13-188.00 MJ Hughes Construction: Sullivan UP Tracks Bridge Deck Resurfacing6kane ,;o0wValley . CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 13 -019 DEPARTMENT OF PUBLIC WORKS PROJECT: Sullivan Rd UP Tracks UC (SB) Bridge #4507 Deck Resurfacing Project CHANGE ORDER NO: 1 CONTRACTOR: MJ Hughes Construction CONTRACT DATE: 7/17/2013 PROJECT NO: 0175 PO #: 43112 DESCRIPTION OF CHANGES 1. Provides for the addition of two (2) days to Contract Time required by the use of Force Account on Item #7, "Force Account Forms for Full Depth Deck Repair." 2. Provides for the addition of two (3) days to Contract Time required by the use of Force Account on Item #8, "Further Deck preparation." 3. Provides for the use of a Contractor - proposed revision in curing method for Item #11, "Finishing and Curing Modified Concrete Overlay," at no additional cost. Total Amount of this Change Order: 0.00 SUBSTANTIAL COMPLETION Original Date: 8/30/2013 Prior to this Change Order: 8/30/2013 Including this Change Order: 9/9/2013 Original Working Days: 15 Working Days Added by this CO: 5 Working Days including this CO: 20 1 THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE: ORIGINAL TOTAL CONTRACT AMOUNT $ 148,873.00 --------------------------- TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 0.00 --------------- - - - -- TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $ 148,873.00 NET THIS CHANGE ORDER $ 0.00 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 148,873.00 CONTRACTOR ACCEPTANCE: �j�._ . DATE: The contractor hereby accepts this adjustment under the terms of the origin contract for all work performed. RECOMMENDED BY: APPROVED BY: APPROVED BY: ATTACHMENTS: Distribution: ORIGINALS TO: City of Spokane Valley Clerk's Office, Contractor COPIES TO: PW Project File, Finance dept Page 1 of 2 DATE: yl U cr / 3 DATE: / Z 3 i DATE: • ii CHANGE ORDER Page 2 of 2 Contract No: 13 -019 Change Order No. 1 This Contract is revised as follows: Section 6- 09.3(6)B is supplemented with the following: Contract Time Two (2) days shall be added to the Contract Time as a result of Force Account Forms for Full Depth Deck Repair work. Section 6- 09.3(6)C is supplemented with the following: Contract Time Three (3) days shall be added to the Contract Time as a result of Further Deck Preparation work. Section 6- 09.3(13) is supplemented with the following: Description of Work The Contractor may use UltraCureDOT blankets to cure the modified concrete overlay. Measurement and Payment This is a no cost Change Order. Bid Schedule ITEM# ITEM DESCRIPTION UNITS QTY PRICE/UNIT TOTAL 1 MOBILIZATION L.S. 1 L.S. 4 qoo O V 2 SPCC PLAN L.S. 1 L.S. 00o , o J 3 PROJECT TEMPORARY TRAFFIC CONTROL L.S. 1 L.S. 0 d O 4 STRUCTURE SURVEYING L.S. 1 L.S. 9 S A ©o 5 REMOVING EXISTING CONCRETE OVERLAY S.Y. 370 / U 57 D D 2,q w;b, Ue) 6 SCARIFYING CONCRETE SURFACE S.Y. 370 -71,0(0 U �76,f 00 7 FORCE ACCOUNT FORMS FOR FULL DEPTH DECK REPAIR EST. 1 500.00 500.00 8 FURTHER DECK PREPARATION EST. 1 25,000.00 25,000.00 9 EXPANSION JOINT PREPARATION L.F. 113 30,0() -3 3 6 0 00 10 MODIFIED CONCRETE OVERLAY C.F. 560 , �0 "E 0 0 11 FINISHING AND CURING MODIFIED CONCRETE OVERLAY S.Y. 370 �Qj. D© Z� 0 12 PAINT LINE L.F. 122 /� 50 (' oO Total TOTAL (in Words): (W, bU il ree dD Person /Entity Name: Michael Hughes Signature Of Bidder: Company: MJ Hughes Construction Date: 6128113 City of Spokane Valley Bid Proposal Documents Sullivan Road UP Tracks UC (SB)- Bridge #4507 Deck Re- Surfacing Project Bid Ho: 13 -0I9