13-139.00 MDM Excavation: Regional Decant Facility Ph 10 t f CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 13 -033 DEPARTMENT OF PUBLIC WORKS PROJECT: Spokane Valley Regional Decant Facility - Phase 1 CHANGE ORDER NO: 1 - ONTRACTOR: MDM Construction, Inc. dba MDM Excavation CONTRACT DATE: 19- Jun -13 PROJECT NO: 0173 PO #: L)LbUKIF l IUN Ur l+rlANIaCJ Change Order #01 allows the contractor to complete Stage 2 work before Stage 1 begins. Relieves the Contractor from completing Stage 1 within 5 working days of the overall project Notice to Proceed and relieves the Contractor from completing Stage 2 within 10 days of Notice to Proceed. (See General Special Provisions 1 -08.4) Does not relieve the Contractor from completing the Stage 1 work within 5 working days once started. Item No Description Unit Quantity Unit Price Total Total Amount of this Change Order: $ - SUBSTANTIAL COMPLETION Original Date: 6/28/2013 Prior to this Change Order: 8/9/2013 Including this Change Order: 8/9/2013 Original Working Days: 30 Working Days Added by this CO: 0 Working Days including this CO: 0 THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE: ORIGINAL TOTAL CONTRACT AMOUNT _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ $_ 147,893.09 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT _ - $ 0.00 ---------- - - - - - - TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER (through CC,# _ _ $ 147,893.09 NET THIS CHANGE ORDER $ - 0.00 -------------------------------- TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 147,893.09 CONTRACTOR ACCEPTANCE: DATE: L(3 The contractor hereby accepts this nder the terms of the original contract for all work performed. RECOMMENDED BY: DATE: `ZCQ i o�ect Manager / APPROVED BY: DATE: c Guth, Public Works Director APPROVED BY: l7 DATE: Mike Jackson, City Manager ATTACHMENTS: Distribution: ORIGINALS TO: City of Spokane Valley Clerk's Office, Contractor COPIES TO: PW Proiect File, Finance dept __