 This Contract is revised as follows: Description of Work The Contractor shall remove existing locate wire from existing ITS conduit along Sullivan Rd from Sprague Ave to Mission Ave, and furnish and install new#14 USE locate wire in the same conduit. The Contractor shall remove existing sidewalk and damaged conduit as noted on the plans. New 1 1/2" Schedule 80 PVC conduit shall be put in its place, connected to existing conduit and sidewalk placed in accordance with Section 8-14. Materials Locate wire shall comply with the requirements of Section 9-29.3(2)A4. Conduit shall comply with the requirements of Section 9-29.1(4) Measurement No specific unit of measure will apply to the lump sum item, "Add #14 USE Locate Wire." No specific unit of measure will apply to the lump sum item, "Conduit Repair." Payment Payment shall be made for the following items: New contract items: "Add #14 USE Locate Wire," lump sum. "Conduit Repair," lump sum Contract Time There is no change in Contract Time as a result of this Change Order. O M a CD s- CL 0 R O O O O U a) v 4 N C) V Q !A 4.i N W J a 0 l0 1 I- N L 0) a) o) o ca a r rn r N LL N ` d J J ce 0 wn Z U 0 r 0. c) co m E C, 2 a) O O � o � J i W co w D Et Z v .- v a c +L+ QU ■0 l.) Z E ww y Z Z f41 2 1 14 cv vaat Pag 9N 11-0 I VY`i -- .,,,,,`4,a• `NA 2 ,r ___mo-Fge..?s:-Nn1-3.1,vvi 0,- 1 t o 0 r , ____1 c,,,,„ c . m o) 1 ..c cr,___, '',5;..,1 0 o_ 1 o5 1 '...z t------T1 1- 7 .0 1//''' .._., ID I '''''''.2 '..., t• ....y,a• 11.1 .1L---- 1 1 ,.... i 1 i 11 1 •-; -.....-.,,, !„ .a' , V — 5•, P L'i 1 i , ; - : c«el! 1 , , ■ I ' ,•• 1 4 zi. ' I---- • I '''')I: 5,*•,, ,,,,,•E'43.a, ..,, I "•.' I 1 ._ .. _ — , 1 i ii," irii•-,:... ilv:,'',',1:',,,11: ,L;I:t4' - ---1 ..,.. .... $' - •':1 , ,.,,,,.7 x.,...., -, _ „ I 474 i '•, IL, — — — 1 ''•aa': --- —.. L__—.— — — '.-, ,_,,, .__.--- :L. i; , 1 1 E w 1 2,-: P il 5 5 n 1 P '''' 1 0 z, ,..,',.,, ,a,..',. , v 4., . I E !7 - =,. '''.. 1 . ..., — • ',1—. ,L 1'' '-a- - .I,,1' al .•,.. j1 ' , . 7.ri I • . • .,. - a— • .„ ' I '— — • --,,,9 6 `,. 1 11 5c, . , , ,----- "54 I I-' Milillii* e if 1 ----, b,,' 4 1 I P ' -,4-■-•'f .;,t' It ._.\ , . •:1I -,, ‘-• .-i. ..,','i.,s.,4, , I 4,• T3 ,i'5, ,,'''t,'--..- Zi I ........ ; 1 $, ..... I :-, -g, 1. ---- if , I 1 1' i '''1/I i 1 If ZOS_J 338 341H3IVIN 3),,08V 3_13^2.N I aiNiei Il .?:. t....,-, z-,,.. 7.,,,' ;"....,I; 6•<"..44', .'..-. Ii,_,. •,... . ,., a Ig .-.. ECOPY cr Y of Public Works Department SP okane Capital Improvement Program • Valley® -11707 E Sprague Ave Suite 106 • Spokane Valley WA 99206 509.921.1000 • Fax: 509.688-0261 • cityhall®spokanevalley.org Change Order Memorandum Date: April 30,2013 To: Eric Guth From: Ken KnutsoVa. Through: Steve M.Worley,Senior CIP Engineer Re: Change Order#1 for Sprague/Sullivan ITS, CIP#0133 Budget Account No. 303.303.133.595.61.41.08 Aztech Electric Contract 12-035 Originally we had intended to re-use the existing locate wire for the fiber optic cable route on Sullivan Rd between Sprague Ave and Mission Ave. While upsizing junction boxes,it became apparent that the existing wire did not meet current standards and could fail to adequately identify the fiber's location. This change order replaces the wiring. While attempting to install a pull string in existing conduit on Sullivan,the Contractor discovered a blockage. Spokane County and WSDOT were able to identify the location. This change order provides for the repair of the conduit. The total estimated cost (incl. tax) for this Change Order work is $3,117.08. There are sufficient funds in the project budget to cover these costs. Note that the CN costs in the Project Expenditures table reflect both Sprague ITS Phase 1 AND the current construction project. Original Contract amount= $202,531.21 Previous Change Order Cost= $ 0.00 Change Order#1 Cost= $ 3,117.08 Project Cost including Change Order#1 = $ 205,648.29 15% of Original Contract amount= $ 30,379.68 Max Public Works Director Contract authority= $ 30,379.68 Change Order Cost to date= $ 3,117.08 Remaining P.W. Director Contract Authority after CO#1 $ 27,262.60 Project Revenues Est.Project Expenditures: ITS Plan- $ 64,800 EECBG Grant $ 420,000 PE - $ 135,200 CMAQ Grant $ 244,425 RW- $ 0 City Match $ 103,696 CN- $ 568,121 Total $ 768,121 Total $ 768,121 cc: Finance Department Clerk's office 4 • Emptoyment Security Department affer WASHINGTON ST.e'+,7t P.O. Box 9046 Olympia, WA 98507-90461 Fax 360-902-9287 CERTIFICATE OF CITY OF SPOKANE VALLEY )PAYMENT OF CONTRIBUTIONS . 11707 E SPRAGUE AVE STE 106 )PENALTIES AND INTEREST ON SPOKANE VALLEY, WA 99206 )PUBLIC WORKS CONTRACT ES Reference#: 31254400 3 • UBI No: 328054758 CONTRACTOR: AZTECH ELECTRIC INC P O BOX 11795 SPOKANE, WA 992.11-1795 • The Employment Security Department hereby certifies those contributions,penalties and interest due from the above named contractor under the Employment Security Act have been paid in full or provided for with respect to the following public works contract: Description: SPRAGUE/SULLIVAN ITS PROJECT. Contract number: 12-035 The Employment Security Department hereby certifies that it has no claim pursuant to RCW 50.24.130 against the public body named above for tax attributable to service.performed for said public body by the above named contractor on the above described contract. The Employment Security Department releases its lien on the retained percentage which is provided by RCW 60.28.040 for contributions, penalties and interest due from said contractor. This certificate does not release said contractor from liability for additional contributions, penalties and interest which may be later determined to be due with respect to the above mentioned contract. Dated at Olympia, Washington on October 17, 2013. EMPLOYMENT SECURITY DEPARTMENT By Robyn R. Wells Authorized Representative Original - Disbursing Officer Duplicate - Employer Triplicate - Central. Office Files ,01. —075