13-189.00 West Company: Sullivan Bridge Drain Retrofit *Mane
Valleyy CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 13-002
DEPARTMENT OF PUBLIC WORKS
PROJECT: Sullivan Bridge Drain Retrofit Project CONTRACT DATE: 9/5/2013
CONTRACTOR: West Company,Inc CHANGE ORDER NO: 3
CAPITAL IMPROVEMENT PROJECT NO: 0150
BID NO.: 13-002
This Change Order pays for furnishing and Installing 2 galvanized Interior Diaphragm Brackets fabricated to the dimensions
shown on the attached plan.
Item No Description Unit Quantltti Unit Pr ce Total
103 Modified Interior Diaphragm Bracket EA 2 $228.57 $457.14
Total Amount of this Change Order(incl.Tax): $457.14
SUBSTANTIAL COMPLETION
Original Date: 9/23/2013 Prior to this Change Order. 10/18/2013 Including this Change Order. 10122/2013
Original Working Days: 20 Working Days Added by this CO: 0 Working Days including this CO: 22
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT PRICE;
ORIGINAL TOTAL CONTRACT AMOUNT _ _ $ 232,918.50
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT __- „ . 18,289.90
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER ___ ___�-__„�„__ „,„, _ 251,208.40
NET THIS CHANGE ORDER 457.14
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 251,665.54
CONTRACTOR ACCEPTANCE: /j7 DATE: /0/444
d'ustment under the terms of the original cofor all work perfomed.
The contractor hereby accepts this adjustment
RECOMMENDED BY: "� DATE /V'22`r 3
APPROVED BY: ' ' DATE: /O/zq//3
ubilc Works
APPROVED BY: //M DATE:
City Manager
ATTACHMENTS: None
Distribution:
ORIGINALS TO: Contractor,City of Spokane Valley Clerk's Office,PW Project File
COPIES TO: PW Project File P:Publ:e works/Purche'ngrCO(snsaoorl
( O►"3—I 89
Nate
Subject: FW:City of Spokane Valley-Quote for Drain Supports
Attachments: Added Angles(2) - Revised jpg;_Certification_.htm
Importance: High
From:Todd E. Weaver[mailto:Toddw @metalsfab.coml
Sent:Tuesday, October 22, 2013 11:18 AM
To: 'Nate'
Cc: Kenb @metalsfab.com;jp(ametalsfab.com; mattm(ametalsfab.com; Robert Provencio; soencerh @metalsfab.com
Subject: FW: City of Spokane Valley-Quote for Drain Supports
Importance: High
Nate, -II 3573.00 +d `ro 1 = A3ao.LI c
ik$350.00 FOB Metals Fab. -. 38a.V�S t 20%a m.u. = c/S�•SY
Thank you,
,jj.6_JI Todd E.Weaver I President II fr
Metals Fabrication Company
_.Gua r s1,^z
p. 509.244.2909 x 40
METALS FAiiRICATtON f. 509.244.9642
CO M P A N 'r W. www.metaisfab.com
e. toddw@metalsfab.com
Structural Steel Excellence Since 1966
From Nate [mailto:natem @westway.ccl
Sent: Friday,October 18, 2013 1:59 PM
To: 'Todd E. Weaver'
Cc: mattm @metalsfab.com; spencerh @metaisfab.com
Subject: RE: City of Spokane Valley-Quote for Drain Supports
Todd;
The additional 2 angles(3'-0" long and 6"x4"x1/2")were detailed incorrectly in the plans;thus,the ones you made will
not work. The City is requesting a price for 2 new angles to replace these. The 2 new ones are different dimensions,
please see attached detail. The dimension between the inner holes has changed from 14"to 16%"and the overall
length has changed from 3'to 3'-2'A". How much for 2 of these galvanized?
Thanks!
Nate McKinley
(509)939-8533
1
•