13-190.00 Cameron-Reilly: Wellesley Ave & Adams Rd Sidewalks Spokane
Valley- CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 13-022
DEPARTMENT OF PUBLIC WORKS
PROJECT: Wellesley Avenue Sidewalk and Adams Road Sidewalk Project CHANGE ORDER NO: 3
CONTRACTOR: Cameron-Reilly,LLC CONTRACT DATE: 9/16/2013
PROJECT NO: 168 PO#: 43116
DESCRIPTION OF CHANGES
Change Order 3 provides additional contract time to account for the addition of a curb wall at the northeast corner of Wellesley and Moore,additional driveway
removal and replacement at 16019 E.Wellesley along with time delays due to a shallow Century Link fiber optic line that needed to be lowered.
Item No I:, iption Unit Quantity Unit Price Total
TIME ONLY CHANGE ORDER N/A N/A $0.00
Total Amount of this Change Order: $ $0.00
SUBSTANTIAL COMPLETION
Original Date: 10/24/2013 Prior to this Change Order: 10/30/2013 Including this Change Order: 11/7/2013
Prior Working Days: 32.5 Working Days Added by this CO: 6.5 Working Days including this CO: 39
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE:
ORIGINAL TOTAL CONTRACT AMOUNT $ 542,200.00
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 27,392.00
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER(through CO#2) $ 569,592.00
NET THIS CHANGE ORDER $ 0.00
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 569,592.00
CONTRACTOR ACCEPTANCE: Qit.-------------1 DATE: /0 -22 _12
The contractor hereby accepts this adjustment under the\t rms of the original contract for all work performed.
IL
RECOMMENDED BY: 6(41;1 '/ " C14'J_ DATE: 10 Z 3
Project Manager
APPROVED BY: � DATE: /D/Z£/X
Eric Guth,Public Works Director
APPROVED BY: N/A DATE:
Mike Jackson,City Manager
ATTACHMENTS:N/A
Distribution:
ORIGINALS TO: City of Spokane Valley Clerk's Office,Contractor
COPIES TO: PW Project File,Finance dept